Stakeholder Meeting May 20, 2020

slide-2
SLIDE 2

2

This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity

  • ther than FDOT staff is not official. Any questions can be sent to FDOT-

D6PIO@dot.state.fl.us. This presentation may not be altered.

slide-3
SLIDE 3

* This schedule does not reflect days added to the contract for holidays, weather days or special events

3

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

  • Contractor completed concrete

pavement replacement of the three inside southbound I-95 lanes from NW 29 Street to south of NW 20 Street on Sunday, May 3.

  • Contractor implemented continuous

lane closures on northbound I-95 to complete the concrete pavement replacement of the lanes adjacent to the median from NW 20 Street to NW 29 Street.

slide-4
SLIDE 4

* This schedule does not reflect days added to the contract for holidays, weather days or special events

4

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

ANTICIPATED LANE CLOSURES ON THE I-95 CORRIDOR:

  • Nighttime lane/ramp closure along I-95 between NW 8 Street and NW

29 Street

  • Closure hours have been adjusted based on current traffic

conditions from 8 p.m. until 8 a.m.

slide-5
SLIDE 5

5

  • Traffic shifted on westbound SR

836 from the Miami River to east

  • f NW 17 Avenue to the left side
  • f the roadway
  • Traffic shifted on eastbound SR

836 from NW 17 Avenue to the Miami River to the right side of the roadway

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-6
SLIDE 6

6

  • Demolition of median area on

SR 836 has started at NW 12 Avenue and will be moving to the west over the Miami River

  • Work started in the east over

court parking area and moving to the west

  • Demolition work currently taking

place during the day with a single westbound lane closure

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-7
SLIDE 7

7

  • Contractor implemented a

continuous closure of the outside eastbound SR 836 lane to expedite the replacement of the concrete pavement with asphalt pavement

  • Contractor continues Auger Cast

Pile (ACP) testing program on SR 836 for the foundations of the new double decked section

  • Production ACP piles expected to

begin in July 2020

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-8
SLIDE 8

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

8

ANTICIPATED LANE CLOSURES ON SR 836 CORRIDOR:

  • Single and double lane/ramp closures along eastbound and westbound

SR 836

  • Arterial roads under SR 836
  • Closure hours have been adjusted based on current traffic

conditions from 8 p.m. until 8 a.m.

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

slide-9
SLIDE 9

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

9

  • Construction of the center pier

signature bridge foundations (Ongoing)

  • Construction of westbound outside

local road bridge foundations (Ongoing)

  • Demolition of portions of existing

eastbound I-395

  • Contractor started eastbound
  • utside local road bridge

foundations

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-10
SLIDE 10

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

10

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

The westbound I-395 ramp to northbound I-95 has been reduced from two lanes to one lane The reduction in lanes is necessary to reconstruct the section of I-95 where the eastbound SR 836 ramp and westbound I-395 ramp join I-95 The lane reduction is expected to be in place for approximately 18 months

slide-11
SLIDE 11

* This schedule does not reflect days added to the contract for holidays, weather days or special events

11

Ongoing segmental bridge column construction

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

slide-12
SLIDE 12

* This schedule does not reflect days added to the contract for holidays, weather days or special events

12

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

  • Westbound MacArthur Causeway

ramp lane to Biscayne Boulevard has been shifted to the left to allow for the construction of a new retaining wall on the right side Only one travel lane is available

  • n the ramp from the MacArthur

Causeway to North Bayshore Drive

slide-13
SLIDE 13

* This schedule does not reflect days added to the contract for holidays, weather days or special events

13

ACP Completed: 335/1948

  • I-395 Segmental ACP – 275/857
  • I-395 Signature ACP – 60/520
  • SR 836 Viaduct ACP – 0/571

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

Contractor mobilized into Lot Q and to begin driving steel sheets for signature bridge arch 4

slide-14
SLIDE 14

* This schedule does not reflect days added to the contract for holidays, weather days or special events

14

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. There will be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street) and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur Causeway). Close Bayshore loop ramp to EB MacArthur Causeway (July 2020)

1 1 2 2

slide-15
SLIDE 15

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

15

ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:

  • Lane closures along eastbound and westbound I-395
  • Lane closures along Biscayne Boulevard and other arterial roadways

adjacent to I-395

  • I-395 to I-95 ramp closures
  • Closure hours have been adjusted based on current traffic

conditions from 8 p.m. until 8 a.m.

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

slide-16
SLIDE 16

16

COMMUNITY OUTREACH

PROJECT WEBSITE

  • www.i-395miami.com
  • Sign-up for project alerts/updates

Lane closure information Upcoming construction activities Presentations

  • Calendar of events

OUTREACH OFFICE IN THE OVERTOWN COMMUNITY

  • 1035 NW 3 Avenue, Miami, Florida 33136 (CLOSED AT

THIS TIME) STAKEHOLDER MEETINGS

  • Stakeholder meetings will be held virtually until further

notice, Date TBD.