the davis
play

The Davis Woodland Water Supply Project W OOD LA N D R OTA RY C - PowerPoint PPT Presentation

The Davis Woodland Water Supply Project W OOD LA N D R OTA RY C LU B D ecember 13, 2016 Presentation Overview Surface Water Project Overview Project Delivery Method Water Rights & Operations Budget and Schedule 2 Water Supply Issues


  1. The Davis Woodland Water Supply Project W OOD LA N D R OTA RY C LU B D ecember 13, 2016

  2. Presentation Overview Surface Water Project Overview Project Delivery Method Water Rights & Operations Budget and Schedule 2

  3. Water Supply Issues Degrading 100% Example: groundwater Nitrates water quality Dependent on groundwater Increasingly Example: stringent drinking Hexavalent water regulations Chromium Aging water Increasingly restrictive Example: infrastructure wastewater discharge Selenium, Salinity regulations 3

  4. Woodland Aging Well System 30 – 50 years is the typical lifespan of a well 50 30 0 4

  5. City of Davis Well Nitrate Levels 60 Concentration (mg/L) Drinking Water Action 30 0 1999 2007 2015 2023 2031 5

  6. Well Shutdowns Woodland Davis Well shut downs Active wells Under Construction 6

  7. Governing Board: 2 council members from each city Non-voting representative from UC Davis and Yolo County September 15, 2009 FORMED Davis and Woodland JPA UC Davis a Contracting Agency User fees in each city; cost Funded sharing based on capacity allocation 7

  8. Project Goals and Objectives Quantity & Improve water supply quantity and quality Quality Comply with drinking water & wastewater Regulations discharge regulatory requirements Provide environmental benefits and Environmental minimize impacts Diversify supply portfolio to improve Diversify supply reliability Allow sustainable groundwater Sustainable GW pumping integrated with ASR wells Integrate water conservation elements Conservation 8

  9. ASR Wells Raw Water Transmission 4.5 miles Intake/Pumping Treatment Facility 400 cfs 30 mgd Local Transmission Water Transmission 9.9 miles Local Transmission 9

  10. Project Partners Reclamation District 2035 Intake City of Davis Davis- Woodland City of Woodland Water Supply Project 10

  11. Joint Intake Concept Drawing

  12. Joint Intake Raw Water Piping in Pump Room

  13. Joint Intake Installation of vibration sensors (left), ongoing electrical work (right)

  14. Joint Intake Architectural work on building exterior

  15. Groundbreaking Ceremony- April 10, 2014 15

  16. May 2, 2016 16

  17. Presentation Overview Surface Water Project Overview Project Delivery Method Water Rights & Operations Budget and Schedule 17

  18. Delivery Methods Selected Design-Build-Operate Treatment Plant • Treatment Plant & Transmission Pipelines Pipelines Design-Bid-Build: • Intake • City distribution pipelines Intake 18

  19. Design-Build-Operate Initial DWWSP Concerns Are we stuck with private Is this operations Who controls private forever? water rates? ownership? 19

  20. DBO is NOT… • Private ownership • Establishment or control of water rates • Private determination of customer water quality • Permanent private operation • Replacement of city staff 20

  21. DBO is… • Guaranteed price for performance • Cost-effective operations • Timely project completion • Facilities repair and replacement program • Local employment and contracting • Allocation of risk between public and private 21

  22. Design-Build-Operate Benefits to DWWSP • Faster Delivery • Life Cycle Cost Savings • Early Price Certainty • Opportunity for Innovation • Collaborative Selection and Negotiation Process • Singular Responsibility • Appropriate Allocation of Risk • Long-Term Operations 22

  23. Service Contract Items Important to Community Local employment and contracting Pre-approval of subcontractors and key personnel Quality Management Plan 23

  24. Presentation Overview Surface Water Project Overview Project Delivery Method Water Rights & Operations Budget and Schedule 24

  25. Balancing Supply and Demand Demands/Plant Supply Yield Supplemental Sizing Analysis Supply Sources 5 – 15% 85 – 95% PREVIOUS FUTURE 25

  26. Water Supplies ASR/ Supplemental Supplies (primarily Woodland) Municipal Groundwater (Davis: Deep aquifer wells; Woodland: Emergency GW use only) Purchased Water (available Apr – Oct; subject to Shasta critical years) Agency Water Right (subject to Term 91 curtailments) 26

  27. Presentation Overview Surface Water Project Overview Project Delivery Method Water Rights & Operations Budget and Schedule 27

  28. Project Costs – June 2016 (million dollars) Capital Costs, 2009-2016 UC Construction Costs Cost Category Total Woodland Davis Davis Agency Administration 3.18 1.56 1.47 0.16 Project Component Cost Program Management 4.40 2.17 2.05 0.17 DBO Contract 145.86 Water Supply 1.81 1.29 0.50 0.02 Agency Quality Assurance & 7.52 Contract Compliance (a) Environmental & Permitting 1.27 0.62 0.60 0.06 Joint Intake 17.57 Land/ROW Acquisition 4.24 2.00 2.00 0.25 Pre-Design 5.94 3.21 2.51 0.22 TOTAL 170.95 Construction 170.95 91.26 68.74 10.94 (a) Includes Agency design review, construction Capital Contingency 5.19 2.63 2.34 0.22 quality assurance and contract compliance, submittal and RFI review, environmental construction monitoring, environmental Costs Expended 2009-2011 7.59 4.02 3.48 0.06 mitigation, Agency permitting and incidental costs. Total Regional Costs 204.54 108.75 83.69 12.11 Woodland and Davis Local 74.70 31.50 35.50 7.70 Facilities TOTAL CAPITAL COSTS 279.2 140.2 119.2 19.8 Updated: 6/15/16 28

  29. Project Funding Federal/State Grants Intake • $40.2M obtained ($20.1M each) • Local WDCWA Share State Revolving Fund Loans • Project Wastewater Nexus • Safe Drinking Water and Clean Water SRF loan programs • $274M of SRF loans secured 29

  30. Project Implementation Schedule 2010-2016 2016 2012 2014 Design/Permitting Completion of Construction Land Acquisition Regional/Local Facilities System Testing DBO Procurement Design & Construction Start-up and Operation Financing Intake Construction 2011 Financing Permitting 2013 Land Acquisition Pre-Design DBO Contract Negotiation Permitting Water Right Permits Land Acquisition DBO Procurement Project Optimization Financing Local Facilities Design Financing 2015 2010 Intake/Pipelines/ Permitting Water Treatment Pre-Design Facility/Local Facilities Construction D E S I G N C O N S T R U C T I O N O P E R A T I O N 30

  31. Schedule Milestones Task Completion By Begin Initial Water Deliveries to Cities Early June 1 2016 Completion of Acceptance Test and Commencement of Operations Period June 29, 2016 Begin deliveries of raw water through Joint Intake Facility September 2016 Substantial Completion of Joint Intake Facility December 2016 Updated: 9/14/16

  32. Dedication and ribbon cutting ceremony at the new RWTF – July 28, 2016 32

  33. Joint Intake Dedication Ceremony September 13, 2016 33

  34. Operations • Currently delivering ~ 12 mgd of treated surface water: – Woodland: ~ 6 mgd – Davis: ~ 6 mgd • Meeting all regulatory and contract drinking water requirements • CH2M working to optimize process operations 34

  35. Questions

  36. 36

  37. 37

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend