RUBBER LINING Surface Protection Presented by : PT Ranadityo Sukses Makmur Authorized Distributor of Bando Rubber Lining Jl. Bakti 4 Kav. 52, Cilandak KKO, Cilandak Timur, Pasar Minggu, Jaksel 12560 Phone. (021) 30338828 / 7823856 ; Fax. (021)


  1. RUBBER LINING Surface Protection Presented by : PT Ranadityo Sukses Makmur Authorized Distributor of Bando Rubber Lining Jl. Bakti 4 Kav. 52, Cilandak KKO, Cilandak Timur, Pasar Minggu, Jaksel 12560 Phone. (021) 30338828 / 7823856 ; Fax. (021) 7823856 Email. sales@ranadityo.co.id / ranadityo_suksesmakmur@yahoo.com Website. www.ranadityo.co.id

  2. Purpose Use of Rubber Lining The purpose of the use of rubber lining is to protect an equipment against corrosion / rust and chemicals that abbrasive and other ingredients such as sea water, acid, sand, slurry, etc., which can damage an equipment.

  3. Application Method of Rubber Lining 1. HOT BONDING Process Rubber Sheet Unvulcanized 2.COLD BONDING Process Rubber Sheet Vulcanized

  4. RAW MATERIAL WEIGHING FLOW CHART RUBBER PLASTICIZING/MIXING SHEET PROCESS AND (BANBURY/KNEADER/OPEN MILL) APPLICATION FORMING / SHEETING (ROLLER HEAD – EXTRUDER / CALENDER) FOR COLD BONDING FOR HOT BONDING WINDING OF GREEN SHEET TANK CURING OF SHEET GREEN SHEET CUTTING INTO ( ROTO CURE ) REQUIRED LENGTH SHOT BLASTING OF SURFACE TO BE LINED BUFFING OF SURFACE TO BE APPLIED APPLICATION OF BONDING AGENT LAYING OF SHEET ON THE SURFACE TO BE LINED AUTO CLAVE ROOM TEMPERATURE CURING FINISHING FINISHING FINAL INSPECTION FINAL INSPECTION DELIVERY DELIVERY

  5. Material & Specification Material Type Method Service Recommended Usage In Industry Temperature BI-H-10 Hot Bonding Below 90 C Brine Storage, Hcl Storage, Caustic soda storage tank, H3PO4 Tank, H2SO4 etc. BI-H-20 Hot Bonding Below 90 C Brine Storage, Hcl Storage, Caustic soda storage tank, H3PO4 Hard Rubber Tank, H2SO4 etc. BI-H-30 Hot Bonding Below 90 C Aplication where low Ca, Mg ions are demanded BI-S-N Cold Bonding Below 90C Acid Storage tank, Anion, cation, Cation Exchanger, water Storage tank etc. BI-S-A Hot & Cold Below 90C Soft Rubber Bonding BI-S-11 Hot & Cold Below 90C Acid Storage tank, Anion, Cation Exchanger, Hcl Storage Tank, Bonding Phosphoric acid storage tank, ZnCl2 Reaction tank EPDM BI-EP-V Cold Bonding Below 135C Sea water piping, Cooling system piping, water boxes etc. RUBBER CLOROPRENE BI-CR-V Hot & Cold Below 100C Sea water piping, Cooling system piping, water boxes etc. RUBBER Bonding NITRILE BI-NBR-V Cold Bonding Below 100C Storage tank for petroleum oils RUBBER BUTYL BI-BUTYL-V Hot & Cold Below 125C Corosive Chemicals, Hypochlorite etc RUBBER Bonding

  6. Lining Method for Hot Bonding 1. Surface Preparation - All substrate surface to be lined is inspected visually before shotblasting. - All Surfaces to be lined shall be blasted. 2. Adhesive Application Rubber Sheet Rubber Adhesive Bonding Agent Primer Substrate/Stee l

  7. Application of the Rubber Sheet 1. Individual sheet shall be spread on the working table and edges shall be beveled to make overlap scraf joints. Overlap scraf joints shall be made so 10mm – 30 mm that the overlap follow the direction of flow. 2. Applying the lining sheet to the Rubber Sheet substrate. Substrate/Steel 3. All sheet and joints shall be checked visually and pinholes testing shall be done to detect defects. 2.5 x t 4. Rubber sheet edge shell be cut scantly at the width about 2,5t using soldering iron of knife. Rubber Sheet t 5. For joints, the length of overlap is about 10 – 30 mm for shell and flat area, and internal support and flange area will be 10 – 30 mm.

  8. Curing Procedure 1. Autoclave Cure - Steam pressure shall be kept constantly - Curing Steam pressure max 4,0 kg/cm² - Time max 4 hours 2. Exhaust Steam Cure The equipment which can not be put into autoclave shall be cured with steam at ambient pressure.

  9. Inspection Procedure 1 . Surface Cleanliness 2 . Quality of the lining and bonding materials 3 . Visual check before curing 4 . Visual check after curing 5 . Hardness Test 6 . Spark Test / Pinhole Test 7 . Bonding Strength Test

  10. Lining Method for Cold Bonding 1. Surface Preparation 2. Sheet Preparation 3. Application Rubber Sheet Rubber Sheet Adhesive Primer Substrate

  11. Inspection Procedure 1. Surface Cleanliness 2. Spark Test 3. Hardness 4. Thickness

  12. Production Facility ROTO-CURE ROLLER HEAD

  13. Laboratory Facility Our Quality Assurance procedures are based on ISO- 9001-2000/ISO-TS 16949- 2002 recommendations and cover related activities to control the manufacturing process. We have a full- Rheometer Mooney Viscosity fledged laboratory with sophisticated testing equipments for analysis of raw-materials, in-process material and finish goods. Abrasion Tester Type DIN

  14. Work Reference

  15. 15

  16. Work Reference Sea Water Pipe

  17. Work Reference

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.