title the construction of letaba tarentaal 8km 132kv
play

Title: The construction of Letaba - Tarentaal 8km 132kV Kingbird - PowerPoint PPT Presentation

Tender number: 59 CON 1943 Title: The construction of Letaba - Tarentaal 8km 132kV Kingbird line within the Limpopo Operating Unit over a period of 6 months Clarification date: 08 July 2020 Tender Information C3.1 Works information


  1. Tender number: 59 CON 1943 Title: The construction of Letaba - Tarentaal 8km 132kV Kingbird line within the Limpopo Operating Unit over a period of 6 months Clarification date: 08 July 2020

  2. Tender Information • C3.1 Works information” • Type of contract: NEC 3 - ECC • Buyer: Motsatsi Magwele • Date of Issue: 26 June 2020 • Clarification date: 08 July 2020 • Closing date: 27 July 2020 • Quality Requirements Tender Enquiry – Category 3 requirements – Category 3 criteria; Form A ;QM 58 document; CQP and QCP • Quality evaluation to be done after Technical/ Price & BBBEE - only on successful supplier shortlisted for award. 2020/07/10 2

  3. Quality Requirements Returnable 1. QM 58 for reference only- NB: do not print and submit; 2. Category 3 Quality requirements - submit listed items; Category 3 Form A – sign and complete Sections A and Section D 3. and return 4. Templates provided - • Section C of Quality Criteria – CQP to be completed and returned based on the NEC document Scope of Work as per template provided; • Section D of Quality Criteria - QCP/ITP to be completed and returned based on the Previous or simulated Task order specific Scope of Work as per template provided; 2020/07/10 3

  4. Download category 3 Form A from the Quality subfolder 2020/07/10 4

  5. Contractual requirements 2020/07/10 5

  6. Quality requirements for the tender (based on new QM 58- Category 3) Section A & B 2020/07/10 6

  7. Quality requirements Cont’d 2020/07/10 7

  8. NEC3- ECSC - C3.1 Description of Works (for completing the CQP template) 2020/07/10 8

  9. Detailed SCOPE of Work- Important for Section C The construction of Letaba - Tarentaal 8km 132kV Kingbird line within the Limpopo Operating Unit over a period of 6 months The scope of work below to be used in conjunction with the Bill of Quantities: • Establishment of facilities on sites; • Perform bush clearing along the servitude • Conduct soil nominations, foundations and where required foundation design • Transporting all material required to pole/line position • Testing of pole/tower footing resistance and poles earthing as well as earthing correction where required • Erection of structures/poles 2020/07/10 9

  10. NEC scope of work continued • Installation of all required stays; • Poles dressing; • Stringing, Regulation, Crossings, Joints; Dampers • Line labelling • Dismantling of lines (structures and conductor) as indicated on the Bill of Quantities/Design • Closing spans at the substation; • Earthing of terminal poles to the substations earth grids. • Perform all line tests as indicated on the Bill of Quantities/Design • Handing over of the Asset 2020/07/10 10

  11. NEC Quality contract conditions • Quality Control • Final Contract Quality Plan must be signed 30 days after contract award by Project manager; • An approved Quality Control Programme/ Plan ( QCP/ ITPP) is to be compiled prior to task order execution in conjunction with, and to the approval of, the Project Manager. • A Quality Check sheet per structure and line section installation is to be developed and approved by the Project Manager and the CPE. 2020/07/10 11

  12. Common mistakes made by tenderers on Quality submissions 1. Section A 1. Quality manual structure layout not aligned to latest Standard (2008 or 2015); 2. QMS Procedures incomplete and do no comply with particular ISO clause elements; Do not copy and paste the ISO standard- inteprete and customise to your business; address all elements of the procedure as per clause requirements 3. Quality policy not signed or not submitted; or does not comply with clause ISO 9001:2015 - 5.3 ( it’s a controlled document must have ref number; revision; authorization date); 4. For Option1- ISO certification scope must be relevant; valid by tender closing date; 2020/07/10 12

  13. Common errors when evaluating- cont’d Section B 1. QMR appointment letter or and CV not submitted; QMR to attend training on QM in the first 12 months after contract award (contract condition) 2. Organogram has no names and signed nor on letterhead- must be a controlled document; 3. Supplier Management procedure not aligned to Clause 8.4 of ISO 9001:2015; Section C 1. CQP sow not described as in the NEC; project organogram does not include roles and responsibilities of organogram functions in respect of SOW; 2. Does not add the out-sourced SOW functions/activities; and other CQP ;elements; 2020/07/10 13

  14. Common errors when evaluating- cont’d Section D 1. ITP/QCP template not used; 2. If used, sow specific task order is not used (eg; design instead of installation; construction instead of design – Use a Tender SOW Task order); 3. QCP to be based on the scope of work activities- refer to NEC, this tender scope of work has more than 1 QCPs; Section E 1. Satisfaction surveys not completed by clients; Name of clients- name of project/service- stamp/signature missing; Submit CS survey templates- rather submit reference letter ( name of client- project/service-date); Reference letter from previous clients; 2. Incorrect Form A - old Forms; 3. Form A neither completed not signed and incorrectly marked Form submitted. 2020/07/10 14

  15. 2020/07/10 15

  16. 2020/07/10 16

  17. When completing CQP & ITP/QCP • Complete the scope of work as described on the NEC- ECSC Works Information ; • complete other information as indicated in the Index, some requirements are not applicable. If any section on CQP not applicable indicate so and reason why. 2020/07/10 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.