Bridge Owners Forum 21 st January 2014 Huw Davies National Cycle Network Director Paul Thomas Bridge Engineer Sustrans Railway Paths Limited (RPL) Connect 2 Connect 2 Bath 2 Tunnels Bath 2 Tunnels The Sustrans and RPL Bridges
SLIDE 2
SLIDE 3
Connect 2
SLIDE 4
Connect 2
SLIDE 5
Bath 2 Tunnels
SLIDE 6
Bath 2 Tunnels
SLIDE 7
The Sustrans and RPL “Bridges” Team
Paul Thomas John Litt
SLIDE 8
How Many Structures?
- These include viaducts, tunnels, bridges, culverts,
abutments and retaining walls
- Some have walking and cycling paths, some don’t
Eng / Scot / Wales RPL 710 Sustrans 430 Total 1140
SLIDE 9
Overview
In general our structures date from the period of the expansion of the railways (100 to 150 years old) Mostly
- Brick and masonry arch
- WI and steel beam
Some
- RC decks (replacements)
- Timber footbridges
None
- Suspension bridges
- Cantilever bridges
SLIDE 10
The viaducts – 71 no.
- Larpool
SLIDE 11
Viaducts cont.
- Larpool
SLIDE 12
Listed Structures – 33 no.
Thornton Lee Moor Vauxhall
SLIDE 13
Tunnels – 18 no.
- Devonshire, Clydach, Tid
SLIDE 14
Curios
SLIDE 15
Structures – Managing decline
Overbridge Underbridge Our fortunate position – our underbridges generally have large reserves
- f strength.
We manage the decline of underbridges and concentrate resources
- n overbridges that carry the public highway.
SLIDE 16
Inspections
Inspections
- Routine / visual inspection
every year
- Principal / detailed inspection
every 6 years (or less)
- Special Inspection
as necessary Risk assessment (with principal inspections)
- Scour and flooding
- Tunnels
- Culverts
SLIDE 17
Challenges
- Scour and flood related damage
- Listed viaducts
- Overbridges supporting the public highway
- Remote culverts