long term electricity transmission inquiry
play

Long-Term Electricity Transmission Inquiry Overview of BC - PowerPoint PPT Presentation

B1-2 Long-Term Electricity Transmission Inquiry Overview of BC Transmission Corporation' Planning April 17, 2009 S ECTION 5 T RANSMISSION I NQUIRY E XHIBIT Overview of Presentation BCTC Who we are What we do Transmission


  1. B1-2 Long-Term Electricity Transmission Inquiry Overview of BC Transmission Corporation' Planning April 17, 2009 S ECTION 5 T RANSMISSION I NQUIRY E XHIBIT

  2. Overview of Presentation � BCTC Who we are • What we do • � Transmission planning today � Transmission planning for 2040 2

  3. About BC Transmission Corporation BC’s Independent Transmission Company: � Established in 2003 � Crown corporation, 100% government-owned � Responsible for planning, constructing, operating and maintaining the Province’s publicly owned electrical transmission system � Plan the long-term expansion of the transmission system 3

  4. Planning the System Maintain reliability Meet growth Interconnect new generation 4

  5. The Transmission System in BC System Snapshot: � 18,336 km of transmission lines (60 kV - 500 kV) � 291 switching, distribution and capacitor stations � 1 primary control centre and one backup control centre � 169 microwave and fibre-optic sites � 75,000 hectares of right-of-way � Interconnected to Alberta and the Pacific Northwest 5

  6. Planning Objectives � Provide cost-effective, safe and reliable transmission in a socially and environmentally responsible manner � Serve Firm Load � Connect Generation � Meet Point To Point Obligations � Manage Uncertainty 6

  7. Planning Uncertainties � Timing, location and size (capacity) of generation additions � Timing, location and size of demand for electricity � Long lead times for design, approval and construction of new high voltage transmission lines - e.g. new transmission lines may take 7-10 years to go through the design, approval and construction process while some types of generation only take a couple of years 7

  8. Planning Challenges Most Transmission facilities were built between 1940-1980 � Many facilities are reaching their capacity limits � Some assets are reaching the end of their useful lives A Unique System � Rough Terrain � Regionally dispersed � Challenging climate 8

  9. Transmission Planning Process • Model system under various • Project included in BCTC’s • BC Hydro Network scenarios and evaluate Capital Plan Integrated Transmission performance using North • Project initiated to conduct Service Application (Long- American Electric Reliability detailed planning studies, Term Acquisition Plan Load Corporation and Western conduct consultation and Forecast & Resource Plan) Electricity Coordinating Council obtain required regulatory • Fortis Wheeling Agreement criteria approvals • Interconnection requests • If upgrade is required, identify • Point to Point Requests and evaluate alternatives to upgrade the system to provide the required capacity 9

  10. BCTC-BC Hydro Planning Process BC Hydro LTAP & NITS BC Hydro CRPs � Application RRA � BC Hydro/BCTC NITS Study BC Hydro Inputs: NITS Load & Resource Agreement Plans BCTC: System Studies Transmission BCTC BCTC BCTC Revenue Capital Capital Requirement Planning Plan � Application � Process � BCUC Review 10

  11. BCTC Capital Plan 10 year Plan � Describes investments required to meet load growth, interconnect new generation, and sustain and operate the transmission system Plan Total : 1000 $5.3 billion over 10 years 900 800 700 600 Growth $M 500 Sustain BCTC 400 300 200 100 0 F2005 F2006 F2007 F2008 F2009 F2010 F2011 F2012 F2013 F2014 F2015 F2016 F2017 F2018 F2019 Fiscal Year 11

  12. BCTC Planning Processes Long-Term Transmission Vision: � New process � Provide 30 year perspective on transmission needs, technology and investments required to sustain the transmission system � Developed new Long-term Planning tool to model a variety of scenarios � Informed by outcomes of Commission’s Inquiry 12

  13. Long-Term Electricity Transmission Inquiry Inquiry Provides: � An open forum for public input and debate � Opportunity to identify “need” earlier in the planning process � Ability to take a provincial perspective � Alignment with regional planning initiatives 13

  14. Integrating Inquiry Outcomes Inquiry results Broad 30 Year Perspective – high level planning looking at Transmission 2040: BCTC’s location, volume & timing of Long-term Transmission Vision needed 230 and 500 kV transmission enhancements 10 Year Capital Plan 10 Year Project Outlook – more detailed planning studies including power flow modeling system stability and voltage studies Approved Projects 14

  15. For Additional Information New BCTC website focused on Long-term Planning: www.bctransmission2040.ca F2010 Capital Plan (includes State of the Transmission System Report): www.bctc.com/regulatory_filings and/or www.bcuc.com Inquiries: info@bctransmission2040.ca or 604-699-7456 15

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend