surface remediation
play

Surface Remediation Overview and Key Concerns Surface Remediation - PowerPoint PPT Presentation

Surface Remediation Overview and Key Concerns Surface Remediation Primary components Baker Creek Tailings and sludge ponds Pits Contaminated soil Buildings and roadways Others Site Overview Site Overview Site


  1. Surface Remediation Overview and Key Concerns

  2. Surface Remediation • Primary components – Baker Creek – Tailings and sludge ponds – Pits – Contaminated soil – Buildings and roadways – Others

  3. Site Overview

  4. Site Overview

  5. Site Overview

  6. Site Overview

  7. Site Boundary

  8. Baker Creek

  9. Baker Creek

  10. Baker Creek • Baker Creek flows through the site – Enters above Baker Pond and exits into Back Bay

  11. Baker Creek • Both “natural” and “constructed” reaches

  12. Baker Creek

  13. Baker Creek

  14. Baker Creek • Reach 4 flowed over arsenic stopes – Relocated and stabilized in 2006 4

  15. Baker Creek • Problem sections of Baker Creek in flood – Narrow diversions above C1 pit and A2 pit 3 1 4

  16. Baker Creek • High value habitat – Reach 4 – Grayling spawning – Reach 6 – Temperature and nutrients 3 1 4 6

  17. Baker Creek • Other fish habitat and uses – Every reach is now known to support some fish uses 3 2 1 4 5 6

  18. Baker Creek • Arsenic in sediments – Reach 2, 5, 6 – But other reaches also have areas of contaminated sediments 3 2 1 4 5 6

  19. Baker Creek • Water quality – Arsenic in Baker Creek comes from water treatment plant – And from upstream 220 kg/yr 3 2 1 4 5 6 300 kg/yr

  20. Baker Creek • Key Concerns – Physically impacted in mine area – Water quality – Sediment quality – Concerns for fish, muskrat and humans? – Disturbance from sediment remediation?

  21. Tailings • South, Central & North Ponds • Northwest Pond

  22. Tailings • Foreshore tailings • Offshore tailings

  23. Tailings • North, Central & South Ponds – 7M tonnes tailings covering 51 ha – Sludge ponds

  24. Tailings

  25. Tailings

  26. Tailings • Seven dams around Original Impoundments • Up to 20 m high • Inspected annually by geotechnical engineer

  27. Tailings • Northwest Pond – 6.5M tonnes tailings covering 44 ha

  28. Tailings

  29. Tailings

  30. Tailings • Six dams around Northwest Pond • 15-20 m high • Well engineered and constructed • Inspected annually by geotechnical engineer

  31. Tailings • Tailings are fine silty powder • About 2,000-4,000 mg/kg arsenic

  32. Tailings

  33. Sludge Ponds • Settling pond and polishing pond – Water treatment residuals

  34. Tailings & Sludge Ponds • Key concerns – Dust – Surface exposure of arsenic – Lack of vegetation – Seepage

  35. Pits • Five major pits • A2, A1, C1, B2, B1

  36. Pits

  37. Pits • Five large pits and three small pits – Table of pits and volumes Existing Void Pit Volume 1 (m 3 ) Pit Plan Area (m 2 ) A1 757,000 48,000 A2 479,000 32,000 C1 372,000 31,000 B1 331,000 22,000 B2 203,000 20,000 B3 56,000 9,000 B4 10,000 4,000 Brock 10,000 2,000 TOTALS 2,218,000 158,000 1 Volume to spill point elevation

  38. Pits • Key concerns – Safety • Steep pit walls are a potential hazard to people • Long-term stability of stopes directly below pits • Openings to surface – If Baker Creek channel issues not addressed • Flooding could allow water into pits and underground

  39. Contaminated Soils

  40. Contaminated Soils • Key concerns – Land use vs soil contamination levels – Soil quality • Human risk – Inhalation / ingestion – Arsenic uptake by vegetation • Wildlife – Disturbance related to soil remediation?

  41. Buildings • Buildings – In general all buildings on the site will be cleaned and demolished – Five areas with different “issues”

  42. Buildings • Townsite Area – City interested in four Townsite homes

  43. Buildings • Townsite and A-Shaft – NWT Mine Heritage Society interested in Community Hall – A-Shaft is a safety hazard

  44. Buildings • Mill Area – Significant arsenic and asbestos contamination – Requires careful sequence of hazardous material removal, demolition and disposal

  45. Buildings

  46. Buildings • Tailings Retreatment, Effluent Treatment, and Akaitcho Shaft – Some short-term uses – Then demolition and removal

  47. Buildings • Key concerns – Many remaining buildings contain hazardous materials which could pose risks to workers and environment during demolition if not controlled – Decontamination will generate hazardous wastes requiring safe disposal (either on-site or special facility off-site) – Demolition will generate a large volume of non- hazardous waste requiring on-site disposal

  48. Roadways

  49. Roadways • Key concerns – Some road sections contaminated • Mine waste rock containing arsenic – Some roadways impede site drainage • Local flooding problems – Many roadways not required for future uses • Occupied land can be rehabilitated

  50. Other • Remediation will create other surface components

  51. Other • Arsenic trioxide management areas

  52. Other • Water management system

  53. Other • Soil borrow sources

  54. Other • Landfill ???

  55. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend