Optimizing LCC for Pier Bridges using FRP Members Professor Seishi - - PowerPoint PPT Presentation

optimizing lcc for pier bridges using frp members
SMART_READER_LITE
LIVE PREVIEW

Optimizing LCC for Pier Bridges using FRP Members Professor Seishi - - PowerPoint PPT Presentation

US-Japan Workshop on Life Cycle Assessment of Sustainable Infrastructure Materials Sapporo, Japan, October 21-22, 2009 Optimizing LCC for Pier Bridges using FRP Members Professor Seishi Yamada Chairman of Faculty Meeting, Head of Dept, Dept of


slide-1
SLIDE 1

Optimizing LCC for Pier Bridges using FRP Members

Professor Seishi Yamada Chairman of Faculty Meeting, Head of Dept, Dept of Civil Engrg, Toyohashi University of Technology, Japan

US-Japan Workshop on Life Cycle Assessment of Sustainable Infrastructure Materials Sapporo, Japan, October 21-22, 2009

slide-2
SLIDE 2

Task Committees for FRP Bridges in JSCE

  • Task Committee for Research on FRP Bridges (2000-2)

– Chair: Prof. Ohshima, Kitami Univ. of Technology

  • Task Committee for Research on FRP Bridges (2002-4)

– Chair: Prof. Maeda, Tokyo Metropolitan Univ.

  • Task Committee for Design of FRP Bridges (2004-6)

– Chair: Prof. Yamada, Toyohashi Univ. of Technology

  • Task Committee for FRP Hybrid Bridge (2006-9)

– Chair: Prof. Yamada, Toyohashi Univ. of Technology

slide-3
SLIDE 3

Optimizing LCC for Pier Bridges using FRP Members Contents

  • 1. Introduction
  • 2. Situation of Steel Pier Bridges
  • 3. Cost Analyses for Pier Bridges

3.1 Initial Construction Cost 3.2 Comparison of Costs Considering LCC

  • 4. Conclusions

Appendix: FRP Footbridges in Japan

US-Japan Workshop on Life Cycle Assessment of Sustainable Infrastructure Materials Sapporo, Japan, October 21-22, 2009

slide-4
SLIDE 4

Fiber reinforced polymer (FRP) is anticipated for the use as innovative structural members that replace the conventional materials, and in the last decade in USA, many applications to the structural, girder, slab and truss members have been presented. Also in Japan, a several FRP foot bridges have recently constructed based upon various energetic research developments. To infiltrate FRP footbridges into Japan, JSCE has engaged to make FRP footbridge design guidelines. Meanwhile, it would be also important to find the new places to apply FRP structural members and JSCE has also targeted the investigation of the application to PIER bridges.

slide-5
SLIDE 5

It would be well known that pier bridges connect between wharf and pontoon and is generally located

  • n hard salt environment.

The pier bridges vary from

slide-6
SLIDE 6

Large pier bridge which is able to pass a car Small pier bridge which passes people mainly

slide-7
SLIDE 7

Using the construction details including the costs of recently erected footbridges in Japan (see Appendix), this paper estimates the initial construction cost and life cycle cost (LCC) of a pier bridge through the analyses of maintenances and repaints, and discusses on the applicability of FRP to pier bridges.

slide-8
SLIDE 8
  • 2. Situation of Steel Pier Bridges

Currently, almost pier bridges are of steel, therefore, a lot of administrators of pier bridges are now faced with big problems on the durability and maintenance for steel members due to the use under the hard environment. Main deterioration factors are corrosion due to splash salt, and fatigue due to waves in the storm and enforcement deflection by landing ship.

slide-9
SLIDE 9

Fatigue due to waves in the storm

Wave or Landing

Storm

Corrosion due to splash salt

slide-10
SLIDE 10

Steel pier bridges in Hiroshima, Japan

Investigated by the author, 2007

slide-11
SLIDE 11

It is much difficult for the administrator to inspect and sustain his pier bridges as offshore structures. He tends to overlook and leave progress of corrosion because the speed of corrosion under the deck is quicker than one over the deck. Also, the maintenance requires hard working because the workers need a boat for the inspection and painting.

slide-12
SLIDE 12

The other point of view is its ability of rehabilitation after damage due to a heavy storm; pier bridges drop from pontoon and sink into the sea, so they would be required to be taken to salvage and to be recovered after storming as soon as possible. In order to solve these problems, the FRP pier bridges having various advantages (hard corrosion, hard fatigue, light weight and short construction period) are now anticipated strongly by many administrators in Japan.

slide-13
SLIDE 13

3 COST ANALYSES FOR PIER BRIDGES 3.1 Initial Construction Cost We have four FRP footbridges whose detailed data were already presented in Japan. All are of girder or truss types, so these two types are adopted in this study. According to domestic achievement, it seems that length of span about girder and truss limited 20 meters due to serious specification of deflection in Japanese conventional design guidelines for steel bridges. The obtained analytical results are represented in Appendix in which each completion time, weight, structure cost, maintenance cost are listed, consequently they can be easy compared together.

slide-14
SLIDE 14

Through the preliminary design for steel as well as FRP pier bridges of above bridge types, their initial construction costs were tried to estimate. On the pier bridges of this study, the effective width = 2m, the length of span = 5m, 10m, 15m and 20m. Referring to the Japanese Standard for Vertical Cross Footbridges 1979, the design live load = 3.5 kN/m

2

the limit of deflection = L/600 for steel pier bridges = L/400 for FRP pier bridges (L = length of span)

slide-15
SLIDE 15

For a STEEL pier bridge, its weight in ton force unit (9.8kN) was computed as referring the design data of selected existing steel pier bridges in Japanese Design Data Book, then its computed weight was multiplied with the following constant; 1.0 million JPY/tonf for the girder type

  • r 1.2 million JPY/tonf for the truss type.
slide-16
SLIDE 16

For a FRP pier bridge, its floor space in square meter was computed then its computed weight was multiplied with the constant; 0.45 – 0.47 million JPY/m2 for the girder type

  • r 0.32 – 0.35 million JPY/m2 for the truss type.
slide-17
SLIDE 17

Initial Construction Cost (Effective width=2m) 5 10 15 20 25 5 10 15 20 Length of Span (m) Cost(million JPY)

Steel Gider Steel Truss FRP Truss FRP Girder

Examples: Initial construction costs for 2m width. The cost performances: the parameter = span L The FRP girder pier bridge is the most expensive. The cost of FRP truss pier bridges is almost the same price as that of steel pier bridges.

slide-18
SLIDE 18

3.2 Comparison of Costs Considering LCC Generally, steel pier bridges require the periodic repaint due to preventing from corrosion. Thus, the interval of repaint for steel pier bridges is 10 years from actual achievement. The unit cost of paint for steel pier bridge is 9,000 JPY/m2 as polyurethane paint with epoxy on sand blasted base. The interval of repaint for FRP pier bridges is assumed to be 15 years because FRP did not corrode but needs to keep surface for preserving aesthetic view against ultraviolet ray degradation. The unit cost of paint for FRP pier bridge with effective width 2m was estimated to be 0.6 million JPY/m from the domestic achievement, e.g. acrylic urethane paint or fluorine paint.

slide-19
SLIDE 19

. 2 . 5 5 . 7 . 5 1 . 5 1 1 5 2 2 5 3 3 5 4 4 5 5

Y e a r C

  • s

t ( m i l l i

  • n

J P Y ) S t e e l G i r d e r S t e e l T r u s s F R P T r u s s F R P G i r d e r

Fig.7 Life Cycle Cost for the case of “Length of Span = 5m” Results for LCC The FRP truss pier bridges are superior to the steel pier bridges at 20 years after completion

slide-20
SLIDE 20

The FRP truss pier bridges are superior to the steel pier bridges at 20 years after completion Fig.8 Life Cycle Cost for the case of “Length of Span = 10m”

. 2 . 5 5 . 7 . 5 1 . 1 2 . 5 1 5 . 5 1 1 5 2 2 5 3 3 5 4 4 5 5

Y e a r C

  • s

t ( m i l l i

  • n

J P Y )

S t e e l G i r d e r S t e e l T r u s s F R P T r u s s F R P G i r d e r

slide-21
SLIDE 21

The FRP truss pier bridges are superior to the steel pier bridges at 20 years after completion Fig.9 Life Cycle Cost for the case of “Length of Span = 15m”

. 5 . 1 . 1 5 . 2 . 2 5 . 5 1 1 5 2 2 5 3 3 5 4 4 5 5

Y e a r C

  • s

t ( m i l l i

  • n

J P Y ) S t e e l G i r d e r S t e e l T r u s s F R P T r u s s F R P G i r d e r

slide-22
SLIDE 22

The FRP truss pier bridges are superior to the steel pier bridges at 20 years after completion Fig.10 Life Cycle Cost for the case of “Length of Span = 20m”

. 5 . 1 . 1 5 . 2 . 2 5 . 3 . 3 5 . 5 1 1 5 2 2 5 3 3 5 4 4 5 5

Y e a r C

  • s

t ( m i l l i

  • n

J P Y ) S t e e l G i r d e r S t e e l T r u s s F R P T r u s s F R P G i r d e r

The cost of FRP girder pier bridges is also shown to be smaller at 30 years or 40 years than that of the steel truss pier bridges.

slide-23
SLIDE 23

CONCLUSIONS Studying on the feasibility of FRP pier footbridges, it has been interpreted that the LCC for FRP pier bridges is expected to be smaller than that for conventional steel pier bridges. It would be surmised that optimizing span length of the FRP pier footbridges is approximately from 10m to 20m under the cost data of recently constructed four FRP footbridges in Japan and the truss type is the better choice rather than the girder type for FRP pier footbridges.

slide-24
SLIDE 24

Quality Index

initial cost LCC IQC > IQR IEC > IER ICC > ICR LCO2e Neglect of Greenhouse Emission Effects conventional design appropriate design New Concept of Performance Based Environmental Design for Infrastructures by Seishi Yamada 2009

Life Cycle Environmental Friendly Index Cost Reduction Index

strength, ductility, beauty, comfort ability