Transmission planning and investment Richard Khoe October 2018 - PowerPoint PPT Presentation

Transmission planning and investment Richard Khoe October 2018 aer.gov.au 1 Objective of the RITs Transmission assets are long-lived and expensive need a rigorous and transparent process to reduce risk that consumers will pay for


  1. Transmission planning and investment Richard Khoe October 2018 aer.gov.au 1

  2. Objective of the RITs • Transmission assets are long-lived and expensive – need a rigorous and transparent process to reduce risk that consumers will pay for inefficient assets. • RITs are a cost-benefit analysis performed by a TNSP prior to investing. • Start with a need on the transmission network, consider net benefits to the market. • Consultation helps identify credible alternatives. 2 aer.gov.au

  3. Relevant aspects of RITs • Interplay with revenue setting process – RITs focus on the options for meeting the network need – AER revenue setting focuses on efficient revenues for regulatory control period. • Timing – Robust modelling does take time – Rigorous consultation does take time – High cost, long-lived sunk assets 3 aer.gov.au

  4. ISP • ISP offers an important NEM-wide perspective on developing the transmission network. • AER welcomes consideration and feedback on the options for converting the ISP into an actionable strategic plan. 4 aer.gov.au

  5. Approach to the ISP Key criteria for testing options: 1. Protect consumers from funding inefficient investments through a rigorous cost benefit analysis. 2. All credible options, including non-network options like DER need to be assessed fairly. 3. Consumers want to be part of the process. They need to have confidence that costs they may have to pay for are tested through a robust and transparent process. 5 aer.gov.au

  6. RIT Guidelines Process • Draft guidelines include guidance on how RIT-T proponents might include aspects of the ISP into a RIT. • Review is under the current regulatory framework. • If the COGATI process changes the overall framework to make the ISP actionable the RIT Guidelines may need to be amended. 6 aer.gov.au

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.