The Elizabeth River Tunnels Project Project Overview and MLK - - PowerPoint PPT Presentation

the elizabeth river tunnels project
SMART_READER_LITE
LIVE PREVIEW

The Elizabeth River Tunnels Project Project Overview and MLK - - PowerPoint PPT Presentation

The Elizabeth River Tunnels Project Project Overview and MLK Presentation March 18, 2014 The Design-Build Team Design-Build Joint Venture Skanska USA Civil SE Kiewit Infrastructure Company Weeks Marine Design Team Parsons


slide-1
SLIDE 1

Project Overview and MLK Presentation March 18, 2014

The Elizabeth River Tunnels Project

slide-2
SLIDE 2

 Design-Build Joint Venture —Skanska USA Civil SE —Kiewit Infrastructure Company —Weeks Marine  Design Team —Parsons Brinckerhoff —Volkert & Associates  Immersed Tube Tunnel Experience: —Since 1964, installed 74% of the ITT’s in the USA —Installed 52,500 feet in the USA —19,700 feet of ITT in the Norfolk Area

2

The Design-Build Team

slide-3
SLIDE 3

3

Timeline for Development

Timetable

Call for conceptual proposals May 2008 Conceptual proposal submittal September 2008 Public Hearings – Independent Review Panel March to June 2009 Positive CTB Recommendation July 2009 Key business points presented to CTB October 2009 Signature of Interim Agreement January 2010 IA Phase 1 - Feasibility Stage January 2010 IA Phase 2 - Development Stage June 2010 Signature of Comprehensive Agreement December 2011 Financial Close / Construction Start April 2012

slide-4
SLIDE 4

Contract Structure

4

slide-5
SLIDE 5

5

Scope

New Midtown Tunnel Rehab Existing MTT MLK Extension Rehab Existing Downtown Tunnels (EB & WB) Portsmouth Norfolk

slide-6
SLIDE 6

New Midtown Tunnel

6

 Concrete shell, Immerse Tube Tunnel (ITT)  West bound Tube connecting Norfolk to Portsmouth  Two vehicular lanes and an egress corridor

slide-7
SLIDE 7

New MTT – Tube Fabrication

7

 Construction in Baltimore due to availability of dry docks  Trial Casting — Demonstrate techniques — Test thermal modeling  Two Casting Cycles — CC 1 – 6 elements — CC 2 – 5 elements  Dimensions (average) — 350’ x 54’ W x 28’ T — 16,000 Tons each

slide-8
SLIDE 8

New MTT – Tube Fabrication

8

 Construction in Baltimore due to availability of dry docks  Trial Casting — Demonstrate techniques — Test thermal modeling  Two Casting Cycles — CC 1 – 6 elements — CC 2 – 5 elements  Dimensions (average) — 350’ x 54’ W x 28’ T — 16,000 Tons each

slide-9
SLIDE 9

New MTT – Tube Fabrication

9

slide-10
SLIDE 10

New MTT – Tube Fabrication

10

 Each Element constructed in Segments — Inverts (5 per element) — Interior Walls (5 per element) — Roof (Doghouse) (5 per element)  Formwork Traveler — Progresses from segment to segment — Moving production line

slide-11
SLIDE 11

New MTT – Tube Fabrication

11

slide-12
SLIDE 12

Conventional Lay Barge and Screed Barge Methods

12

slide-13
SLIDE 13

MTT Lay Barge

13

slide-14
SLIDE 14

New ITT - Immersion

14

 Elements to be immersed into a dredged trench with a screeded gravel base — Approx. max depth of 95 feet

slide-15
SLIDE 15

New ITT - Immersion

15

 Seals between Elements — Gina Joint (gasket type) — Omega Seal (inner connection)  Elements to connect to Cast in Place Approach work

slide-16
SLIDE 16

New ITT - Immersion

16

 Seals between Elements — Gina Joint (gasket type) — Omega Seal (inner connection)  Elements to connect to Cast in Place Approach work

slide-17
SLIDE 17

New ITT - Immersion

17

 Elements to be immersed into a dredged trench with a screeded gravel base — Approx. max depth of 95 feet

slide-18
SLIDE 18

New MTT - Approaches

18