Tender number: 59 CON 1943 Title: The construction of Letaba - Tarentaal 8km 132kV Kingbird line within the Limpopo Operating Unit over a period of 6 months Clarification date: 08 July 2020 Tender Information C3.1 Works information


slide-1
SLIDE 1

Tender number: 59 CON 1943

Title: The construction of Letaba - Tarentaal 8km 132kV Kingbird line within the Limpopo Operating Unit over a period of 6 months Clarification date: 08 July 2020

slide-2
SLIDE 2

Tender Information

  • C3.1 Works information”
  • Type of contract: NEC 3 - ECC
  • Buyer: Motsatsi Magwele
  • Date of Issue: 26 June 2020
  • Clarification date: 08 July 2020
  • Closing date: 27 July 2020
  • Quality Requirements Tender Enquiry – Category 3 requirements – Category 3

criteria; Form A ;QM 58 document; CQP and QCP

  • Quality evaluation to be done after Technical/ Price & BBBEE - only on successful

supplier shortlisted for award.

2020/07/10 2

slide-3
SLIDE 3

Quality Requirements Returnable

1. QM 58 for reference only- NB: do not print and submit; 2. Category 3 Quality requirements - submit listed items; 3. Category 3 Form A –sign and complete Sections A and Section D and return 4. Templates provided -

  • Section C of Quality Criteria– CQP to be completed and returned based on

the NEC document Scope of Work as per template provided;

  • Section D of Quality Criteria - QCP/ITP to be completed and returned

based on the Previous or simulated Task order specific Scope of Work as per template provided;

2020/07/10 3

slide-4
SLIDE 4

Download category 3 Form A from the Quality subfolder

2020/07/10 4

slide-5
SLIDE 5

Contractual requirements

2020/07/10 5

slide-6
SLIDE 6

Quality requirements for the tender (based on new QM 58- Category 3) Section A & B

2020/07/10 6

slide-7
SLIDE 7

Quality requirements Cont’d

2020/07/10 7

slide-8
SLIDE 8

NEC3- ECSC - C3.1 Description of Works (for completing the CQP template)

2020/07/10 8

slide-9
SLIDE 9

Detailed SCOPE of Work- Important for Section C The construction of Letaba - Tarentaal 8km 132kV Kingbird line within the Limpopo Operating Unit over a period of 6 months

The scope of work below to be used in conjunction with the Bill of Quantities:

  • Establishment of facilities on sites;
  • Perform bush clearing along the servitude
  • Conduct soil nominations, foundations and where required foundation design
  • Transporting all material required to pole/line position
  • Testing of pole/tower footing resistance and poles earthing as well as earthing

correction where required

  • Erection of structures/poles

2020/07/10 9

slide-10
SLIDE 10

NEC scope of work continued

  • Installation of all required stays;
  • Poles dressing;
  • Stringing, Regulation, Crossings, Joints; Dampers
  • Line labelling
  • Dismantling of lines (structures and conductor) as indicated on the Bill of

Quantities/Design

  • Closing spans at the substation;
  • Earthing of terminal poles to the substations earth grids.
  • Perform all line tests as indicated on the Bill of Quantities/Design
  • Handing over of the Asset

2020/07/10 10

slide-11
SLIDE 11

NEC Quality contract conditions

  • Quality Control
  • Final Contract Quality Plan must be signed 30 days after contract award by Project

manager;

  • An approved Quality Control Programme/ Plan ( QCP/ ITPP) is to be compiled

prior to task order execution in conjunction with, and to the approval of, the Project Manager.

  • A Quality Check sheet per structure and line section installation is to be developed

and approved by the Project Manager and the CPE.

2020/07/10 11

slide-12
SLIDE 12

Common mistakes made by tenderers on Quality submissions

1. Section A

  • 1. Quality manual structure layout not aligned to latest Standard (2008 or

2015);

  • 2. QMS Procedures incomplete and do no comply with particular ISO clause

elements; Do not copy and paste the ISO standard- inteprete and customise to your business; address all elements of the procedure as per clause requirements

  • 3. Quality policy not signed or not submitted; or does not comply with clause

ISO 9001:2015 -5.3 ( it’s a controlled document must have ref number; revision; authorization date);

  • 4. For Option1- ISO certification scope must be relevant; valid by tender

closing date;

2020/07/10 12

slide-13
SLIDE 13

Common errors when evaluating- cont’d

Section B

1. QMR appointment letter or and CV not submitted; QMR to attend training on QM in the first 12 months after contract award (contract condition) 2. Organogram has no names and signed nor on letterhead- must be a controlled document; 3. Supplier Management procedure not aligned to Clause 8.4 of ISO 9001:2015;

Section C

  • 1. CQP sow not described as in the NEC; project organogram does not include

roles and responsibilities of organogram functions in respect of SOW;

  • 2. Does not add the out-sourced SOW functions/activities; and other CQP

;elements;

2020/07/10 13

slide-14
SLIDE 14

Common errors when evaluating- cont’d

Section D

1. ITP/QCP template not used; 2. If used, sow specific task order is not used (eg; design instead of installation; construction instead of design – Use a Tender SOW Task order); 3. QCP to be based on the scope of work activities- refer to NEC, this tender scope of work has more than 1 QCPs;

Section E

1. Satisfaction surveys not completed by clients; Name of clients- name of project/service- stamp/signature missing; Submit CS survey templates- rather submit reference letter ( name of client- project/service-date); Reference letter from previous clients; 2. Incorrect Form A - old Forms; 3. Form A neither completed not signed and incorrectly marked Form submitted.

2020/07/10 14

slide-15
SLIDE 15

2020/07/10 15

slide-16
SLIDE 16

2020/07/10 16

slide-17
SLIDE 17

When completing CQP & ITP/QCP

  • Complete the scope of work as described on the NEC- ECSC Works

Information ;

  • complete other information as indicated in the Index, some requirements

are not applicable. If any section on CQP not applicable indicate so and reason why.

2020/07/10 17