TVA CCR Pond Closures Shane Harris, PMP and Nick McClung, PE - - PowerPoint PPT Presentation
TVA CCR Pond Closures Shane Harris, PMP and Nick McClung, PE - - PowerPoint PPT Presentation
TVA CCR Pond Closures Shane Harris, PMP and Nick McClung, PE 3/20/18 Highlights CCR Program Strategic Approach National Environmental Policy Act Post Closure Care Closure Cases John Sevier Bottom Ash Pond Closure by
Highlights
Strategic Approach National Environmental Policy Act Post Closure Care
TVA CCR Pond Closures | 2
CCR Program Closure Cases
John Sevier Bottom Ash Pond – Closure by Consolidation Colbert Ash Pond 4 – Closure in Place
CCR Strategic Approach
TVA CCR Pond Closures | 3
Closure of Wet CCP Facilities
- Types of Ponds:
- Ash Ponds
- Chemical Ponds
- Dredge Cells
- Gypsum Ponds
- Good Alignment with CCR
Rule Compliance
Dry Storage Closure of Wet CCP Facilities Water Treatment & Management Wet-to-Dry CCP Process Conversion CCP Facility Stabilization / Remediation
In order to meet the commitment to convert all wet CCR operations to dry operations, GC established the following 5-step strategy, first prioritizing stability of facilities and then progressing to dry CCR processes.
National Environmental Policy Act (NEPA)
TVA CCR Pond Closures | 4
All federal agencies are to prepare detailed statements assessing the environmental impact of and alternatives to major federal actions significantly affecting the environment.
- Three documents to comply – Environmental
Impact Statement (EIS), Environmental Assessment (EA), and Categorical Exclusion (CE).
- NEPA requires public comment.
- EIS process is about 3 years to complete.
Programmatic NEPA - EIS
TVA CCR Pond Closures | 5
Site Specific NEPA - EA
TVA CCR Pond Closures | 6
- Performed 10 EAs for ponds across TN, KY and
AL.
- Closure-in-place was the selected option.
- Held 10 public meetings for each closure.
- Total time for EIS and EA ~1.5 years.
- TVA is currently performing supplemental EAs for
some of these initial documents.
CCR Rule-Closure Performance Standards
“both methods of closure (i.e., clean closure and closure with waste in place) can be
equally protective”- CCR Rule p.21412
- CCR unit must be closed in a manner that will
control post-closure infiltration
- CCR unit must be closed in a manner that will
preclude the probability of impounding water
- CCR unit must be closed in a manner that will
provide for slope stability
- CCR unit must be closed in a manner that will
minimize the need for further maintenance
- CCR unit must be closed in shortest amount of
time consistent with generally accepted engineering practices
TVA CCR Pond Closures | 7
John Sevier Fossil (JSF) Bottom Ash Pond (BAP)– Closure by Consolidation
TVA CCR Pond Closures | 8
JSF BAP – Stilling Pond
TVA CCR Pond Closures | 9
JSF BAP – Water Decanting
TVA CCR Pond Closures | 10
- Water quality for NPDES permit was met
for duration of the project.
- All water was pumped through the
spillways to Outfall 006.
- Discharge was limited to 10 Million
Gallons per Day.
- Closely monitored for total suspended
solids during decanting of pond water. Also monitored TSS of Holston River (discharge waterway).
- Flow rate was monitored with a flow
gauge.
- Other parameters in the NPDES permit
were monitored weekly when the BAP was discharging.
JSF BAP – Stilling Pond
TVA CCR Pond Closures | 11
Removal of Fly Ash from Stilling Pond
JSF BAP – New Dike
TVA CCR Pond Closures | 12
Clay being placed for division of closed in place portion from the removed portion.
JSF BAP – Before Closure
TVA CCR Pond Closures | 13
JSF BAP – Preparation for Liner
TVA CCR Pond Closures | 14
JSF BAP – Liner Placement
TVA CCR Pond Closures | 15
JSF BAP – Closure Complete
TVA CCR Pond Closures | 16
COF Ash Pond 4 – Closure in Place
TVA CCR Pond Closures | 17
Placed in service in the 1970’s. Initially received both fly and bottom ash but once the baghouse was added only bottom ash was sluiced to the pond. Upstream construction done in the early 1980’s. Approximately 25,000 tons per year of bottom ash was sluiced to the pond. Estimated 3.2 MM tons of ash in the pond.
History and operation
COF Ash Pond 4 –Closure in Place
- Bottom ash relatively free draining
- Good soil source close by
- Only half of pond (52 acres) held water
TVA CCR Pond Closures | 18
Highlights Hard Spots
- Seismic improvements needed
- Sump flows from plant continue
- Creek adjacent to pond
- “Phantom” oil and grease
- Creating appropriate grades over long
distances
COF AP4 Closure – Seismic Remediation
TVA CCR Pond Closures | 19
4100 Manitowoc Crane 4 gang auger DMM Wall
COF Ash Pond 4 – Sump Flow Re-route
TVA CCR Pond Closures | 20
CYROP New discharge line Previous discharge point Previous Sump discharge point into pond New sump discharge point into CYROP
To Plant To Plant
COF Ash Pond 4 – Cane Creek
TVA CCR Pond Closures | 21
Creek less than 50’ from toe in some areas Widening of working platform and revetment Close proximity to Cane creek was not only a physical constraint but diligence to prevent any fuel or oil releases was a constant threat.
COF Ash Pond 4 – Water handling
TVA CCR Pond Closures | 22
- Still had to meet NPDES permit requirements
during de-canting operations.
- PH, TSS, oil & grease without the benefit of
large volume of water.
- Utilized a lake tank. 600,000 gallon capacity
- Batched water. Once parameters were met,
pumped to CYROP.
- First third took minimal effort. As we got
lower, increased additives were needed.
- Operation went on for most of the duration of
project.
Water quality
COF Ash Pond 4 – Closure Grades
TVA CCR Pond Closures | 23
COF Ash Pond 4 – Pore water readings
430.00 435.00 440.00 445.00 450.00 455.00 460.00 COF_P4_PZ1 COF_P4_PZ11 COF_P4_PZ14 COF_P4_PZ15 COF_P4_PZ4 COF_P4_PZ7 COF_P4_PZ9 COF_PZ4_16S Initial 3’ draw down Closure Construction
TVA CCR Pond Closures | 24
Post-Closure Care
TVA CCR Pond Closures | 25
- Maintenance and
Liner Care Groundwater Monitoring Geotechnical Instrumentation