The Design and Monitoring of Geotextile Tube Use in CCR Impoundment - - PowerPoint PPT Presentation

the design and monitoring of geotextile tube use in ccr
SMART_READER_LITE
LIVE PREVIEW

The Design and Monitoring of Geotextile Tube Use in CCR Impoundment - - PowerPoint PPT Presentation

The Design and Monitoring of Geotextile Tube Use in CCR Impoundment Closure Christopher M. Gee, Dominion Energy Scott Sheridan, Geosyntec Consultants CONFIDENTIAL Chesterfield Power Station Lower Ash Pond 2 2 Layout of the Lower Ash Pond


slide-1
SLIDE 1

CONFIDENTIAL

The Design and Monitoring of Geotextile Tube Use in CCR Impoundment Closure

Christopher M. Gee, Dominion Energy Scott Sheridan, Geosyntec Consultants

slide-2
SLIDE 2

22

Chesterfield Power Station

Lower Ash Pond

slide-3
SLIDE 3

3

Layout of the Lower Ash Pond (LAP)

Area 1 Operational Pool Ash Management Operations

slide-4
SLIDE 4

4

 Dominion wanted to start the Intermediate Water Management Plan (IWMP) for the Lower Ash Pond (LAP) while continuing the operate the pond

– Initially, Dominion desired to implement the IWMP by December 2018 – Chesterfield Power Station needed to continue sluicing CCRs to the Lower Ash Pond through December 2017 while the station was being converted from wet to dry ash handling

  • Design Consideration - One of the VPDES limit for the operating pond was TSS
  • The IWMP needed to control sediment runoff from the filling of Area 1

 Initial Approach – Use of Sheet Piles Walls

– Sheet piles required a platform for access, 50 ft – Concern with embedment depths including possible impacts to underlying natural soils.

 How could the IWMP target date be met? Geotubes  Design Considerations for Using the Geotubes

– Safety during installation – Environmental compliance must be maintained during installation – Stability during and after installation

4

Why the Use of Geotubes was Selected?

slide-5
SLIDE 5

5

Layout of the Lower Ash Pond (LAP)

Area 1 Operational Pool Ash Management Operations

slide-6
SLIDE 6

6

Field Investigations

SPT (2015) CPT (2015) FFP (2016)

slide-7
SLIDE 7

7

Geotechnical Investigation

Coal Combustion Residuals Alluvium Stronger Cretaceous Sediments

Full flow penetrometer ball tip pressure (psf) CPT cone tip pressure (tsf)

20,000 100

CPT sleeve friction (tsf)

4

Field SPT N- values (bpf)

40

slide-8
SLIDE 8

8

Sheet Pile Wall Concept

30

slide-9
SLIDE 9

9

Geotextile Tube Wall Concept

 Construct a geotextile tube wall between Area 1 and pool side  Fill geotextile tubes with ash dredged from the operational pool  Geotextile tubes will act as a gravity structure to improve stability while fill is placed on land side  Geotextile tubes provide BMP for maintaining compliance with discharge permit during filling and grading in Area 1.

slide-10
SLIDE 10

10

Polymer Laboratory Testing

 Bench-scale testing with multiple polymers and multiple dosages  Goal: identify polymer that will most improve the dewatering process

slide-11
SLIDE 11

11

Slope Stability Analysis

slide-12
SLIDE 12

12

Stability of Construction of Geotextile Tube Wall Pad

slide-13
SLIDE 13

13

Stability of Construction of Geotextile Tube Wall

Critical Cross Section Construction Condition Cumulative Geotextile Tube Filling Height (ft) Calculated FS (min. 1.3) Target FS Met Target FS? C First geotextile tube layer, first filling 2 1.30 1.3 Yes C First geotextile tube layer, second filling 5.5 1.32 1.3 Yes C Second geotextile tube layer, first filling 8.5 1.30 1.3 Yes C Second geotextile tube layer, second filling 11 1.31 1.3 Yes B Placement of final cover with 5 ft

  • f stockpile

11 1.36 1.3 Yes B Placement of final cover with 5 ft of stockpile – long-term conditions 11 1.74 1.5 Yes

slide-14
SLIDE 14

14

Construction of Geotextile Tube Wall

Lesson Learned

  • Provide additional positive slope, anticipating settlement and construction impacts, for

liner to reduce ponding at tubes while filling.

slide-15
SLIDE 15

15

Construction of Geotextile Tube Wall

Lesson Learned

  • Provide additional grading behind the geotubes for stormwater control under

varying conditions, keeping in mind the tubes act as a dam.

slide-16
SLIDE 16

16

Construction of Geotextile Tube Wall

Lessons Learned

  • Polymer dosing can be highly variable during the dredging operations, so a

thorough monitoring plan that provides the ability to adjust dosing is necessary.

slide-17
SLIDE 17

17

Pore Pressure Monitoring

Lessons Learned

  • Provide adequate space for

piezometer readouts so they are not too close to the geotubes for future monitoring

  • Strong communication of

monitoring program and expectations.

Design Engineer Input Design Engineer Input

slide-18
SLIDE 18

18

18

Aerial View of Post Construction Condition of Geotextile Tube Wall Construction

Geotextile Tube 2 Geotextile Tube 1

slide-19
SLIDE 19

19

19

Post Construction Gradation of Ash in Tubes

slide-20
SLIDE 20

20

20

Post Construction %Moisture of Ash in Tubes

slide-21
SLIDE 21

21

 A thorough monitoring plan is needed to track the dosing rate.  Stormwater controls should be considered under varying conditions.  On this project, pore pressures dissipated quicker than expected.  The geotubes provided effective separation between construction and

  • perations.

 The structural fill was placed successfully within Area 1 without any compliance or stability issues.  The condition of the ash in the geotubes may or may not vary, depending on the variable of dosing, runoff control, filling sequence, and time.  Geotubes were more cost-effective than sheet pile wall installation.

21

Lessons Learned / Effectiveness