in in reducing the cost of f fl flood defence schemes Paul - - PowerPoint PPT Presentation

in in reducing the cost of f fl flood defence
SMART_READER_LITE
LIVE PREVIEW

in in reducing the cost of f fl flood defence schemes Paul - - PowerPoint PPT Presentation

The role of f geotechnical engineering in in reducing the cost of f fl flood defence schemes Paul Quigley and Paul Doherty pquigley@gdgeo.com and pdoherty@gdgeo.com Overview Alternative solutions for Flood Defence Schemes Plastic


slide-1
SLIDE 1

The role of f geotechnical engineering in in reducing the cost of f fl flood defence schemes

Paul Quigley and Paul Doherty pquigley@gdgeo.com and pdoherty@gdgeo.com

slide-2
SLIDE 2

Overview

www.gdgeo.com

  • Alternative solutions for Flood Defence Schemes
  • Plastic sheet piles
  • Geosynethics and membranes
  • Case study – River Dargle
  • Contracts
  • Some ideas and recommendations
slide-3
SLIDE 3

Plastic sheet piles

www.gdgeo.com

  • Suitable where limited cut-off required.
  • GDG has used this solution to provide low cost

flood protection

  • Driven piles or excavate trench and backfill

around sheet pile. Need to be careful about the back fill materials.

  • Used successfully in UK
  • Guidance provided in paper on durability
slide-4
SLIDE 4

Embankments

www.gdgeo.com

  • Footprint of Embankments can be

larger than desired.

  • Embankments need to prevent

seepage during flood events

  • GDG has used geotextile such as

ParadrainTM to reinforce cohesive materials

  • Geomembranes to provide cut-off in

granular materials.

slide-5
SLIDE 5

Case study – River Dargle

www.gdgeo.com

slide-6
SLIDE 6

Ground conditions

www.gdgeo.com

  • Stability Modelling
  • Seepage Analysis

Deemed Critical

  • Additional boreholes

drilled and piezometers installed with dataloggers to investigate tidal influences.

slide-7
SLIDE 7

Flood wall analysis

www.gdgeo.com

  • 1

1 2 3 4 5 6 12 18 24 30 36 Head (m) Time (hours)

The change in Head (m) over time (hours)

  • 0.2

0.2 0.4 0.6 1

Low River Level -0.20 mOD Gravel Design Flood Level 3.80 mOD Gravel Silt Swale River Wall Flood Defence Wall Golf Course Road Hight Tide 1.54 mOD

0.32512 m³/days . 2 8 5 2 9 m ³ / d a y s

Distance (m)

5 10 15 20 25 30 35 40 45 50 55

Elevation (m)

  • 9.55
  • 8.55
  • 7.55
  • 6.55
  • 5.55
  • 4.55
  • 3.55
  • 2.55
  • 1.55
  • 0.55

0.45 1.45 2.45 3.45 4.45 5.45

slide-8
SLIDE 8

Contract structures

www.gdgeo.com

slide-9
SLIDE 9

Design fees

www.gdgeo.com

  • Typical contracts tendered
  • n lump sum for Stage I

and II & percentage of the construction costs for Stages III to V

  • Percentage banded on

contract value

  • High risk for designers

Plot from Engineers Fees, 2017

slide-10
SLIDE 10

Impact on solutions

www.gdgeo.com

  • Consider 75m to 100m long section

where sheet piles may be required

  • Bedrock at 22.5m below ground

level

  • Made ground to 4m bgl over glacial

deposits.

  • Assume that the reinforced

concrete wall on the surface costs the same.

slide-11
SLIDE 11

Conservative design

www.gdgeo.com

Item Quantity Unit Rate Total Mobilisation

  • f plant and

labour 1 Sum €8,000.00 €8,000 Site moves 2 Sum €2,500.00 €5,000 Piles (AZ 26- 700 Z) 330750 kg €0.95/kg €315,536 Installation 2250 m2 €20.00/m2 €45,000 Burning piles 100 m €20.00/m €2,000 Total cost €375,536

1.

  • 1. In

Install ll sh sheet pile iles to

  • 22

22.5 .5m in into bedrock 2.

  • 2. Sh

Sheet pile iles over 10 100m se section

slide-12
SLIDE 12

Value Engineering

www.gdgeo.com Item Quantity Unit Rate Total Additional GI 1 Sum €20,000 €20,000 Mobilisation of plant and labour 1 Sum €8,000.00 €8,000 Site moves 2 Sum €2,500.00 €5,000 Piles (AZ 26-700 Z) 99225 kg €0.95/kg €94,661 Installation rate 675 m2 €20.00/m2 €13,500 Burning piles 75 m €20.00/m €1,500 Total cost €142,661

1.

  • 1. Undertake detail

iled geotechnical l ass assessment 2.

  • 2. Valu

alue engin ineer ext xtent an and depth of

  • f sh

sheet pile iles to

  • 9m

9m 3.

  • 3. No

No ac account of

  • f costs ass

associated with ith easi asier in install llation

slide-13
SLIDE 13

Comparison between methods

www.gdgeo.com

Capital costs Design costs Total cost Conservative solution €375,536 €13,144 €388,679 Optimised solution €142,661 €4,293 €146,954 Difference €232,875 (€8,851) €241,725

slide-14
SLIDE 14

Alternatives?

www.gdgeo.com

  • Look at how road projects are procured

and designed?

  • Split contracts after Stage II?
  • Consider Design and Build options to drive

capital costs down?

  • Design effort driven towards providing

value to both Employer and Contractor

  • More oversight of the design process
  • Optimise programme to complete

schemes quicker to save money

  • Do GI and GIR early in project to identify

issues and potential solutions

slide-15
SLIDE 15

Conclusions

www.gdgeo.com

  • Geotechnical Engineers can deliver optimised Flood Defence

solutions – retaining walls, embankments, seepage analyses. Time and effort spent on design can be very rewarding.

  • The value of a useful ground model is evident in optimising design
  • solutions. Ground model must be developed to understand the

inherent variability in the ground. Best to undertake GI in advance

  • f preliminary design.
  • Value Engineering options available for Flood Defence schemes.
  • Current contract structure results in squeezing design fees and

design effort, risky for consultants and rewards expensive design solutions.

  • Design and Build has potential to provide robust solutions, reward

innovation and deliver lower capital.

slide-16
SLIDE 16

www.gdgeo.com

Thank you