StreamSmart Crossings Mike Mullen, Division of Land Resource Regulation MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION Protecting Maines Air, Land and Water Maine Department of Environmental Protection Main Office and Central Maine


slide-1
SLIDE 1

StreamSmart Crossings

Mike Mullen, Division of Land Resource Regulation

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION

Protecting Maine’s Air, Land and Water

slide-2
SLIDE 2

Maine Department of Environmental Protection

  • Main Office and Central Maine Region

28 Tyson Drive, Augusta (207)287-7688 * (800)452-1942

  • Eastern Maine Region

106 Hogan Road, Bangor (207)941-4570 * (888)769-1137

  • Southern Maine Region

312 Canco Road, Portland (207)822-6300 * (888)769-1036

  • Northern Maine Region

1235 Central Drive, Presque Isle (207)764-0477 * (888)769-1053

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION www.maine.gov/dep

slide-3
SLIDE 3

This Is A Stream If It Has:

  • A channel between defined banks

and at least 2 of the following: – Has a scoured mineral bed – Flows at least 6 months/year – Mapped on a U.S.G.S. topo map as a solid or dashed blue line – Contains fish, aquatic animals or aquatic vegetation – Is devoid of upland vegetation

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION www.maine.gov/dep

slide-4
SLIDE 4

Culvert Replacement

Exempt from permitting if:

  • Erosion controls are used
  • Does not block fish passage
  • Installed to match natural

grade to avoid drops or perching

  • Embedded in stream a

minimum of 1 foot or 25% Diameter (max 2 feet)

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION www.maine.gov/dep

slide-5
SLIDE 5

Permit By Rule (PBR)

  • Fast and easy permitting

process

  • For a project to qualify for

Permit-by-Rule, it must be designed and constructed in compliance with all applicable Chapter 305 Rules

  • Chapter 305 Section 10 covers

stream crossings (bridges, culverts, fords)

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION www.maine.gov/dep

slide-6
SLIDE 6

Stream Crossings

  • Fill slopes must be stabilized
  • 3 times the cross sectional area of the stream

channel OR accommodate 25-year storm

  • Surface water must be diverted through

vegetated buffer areas of at least 25’

  • If working in less than 3’ of water, must divert

water around work area

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION www.maine.gov/dep

slide-7
SLIDE 7

Stream Crossings - Culverts

Culverts:

  • No longer than 75 feet
  • Follow alignment and grade of stream
  • Be placed at or below streambed
  • Back fill must be compacted
  • Inlet and outlet banks must be riprapped

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION www.maine.gov/dep

slide-8
SLIDE 8

Water Management Is Critical

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION www.maine.gov/dep

Jersey Barrier Cofferdam

Rule Requires A Diversion If Working In Less Than 3’ Of Water