pier 4 phase 1 removal action prebid meeting
play

Pier 4 Phase 1 Removal Action Prebid Meeting Relocate Navigation - PowerPoint PPT Presentation

Pier 4 Phase 1 Removal Action Prebid Meeting Relocate Navigation BLAIR WATERWAY Lights Existing Pier 4 Pier 3 Future Pier 4 Reconfiguration Existing wharf deck to remain PARTIAL WHARF DEMOLITION Dredge 49,000 CY BLAIR WATERWAY


  1. Pier 4 Phase 1 Removal Action Prebid Meeting

  2. Relocate Navigation BLAIR WATERWAY Lights Existing Pier 4 Pier 3 Future Pier 4 Reconfiguration Existing wharf deck to remain PARTIAL WHARF DEMOLITION

  3. Dredge 49,000 CY BLAIR WATERWAY contaminated material Southern Hot Spot Central Hot Spot Pier 3 Future Pier 4 Reconfiguration Dredge 9,000 CY clean material DREDGING & DISPOSAL OF TBT MATERIAL

  4. Pier 3 Pier 4 Transload Site APM TERMINALS

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.