stakeholder meeting may 20 2020 this powerpoint
play

Stakeholder Meeting May 20, 2020 This PowerPoint presentation was - PowerPoint PPT Presentation

Stakeholder Meeting May 20, 2020 This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this


  1. Stakeholder Meeting May 20, 2020

  2. This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity other than FDOT staff is not official. Any questions can be sent to FDOT- D6PIO@dot.state.fl.us. This presentation may not be altered. 2

  3. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Contractor completed concrete pavement replacement of the three inside southbound I-95 lanes from NW 29 Street to south of NW 20 Street on Sunday, May 3. * This schedule does not reflect days added to the contract for • holidays, weather days or special events Contractor implemented continuous lane closures on northbound I-95 to complete the concrete pavement replacement of the lanes adjacent to the median from NW 20 Street to NW 29 Street. 3

  4. ONGOING LANE THREE MONTH LOOK CLOSURES AHEAD * This schedule does not reflect days added to the contract for holidays, weather days or special events ANTICIPATED LANE CLOSURES ON THE I-95 CORRIDOR: • Nighttime lane/ramp closure along I-95 between NW 8 Street and NW 29 Street • Closure hours have been adjusted based on current traffic conditions from 8 p.m. until 8 a.m. 4

  5. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Traffic shifted on westbound SR 836 from the Miami River to east of NW 17 Avenue to the left side of the roadway • Traffic shifted on eastbound SR 836 from NW 17 Avenue to the Miami River to the right side of the roadway 5

  6. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Demolition of median area on SR 836 has started at NW 12 Avenue and will be moving to the west over the Miami River • Work started in the east over court parking area and moving to the west • Demolition work currently taking place during the day with a single westbound lane closure 6

  7. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Contractor implemented a continuous closure of the outside eastbound SR 836 lane to expedite the replacement of the concrete pavement with asphalt pavement • Contractor continues Auger Cast Pile (ACP) testing program on SR 836 for the foundations of the new double decked section • Production ACP piles expected to begin in July 2020 7

  8. ONGOING LANE THREE MONTH LOOK CLOSURES AHEAD ANTICIPATED LANE CLOSURES ON SR 836 CORRIDOR: SR 836 UPCOMING CONSTRUCTION ACTIVITIES • Single and double lane/ramp closures along eastbound and westbound SR 836 • Arterial roads under SR 836 • Closure hours have been adjusted based on current traffic conditions from 8 p.m. until 8 a.m. 8

  9. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Construction of the center pier signature bridge foundations (Ongoing) • Construction of westbound outside local road bridge foundations (Ongoing) SR 836 UPCOMING CONSTRUCTION ACTIVITIES • Demolition of portions of existing eastbound I-395 • Contractor started eastbound outside local road bridge foundations 9

  10. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES The westbound I-395 ramp to northbound I-95 has been reduced from two lanes to one lane The reduction in lanes is necessary to reconstruct the section of I-95 SR 836 UPCOMING CONSTRUCTION ACTIVITIES where the eastbound SR 836 ramp and westbound I-395 ramp join I-95 The lane reduction is expected to be in place for approximately 18 months 10

  11. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events Ongoing segmental bridge column construction 11

  12. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES • Westbound MacArthur Causeway ramp lane to Biscayne Boulevard has been shifted to the left to allow for the construction of a new retaining wall on the right side Only one travel lane is available * This schedule does not reflect days added to the contract for on the ramp from the MacArthur holidays, weather days or special events Causeway to North Bayshore Drive 12

  13. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Contractor mobilized into Lot Q and to begin driving steel sheets for signature bridge arch 4 * This schedule does not reflect days added to the contract for holidays, weather days or special events ACP Completed: 335/1948 • I-395 Segmental ACP – 275/857 • I-395 Signature ACP – 60/520 • SR 836 Viaduct ACP – 0/571 13

  14. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 2 1 * This schedule does not reflect days added to the contract for holidays, weather days or special events 1 Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. There will be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street) and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur Causeway). Close Bayshore loop ramp to EB MacArthur Causeway (July 2020) 2 14

  15. ONGOING LANE THREE MONTH LOOK CLOSURES AHEAD ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR: SR 836 UPCOMING CONSTRUCTION ACTIVITIES • Lane closures along eastbound and westbound I-395 • Lane closures along Biscayne Boulevard and other arterial roadways adjacent to I-395 • I-395 to I-95 ramp closures • Closure hours have been adjusted based on current traffic conditions from 8 p.m. until 8 a.m. 15

  16. COMMUNITY OUTREACH PROJECT WEBSITE • www.i-395miami.com • Sign-up for project alerts/updates Lane closure information Upcoming construction activities Presentations • Calendar of events OUTREACH OFFICE IN THE OVERTOWN COMMUNITY • 1035 NW 3 Avenue, Miami, Florida 33136 (CLOSED AT THIS TIME) STAKEHOLDER MEETINGS • Stakeholder meetings will be held virtually until further notice, Date TBD. 16

  17. THANK YOU! www.i-395miami.com Contact: Oscar Gonzalez 786-280-0983 OGonzalez@mrgmiami.com 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend