Long-Term Electricity Transmission Inquiry Overview of BC - - PowerPoint PPT Presentation

long term electricity transmission inquiry
SMART_READER_LITE
LIVE PREVIEW

Long-Term Electricity Transmission Inquiry Overview of BC - - PowerPoint PPT Presentation

B1-2 Long-Term Electricity Transmission Inquiry Overview of BC Transmission Corporation' Planning April 17, 2009 S ECTION 5 T RANSMISSION I NQUIRY E XHIBIT Overview of Presentation BCTC Who we are What we do Transmission


slide-1
SLIDE 1

Long-Term Electricity Transmission Inquiry

Overview of BC Transmission Corporation' Planning

April 17, 2009

B1-2 SECTION 5 TRANSMISSION INQUIRY EXHIBIT

slide-2
SLIDE 2

2

Overview of Presentation

BCTC

  • Who we are
  • What we do

Transmission planning today Transmission planning for 2040

slide-3
SLIDE 3

3

About BC Transmission Corporation

BC’s Independent Transmission Company:

Established in 2003 Crown corporation, 100%

government-owned

Responsible for planning,

constructing, operating and maintaining the Province’s publicly

  • wned electrical transmission

system

Plan the long-term expansion of the

transmission system

slide-4
SLIDE 4

4

Planning the System

Interconnect new generation Maintain reliability Meet growth

slide-5
SLIDE 5

5

The Transmission System in BC

System Snapshot:

18,336 km of transmission lines (60

kV - 500 kV)

291 switching, distribution and

capacitor stations

1 primary control centre and one

backup control centre

169 microwave and fibre-optic sites 75,000 hectares of right-of-way Interconnected to Alberta and

the Pacific Northwest

slide-6
SLIDE 6

6

Planning Objectives

Provide cost-effective, safe and

reliable transmission in a socially and environmentally responsible manner

Serve Firm Load Connect Generation Meet Point To Point Obligations Manage Uncertainty

slide-7
SLIDE 7

7

Planning Uncertainties

Timing, location and size (capacity) of

generation additions

Timing, location and size of demand

for electricity

Long lead times for design, approval

and construction of new high voltage transmission lines - e.g. new transmission lines may take 7-10 years to go through the design, approval and construction process while some types of generation only take a couple of years

slide-8
SLIDE 8

8

Planning Challenges

Most Transmission facilities were built between 1940-1980

Many facilities are reaching their capacity

limits

Some assets are reaching the end of their

useful lives

A Unique System

Rough Terrain Regionally dispersed Challenging climate

slide-9
SLIDE 9

9

Transmission Planning Process

  • BC Hydro Network

Integrated Transmission Service Application (Long- Term Acquisition Plan Load Forecast & Resource Plan)

  • Fortis Wheeling Agreement
  • Interconnection requests
  • Point to Point Requests
  • Model system under various

scenarios and evaluate performance using North American Electric Reliability Corporation and Western Electricity Coordinating Council criteria

  • If upgrade is required, identify

and evaluate alternatives to upgrade the system to provide the required capacity

  • Project included in BCTC’s

Capital Plan

  • Project initiated to conduct

detailed planning studies, conduct consultation and

  • btain required regulatory

approvals

slide-10
SLIDE 10

10

BCTC-BC Hydro Planning Process

BC Hydro BC Hydro/BCTC BCTC

LTAP & CRPs NITS Application BC Hydro RRA NITS Study BC Hydro Inputs: Load & Resource Plans BCTC: System Studies NITS Agreement Transmission Revenue Requirement Application BCTC Capital Planning Process BCTC Capital Plan

BCUC Review

slide-11
SLIDE 11

11

BCTC Capital Plan

10 year Plan

  • Describes investments required to meet load growth, interconnect new

generation, and sustain and operate the transmission system

100 200 300 400 500 600 700 800 900 1000 F2005 F2006 F2007 F2008 F2009 F2010 F2011 F2012 F2013 F2014 F2015 F2016 F2017 F2018 F2019

Fiscal Year $M

Growth Sustain BCTC

Plan Total : $5.3 billion over 10 years

slide-12
SLIDE 12

12

BCTC Planning Processes

Long-Term Transmission Vision:

New process Provide 30 year perspective on transmission

needs, technology and investments required to sustain the transmission system

Developed new Long-term Planning tool to

model a variety of scenarios

Informed by outcomes of Commission’s

Inquiry

slide-13
SLIDE 13

13

Long-Term Electricity Transmission Inquiry Inquiry Provides:

An open forum for public input and debate Opportunity to identify “need” earlier in the

planning process

Ability to take a provincial perspective Alignment with regional planning initiatives

slide-14
SLIDE 14

14

Integrating Inquiry Outcomes

Transmission 2040: BCTC’s Long-term Transmission Vision 10 Year Capital Plan Approved Projects Broad 30 Year Perspective – high level planning looking at location, volume & timing of needed 230 and 500 kV transmission enhancements 10 Year Project Outlook – more detailed planning studies including power flow modeling system stability and voltage studies Inquiry results

slide-15
SLIDE 15

15

For Additional Information

New BCTC website focused on Long-term Planning: www.bctransmission2040.ca F2010 Capital Plan (includes State of the Transmission System Report): www.bctc.com/regulatory_filings and/or www.bcuc.com Inquiries: info@bctransmission2040.ca or 604-699-7456