Shotcrete for Africa Application of Mechanised Wet Shotcreting in - - PowerPoint PPT Presentation

shotcrete for africa
SMART_READER_LITE
LIVE PREVIEW

Shotcrete for Africa Application of Mechanised Wet Shotcreting in - - PowerPoint PPT Presentation

Shotcrete for Africa Application of Mechanised Wet Shotcreting in the Gautrain Tunnels 3 rd March 2009 Presented by Richard McIntyre & Robert Pettit Introduction The Application of Mechanised Wet Shotcreting in the Gautrain Tunnels


slide-1
SLIDE 1

Shotcrete for Africa

Application of Mechanised Wet Shotcreting in the Gautrain Tunnels 3rd March 2009 Presented by Richard McIntyre & Robert Pettit

slide-2
SLIDE 2

Introduction

The Application of Mechanised Wet Shotcreting in the Gautrain Tunnels

  • The Gautrain Rapid Rail Project
  • Design development from a mixture of shotcrete and

insitu concrete lining to shotcrete only.

  • Shotcrete mix design development and testing
  • Equipment selection process
  • Application process for safe and successful tunnel

construction

slide-3
SLIDE 3

Gautrain Tunnels

Bombela Civil Joint Venture - Drill and Blast Tunnel Length 11.4Km

(12.7Km including parallel track, emergency chambers & connections)

slide-4
SLIDE 4

Gautrain Tunnel Stations and Shafts

Park Station Rosebank Sandton D&B D&B TBM (Tunnel Boring Machine) 1000m 900m 220m 2800m 800m 2300m 1300m E1 E5 E2 E3 E4 E6 E7

Mushroom Sandton Marlboro Portal 500m 1800m 3000m

slide-5
SLIDE 5

Lining Design

  • Support requirements were established from

assessment of the ground conditions and categorised into a rock classes.

  • Rock classification was based on the Q System
  • Each class of rock has its own support pattern for the

different tunnel cross sections.

  • Support consists of rockbolts, shotcrete, lattice arches or

steel ribs and canopy tubes.

  • Advance lengths per round were limited for each class.

(between 6m and 1.5m)

slide-6
SLIDE 6

Single Tunnel Lining Design

Support Class Q Shotcrete (Grade C25) Plain-PS Fibre Reinforced-FRS Total Lining Thickness (mm) Maximum Advance Primary (minimum) Secondary Single SC1 >15 Nil Nominal where required (structurally not required) 50mm SS as required <6m Single SC2 6 -15 50mm FRS in Crown Nominal where required Min 50mm FRS 6m Single SC3 2-6 50mm FRS in Crown and Walls Nominal where required Min 50mm FRS 6m Single SC4a 0.5-2 50mm FRS in Crown and Walls 50mm FRS in Crown and Walls Min 100mm FRS 3m Single SC4b 0.07-0.5 100mm FRS in Crown and Walls 150mm FRS in Crown and Walls Arch at 1.5m centres Min 250mm FRS 1.5m Single SC5 0.007-0.07 100mm FRS in Crown and Walls 250mm FRS in Crown and Walls Arches at 1.25m centres Min 350mm FRS 1.5m Single SC6 <0.007 175mm FRS, in Crown and Walls 200m FRS in Crown and Walls Arches at 1.5m centres Min 375mm FRS in Crown and Walls 1.5m

slide-7
SLIDE 7

Twin Tunnel Lining Design

Support Class Q Shotcrete (Grade C25) Plain -PS Fibre Reinforced-FRS Total Lining Thickness (mm) Maximum Advance Primary (minimum) Secondary Twin SC0 >22 Nil Nominal where required (structurally not required) 50mm SS as required 6m Twin SC1 4-22 50mm FRS in Crown and Walls 75mm FRS in Crown and Walls Min125mm FRS 6m Twin SC2 1-4 50mm FRS in Crown and Walls 75mm FRS in Crown and Walls Min 125mm FRS 6m Twin SC3 0.1 to 1 50mm FRS in Crown and Walls 150mm FRS in Crown and Walls Min 125mm FRS 3.5m to 6m Twin SC4 Dry 0.05 to 0.1 175mm FRS in Crown and Walls 50mm FRS in Crown and Walls Min 225mm FRS 1.5m to 4m Twin SC4 Wet 0.05 to 0.1 175mm FRS in Crown and Walls 50mm FRS in Crown and Walls + 50mm of PS Arches at 1.3m centres Min 300mm FRS &PS 1.5m to 2.5m

slide-8
SLIDE 8

Ground classes

Single Tunnel SC3

slide-9
SLIDE 9

Ground classes

Twin Tunnel SC4 Dry

slide-10
SLIDE 10

Ground classes

Twin Tunnel Drainage

slide-11
SLIDE 11

Tunnel Drainage

Half Round Pipe for Localised Inflows

slide-12
SLIDE 12

Tunnel Drainage

Pozidrain Strips with Mesh for Diffuse Seepage

slide-13
SLIDE 13

Duration of process:4 months Key Issues:

  • Definition of the specification:

Workability, Compressive & Flexural Strength, Bond strength, Durability, European Standard EN 206-1 adopted

  • Analysis of the environment (chemistry):

Groundwater and the soil quality

  • Ready-mix industry:

Local supplier quantity, reliability and quality related to the specifications

  • Batching-plants equipment:

BCJV supply option to install batch plants on site, space and sizing

  • Raw materials availability

Supply of Cement and aggregates, suitability, delivery and storage.

Mix Design Development – Summary

slide-14
SLIDE 14

Mix design – Performance results

98.3 89.5 79.0 63.7 51.2 37.0 27.6 19.7 12.2 11 22 37 55 73 100 26 50 72 90 100 100 0.15 0.3 0.6 1.18 2.36 3.35 5 6.3 10 14 20 37.5 4 90 12 10 20 30 40 50 60 70 80 90 100

0 . 1 m m 1 m m 1 m m 1 0 0 m m

Particle size (mm) Percentage passing Combined grading EFNARC Specification

Sieve mm

CEM I 42.5 N 360 kg/m3 64% Fly Ash 100 kg/m3 18% GGBS Slag 100 kg/m3 18% Filler Sand 185 kg/m3 Crusher Sand 816 kg/m3 9.5mm 539 kg/m3 Fibres 4 kg/m3 W/C ratio 0.45 Superplasticizer 5 kg/m3 EFNARC envelop

Slump:

170mm +/- 30mm

Slump retention:

6 hours

Hard Shotcrete

Cubes Compressive strength Compressive strength Flexural strength 8 hours 3 MPa 24 hours 3 MPa 8 MPa 7 days 45 MPa 20 MPa 28 days 60 MPa 30 MPa 3.5 MPa Sprayed Shotcrete with 25 kg/m3 of accelerator

slide-15
SLIDE 15

Site Batch Plant

Park Station Batch Plant 37m3/hr

slide-16
SLIDE 16

Quality Control – Batch plant

  • At the start, approved materials were checked and trial

mixes were batched to demonstrate the performance of the shotcrete

  • Slump test done on every batch, before send to site.
  • Every 50m³ manufactured, cubes are taken for

compressive strength tests.

slide-17
SLIDE 17

Quality Control - Site

  • Every truck received:
  • visual checking

– checking for segregation of mix – fibres agglomeration – aggregate uniformity – mix property

  • slump

– checked at site prior to discharge from the truck – check after storage in Secatol before filling the Agicar in the tunnel, slump test done.

slide-18
SLIDE 18

Quality Control - Site

  • Once a week - panel sprayed for compressive strength

testing.

  • Once every two weeks - panel sprayed for flexural

strength beam testing.

  • Every 100 metres of tunnel - in situ bond strength test

will be done.

  • Every 100 metres of tunnel - in situ compressive strength

will be checked by coring.

  • Shotcrete thickness is checked;

SC1 to SC3 - Visual inspection all bolts covered. SC4a to SC6 - Coring / drilling every 50m.

slide-19
SLIDE 19

Shotcrete supply system

  • 3 Batch plants;

Marlboro portal – 2 by 50m3 / hr Rosebank Station – 37m3 / hr Park Station – 37m3 / hr

  • Dispatched to sites with 6m3 truck mixers – 12 units.
  • Discharged into 5 – 7m3 remix hoppers.
  • When needed discharged into 5.5m3 Agicars and transported to the

face.

  • Weekly forecast
  • Daily conformation
  • 24hrs / day, 7 days per week.
slide-20
SLIDE 20

Supply constraints

  • Delivery schedules being altered – delays.
  • Large concrete pours for stations.
  • Quality of shotcrete supplied with incorrect workability.
  • Traffic (peak hours).
  • Availability of trucks / drivers (especially over weekends).
slide-21
SLIDE 21

Shotcrete supply

slide-22
SLIDE 22

Shotcrete Equipment

Paus ITC 10 000 Agicar with Putzmeister PM 500 Shotcrete Unit Twin Tunnel 8-20m3/hr Paus ITC 10 000 Agicar with Putzmeister PM 407 Shotcrete Unit Single Tunnel 4-15m3/hr

slide-23
SLIDE 23

Shotcrete Equipment

PM 500 at Marlboro

slide-24
SLIDE 24

PM 407

slide-25
SLIDE 25

PM407 Shotcrete Unit Spray Area Single Tunnel

slide-26
SLIDE 26

PM407 Shotcrete Unit Spray Articulation

slide-27
SLIDE 27

Shotcrete in tunnels

  • Key aspects for successful application of shotcrete;

Organisation in the tunnel to arrange delivery on time Correct quality of supply and checking Prior preparation of equipment Maintenance of equipment Skilled operators

slide-28
SLIDE 28

Tunneling cycles

  • SC1 to 3 – Shotcrete every 2nd or 3rd round. “Shotcrete

not critical.”

  • SC4a to 6 – Primary lining to be applied with every

excavation cycle. Shotcrete critical.

  • The quantity and frequency was typically:

monthly shotcrete production: 5110 m³ daily shotcrete production: 189 m3 (7.8 m³/hr) average duration for each shotcrete application in tunnel: 3 hours once to twice a day

slide-29
SLIDE 29

Training of operators

  • Operators – Mixture of experienced foreign and local trained
  • perators.
  • All foreman trained as operators – backup and ensure they have the

required knowledge to manage the process.

  • The ability of the operator will condition:

structural quality visual quality time spent to spray per cycle minimise rebound minimise accelerator consumption

slide-30
SLIDE 30

Application

Quality control before spraying requires the following:

  • shift foreman to scale and wash down the newly exposed rock

surfaces

  • the surveyor to check profile clearances
  • the geotechnical engineer to confirm rock class
  • the operator to check equipment is clean and ready for operation
  • quality control while spraying
  • accelerator dosage to be controlled
  • air delivery pressure to be controlled
  • profile controlled build-up in 50mm thick layers
  • controls in themselves provide direct limitation of rebounds, loss and

wastage

slide-31
SLIDE 31

Application

Quality control after spraying requires:

  • curing of the shotcrete
  • subsequent layers sprayed onto a clean surface
  • depth of cover to protruding rockbolts
slide-32
SLIDE 32

Shotcrete application

slide-33
SLIDE 33

Shotcrete application in arch section

slide-34
SLIDE 34

Tunnel after primary shotcrete application

slide-35
SLIDE 35

Conclusion

  • The approach to providing a drained tunnel solution

using a variable selection of methods with proven materials within the shotcrete application has been shown to be a viable design solution.

  • The requirement to apply shotcrete as a composite

support and final lining was implemented through attention to the shotcrete material design, the selection

  • f suitable equipment to allow high quality work in the

tunnels, while the training of operators to ensure controlled spraying was essential to the successful application of the system.

slide-36
SLIDE 36

Conclusion

  • With the tunnel overbreak typically being 500mm in the

places where concrete lining may have been required, the saving in overbreak concrete alone will amount to some 10,500R/m in the single tunnel.

  • The most significant saving however is in time which will

allow the project to be commissioned more rapidly and bring forward the date at which revenue can be earned.

slide-37
SLIDE 37

Thank You Any Questions ?