the elizabeth river tunnels project
play

The Elizabeth River Tunnels Project Project Overview and MLK - PowerPoint PPT Presentation

The Elizabeth River Tunnels Project Project Overview and MLK Presentation March 18, 2014 The Design-Build Team Design-Build Joint Venture Skanska USA Civil SE Kiewit Infrastructure Company Weeks Marine Design Team Parsons


  1. The Elizabeth River Tunnels Project Project Overview and MLK Presentation March 18, 2014

  2. The Design-Build Team  Design-Build Joint Venture — Skanska USA Civil SE — Kiewit Infrastructure Company — Weeks Marine  Design Team — Parsons Brinckerhoff — Volkert & Associates  Immersed Tube Tunnel Experience: — Since 1964, installed 74% of the ITT’s in the USA — Installed 52,500 feet in the USA — 19,700 feet of ITT in the Norfolk Area 2

  3. Timeline for Development Timetable Call for conceptual proposals May 2008 Conceptual proposal submittal September 2008 Public Hearings – Independent Review Panel March to June 2009 Positive CTB Recommendation July 2009 Key business points presented to CTB October 2009 Signature of Interim Agreement January 2010 IA Phase 1 - Feasibility Stage January 2010 IA Phase 2 - Development Stage June 2010 Signature of Comprehensive Agreement December 2011 Financial Close / Construction Start April 2012 3

  4. 4 Contract Structure

  5. Scope New Midtown Tunnel Portsmouth Norfolk Rehab Existing MTT MLK Extension Rehab Existing Downtown Tunnels (EB & WB) 5

  6. New Midtown Tunnel  Concrete shell, Immerse Tube Tunnel (ITT)  West bound Tube connecting Norfolk to Portsmouth  Two vehicular lanes and an egress corridor 6

  7. New MTT – Tube Fabrication  Construction in Baltimore due to availability of dry docks  Trial Casting — Demonstrate techniques — Test thermal modeling  Two Casting Cycles — CC 1 – 6 elements — CC 2 – 5 elements  Dimensions (average) — 350’ x 54’ W x 28’ T — 16,000 Tons each 7

  8. New MTT – Tube Fabrication  Construction in Baltimore due to availability of dry docks  Trial Casting — Demonstrate techniques — Test thermal modeling  Two Casting Cycles — CC 1 – 6 elements — CC 2 – 5 elements  Dimensions (average) — 350’ x 54’ W x 28’ T — 16,000 Tons each 8

  9. 9 New MTT – Tube Fabrication

  10. New MTT – Tube Fabrication  Each Element constructed in Segments — Inverts (5 per element) — Interior Walls (5 per element) — Roof (Doghouse) (5 per element)  Formwork Traveler — Progresses from segment to segment — Moving production line 10

  11. 11 New MTT – Tube Fabrication

  12. 12 Conventional Lay Barge and Screed Barge Methods

  13. 13 MTT Lay Barge

  14. New ITT - Immersion  Elements to be immersed into a dredged trench with a screeded gravel base — Approx. max depth of 95 feet 14

  15. New ITT - Immersion  Seals between Elements — Gina Joint (gasket type) — Omega Seal (inner connection)  Elements to connect to Cast in Place Approach work 15

  16. New ITT - Immersion  Seals between Elements — Gina Joint (gasket type) — Omega Seal (inner connection)  Elements to connect to Cast in Place Approach work 16

  17. New ITT - Immersion  Elements to be immersed into a dredged trench with a screeded gravel base — Approx. max depth of 95 feet 17

  18. 18 New MTT - Approaches

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend