spill response site assessment and remediation of a
play

Spill Response, Site Assessment and Remediation of a Significant - PowerPoint PPT Presentation

Spill Response, Site Assessment and Remediation of a Significant Gasoline Release to Land, Resolute Bay, Nunavut Challenges and Successes in the approach to remediation in a Remote Community in the Canadian Arctic RPIC Montreal 2016 Rob


  1. Spill Response, Site Assessment and Remediation of a Significant Gasoline Release to Land, Resolute Bay, Nunavut Challenges and Successes in the approach to remediation in a Remote Community in the Canadian Arctic RPIC Montreal 2016 Rob McCullough, Stantec Consulting Ltd. Nathanial Hutchinson, Anil Gupta Government of Nunavut, Petroleum Products Division January, 2016

  2. Agenda 1 Background/Initial Assessment, 2011 2 Site Assessment 2012 3 Site Remediation 2012 - Present 4 Conclusions – Challenges, Successes and Lessons Learned

  3. 1 Background Location of release • October, 2011 • Est 87,000 L of gasoline • Valve failure – day tank • overfill Areal View of Former and Current Tank Farm in Resolute, NU

  4. Site Conditions - Initial Challenges • Stantec on-site November 2011 to assess the release • 2 hours of daylight • Sub zero temperatures and multi-day blizzards • Heavy snow • Most contractors had returned to the south for the winter Location of Horizontal Tanks

  5. Horizontal AST Surface Evaluation Fuel ran down the side of the • tank and onto gravel No definitive evidence of fuel • on the frozen ground Uncertainty as to whether a • fuel spill occurred Police investigation ongoing •

  6. Snow in Catchment Basin Snow in Catchment Basin was in excess of 4 m deep and made hand assessment difficult with no heavy equipment available, limited visibility of hydrocarbons Cold temperatures mitigated vapor detection

  7. 2 Assessment Work in 2012 Snow was 2 to 3 m deep Hand excavation

  8. Rhodamine Dye Application Applied 300 L of dye to the surface/subsurface

  9. Test Pits in Catchment Basin Test pits Test pits excavated in catchment basin to assess the location of the fuel in the ice and snow

  10. Test Pits in Catchment Basin (2) • Assessment of ice below the snow for the presence of gasoline • Fingerprinting of fuel from samples

  11. Ice with Fuel in Catchment Basin Clean Ice Ice with Fuel

  12. Melted Ice/Snow Up to 30 % gasoline by volume in melted sample Gasoline Water

  13. Wildlife Hazards Bear Encounters Up to 30 % gasoline by volume in melted sample

  14. Wildlife Hazards Bear Encounters Up to 30 % gasoline by volume in melted sample

  15. Wildlife Hazards Bear Encounters Up to 30 % gasoline by volume in melted sample

  16. Third Phase of Assessment, July 2012 Test pits excavated across tank farm area and down gradient locations

  17. Third Phase of Assessment, July 2012 Test pits excavated across sea lift staging area down Test pits gradient of site Very difficult to differentiate contaminants in soil Staging area

  18. 3 Site Remediation

  19. Silt Fence at High Water Mark

  20. Ocean Boom in Resolute Bay

  21. Cut Off Trench with HDPE Liner HDPE 60 mil welded liner

  22. Perforated Drain Pipe in Trench h c n e r T f f o - t u C

  23. Trenches Dug in Old Tank Farm Collection of water and phase separated product

  24. On-Site Containment Cell Approximately 5000 m 3 of impacted soil placed in on-site constructed cell

  25. On-Site Containment Cell (2) 60 mil HDPE liner welded in the field

  26. Remedial Excavation at ASTs • Residual dye below tanks • Permafrost bowl under tanks

  27. Main Excavation at Tank Farm Original AST location Excavated to permafrost across impacted zone

  28. Main Excavation at Tank Farm (2) Berm from original tank farm lined and keyed to permafrost

  29. Excavation on Road Exposed shale Bedrock

  30. Backfilling of Road Excavation

  31. Backfilling of Tank Farm Excavation

  32. Reinstatement of ASTs

  33. Remediation Support Equipment Generator, frost-biter, and fuel for equipment

  34. GAC Water Treatment System

  35. Effluent from Water Treatment

  36. 4 Lessons Learned • Sometimes very difficult to assess a release in Arctic conditions even when it should be obvious • Many Hazards to be aware of: cold temperatures, communications, wildlife, safety • Equipment available in the south is not necessarily available in remote Arctic location, need to improvise • Time lag on results and thus decisions • Very expensive in all aspects

  37. 4 Conclusions Tea + -50 o C = Iced Tea

  38. Acknowledgements • Nathanial Hutchinson, Anil Gupta, Government of Nunavut, Petroleum Products Division • Kristi Lowe, Director of Environmental Protection, Department of the Environment Government of Nunavut • Patricio Fuentes, Regional Project Manager, Community and Government Services, Baffin Region, Government of Nunavut • Patrick Kramers, Curtis Didham, Environmental Enforcement Directorate, Enforcement Branch, Environment Canada

  39. Questions? Robert McCullough, B.E.S., CET., CESA., EP Principal Stantec Dartmouth (902) 468-7777 Robert.mcculough@stantec.com

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend