SAFETY CASE - The Role of Contractual Due Diligence Specifications - - PowerPoint PPT Presentation

safety case
SMART_READER_LITE
LIVE PREVIEW

SAFETY CASE - The Role of Contractual Due Diligence Specifications - - PowerPoint PPT Presentation

SAFETY CASE - The Role of Contractual Due Diligence Specifications for an Engineering Project. Townsville Regional Group Geoff Hurst 0426 881 322 ghurst10@live.com Background Need for a new approach Risk Management in the construction,


slide-1
SLIDE 1

SAFETY CASE -

The Role of Contractual Due Diligence Specifications for an Engineering Project.

Townsville Regional Group

Geoff Hurst 0426 881 322 ghurst10@live.com

slide-2
SLIDE 2

Risk Management in the construction, building, infrastructure, service, and manufacturing industries is applied with varying interpretation across businesses and sites within an enterprise.

Background – Need for a new approach

slide-3
SLIDE 3

Risk Management is understanding the past to predict the future

Background – Need for a new approach

slide-4
SLIDE 4

This is

  • ften

and largely a cost contingency approach.

Background – Need for a new approach

slide-5
SLIDE 5

This is

  • ften

and largely a cost contingency approach. We often are very good at predicting the numbers.

Background – Need for a new approach

slide-6
SLIDE 6

This is

  • ften

and largely a cost contingency approach. We often are very good at predicting the numbers.

Background – Need for a new approach

ETTO

Efficiency – Thoroughness Trade Off

slide-7
SLIDE 7

The opportunity however is to identify all the risks and deal with them as

  • pportunities.

Background – Need for a new approach

slide-8
SLIDE 8

2006

Procurement

slide-9
SLIDE 9
  • Does not mean that cheapest is best.
  • Comparative analysis of all relevant costs & benefits
  • Consider the whole procurement cycle
  • Include costs associated with WHS

Commonwealth Procurement Guidelines

The future – Value for money

slide-10
SLIDE 10

Requires

  • ‘looking forward’ in order to consider hazards through the

life of the item, as well as

  • ‘looking back’ to reveal past experiences that might

inform current decision making.

Commonwealth Procurement Guidelines

The future – Safe Design

slide-11
SLIDE 11

What are we Really Trying to do?

slide-12
SLIDE 12

Hold your Breath and Bury your head

Miss out on the benefits

slide-13
SLIDE 13

OR Bury your project

Miss out on the benefits

slide-14
SLIDE 14

OR Bury your project

Miss out on the benefits

slide-15
SLIDE 15

It is an often held view that Risk management costs time and money.

We do it because we have to

slide-16
SLIDE 16

Good Risk Management is Gold

slide-17
SLIDE 17

MANAGEMENT & LEADERSHIP

Geoff Hurst after Bently

Creating a Risk Management Culture

slide-18
SLIDE 18

MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

Geoff Hurst after Bently

Creating a Risk Management Culture

slide-19
SLIDE 19

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

Geoff Hurst after Bently

Creating a Risk Management Culture

slide-20
SLIDE 20

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

Geoff Hurst after Bently

Creating a Risk Management Culture

slide-21
SLIDE 21

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

Geoff Hurst after Bently

Creating a Risk Management Culture

slide-22
SLIDE 22

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

COMMITMENT Geoff Hurst after Bently

Creating a Risk Management Culture

slide-23
SLIDE 23

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

COMMITMENT AWARENESS Geoff Hurst after Bently

Creating a Risk Management Culture

slide-24
SLIDE 24

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

COMMITMENT CULTURE AWARENESS Geoff Hurst after Bently

Creating a Risk Management Culture

slide-25
SLIDE 25

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

METHOD COMMITMENT CULTURE AWARENESS Geoff Hurst after Bently

Creating a Risk Management Culture

slide-26
SLIDE 26

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

METHOD COMMITMENT RESOURCES CULTURE AWARENESS Geoff Hurst after Bently

Creating a Risk Management Culture

slide-27
SLIDE 27

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

METHOD COMMITMENT RESOURCES CULTURE AWARENESS CONTINUOUS IMPROVEMENT Geoff Hurst after Bently

Creating a Risk Management Culture

slide-28
SLIDE 28

SYSTEMS & PROCEDURES MANAGEMENT & LEADERSHIP PARTICIPATION INVOLVEMENT & CONSULTATION

METHOD COMMITMENT RESOURCES CULTURE AWARENESS CONTINUOUS IMPROVEMENT Geoff Hurst after Bently

Risk Management is a Socio-technical System

slide-29
SLIDE 29

Management Model

slide-30
SLIDE 30

Reason’s framework

Creating a Risk Culture

  • Informed culture
  • Reporting culture
  • Just culture
  • Flexible culture
  • Learning culture

Framework for engineering a safe culture - Reason (1998)

slide-31
SLIDE 31

Creating a Risk Culture

  • 1. VULNERABLE
  • 2. REACTIVE
  • 3. COMPLIANT
  • 4. PROACTIVE
  • 5. GENERATIVE

ORGANISATIONAL CULTURE STEPS

slide-32
SLIDE 32

Creating a Risk Culture

Learning Reporting Just Informe d Trust Flexible Flexible

slide-33
SLIDE 33

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility

The Steps to a Risk Culture

slide-34
SLIDE 34

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility

The Steps to a Risk Culture

slide-35
SLIDE 35

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility

The Steps to a Risk Culture

slide-36
SLIDE 36

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility

The Steps to a Risk Culture

slide-37
SLIDE 37

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility

The Steps to a Risk Culture

slide-38
SLIDE 38

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility

The Steps to a Risk Culture

slide-39
SLIDE 39

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility

The Steps to a Risk Culture

slide-40
SLIDE 40

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility

The Steps to a Risk Culture

slide-41
SLIDE 41

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility Generative: Everyone is involved

The Steps to a Risk Culture

slide-42
SLIDE 42

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility Generative: Everyone is involved

Geoff Hurst

ORGANISATIONAL CULTURE STEPS

The Steps to a Risk Culture

slide-43
SLIDE 43

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility Generative: Everyone is involved

How is simple

Geoff Hurst

ORGANISATIONAL CULTURE STEPS

slide-44
SLIDE 44

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility Generative: Everyone is involved

Geoff Hurst

ORGANISATIONAL CULTURE STEPS

How is simple

slide-45
SLIDE 45

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility Generative: Everyone is involved

Geoff Hurst

ORGANISATIONAL CULTURE STEPS

How is simple

slide-46
SLIDE 46

Vulnerable:

Why do anything?

Reactive: Have to do something Compliant: Important to follow rules Proactive: Belief and serious responsibility Generative: Everyone is involved

Geoff Hurst

ORGANISATIONAL CULTURE STEPS

How is simple

slide-47
SLIDE 47

Understanding Risk Culture

slide-48
SLIDE 48

Understanding Risk Culture

slide-49
SLIDE 49

VULNERABLE

Understanding Risk Culture

slide-50
SLIDE 50

VULNERABLE REACTIVE

Understanding Risk Culture

slide-51
SLIDE 51

VULNERABLE REACTIVE COMPLIANT

Understanding Risk Culture

slide-52
SLIDE 52

VULNERABLE REACTIVE COMPLIANT PROACTIVE

Understanding Risk Culture

slide-53
SLIDE 53

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-54
SLIDE 54

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-55
SLIDE 55

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-56
SLIDE 56

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-57
SLIDE 57

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-58
SLIDE 58

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-59
SLIDE 59

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-60
SLIDE 60

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-61
SLIDE 61

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-62
SLIDE 62

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-63
SLIDE 63

VULNERABLE REACTIVE COMPLIANT PROACTIVE GENERATIVE

Understanding Risk Culture

slide-64
SLIDE 64

Statutes - Acts Regulations Common Law Codes Formal Standards Industry Standards Body of Knowledge Guidance notes Operating manuals Maintenance manuals Procedure manuals Custom and practice Practices and rules

WHS Law

slide-65
SLIDE 65

The Project Life cycle

Deloitte

slide-66
SLIDE 66

EA Safer Construction Guideline

slide-67
SLIDE 67

CLIENT

EA Safer Construction Guideline

slide-68
SLIDE 68

CLIENT

Designer

EA Safer Construction Guideline

slide-69
SLIDE 69

CLIENT

Designer

EA Safer Construction Guideline

Constructor

slide-70
SLIDE 70

CLIENT

Designer

EA Safer Construction Guideline

Constructor

TRADITIONAL PROJECT

slide-71
SLIDE 71

CLIENT

Constructor Designer

EA Safer Construction Guideline

slide-72
SLIDE 72

CLIENT

Constructor Designer

EA Safer Construction Guideline

slide-73
SLIDE 73

CLIENT

Constructor Designer 3rd Party Design Review

EA Safer Construction Guideline

slide-74
SLIDE 74

CLIENT

Constructor Designer 3rd Party Design Review

EA Safer Construction Guideline

slide-75
SLIDE 75

Occupier Operator

CLIENT

Constructor Designer 3rd Party Design Review

EA Safer Construction Guideline

slide-76
SLIDE 76

Occupier Operator

CLIENT

Constructor Designer 3rd Party Design Review

EA Safer Construction Guideline

slide-77
SLIDE 77

Occupier Operator

CLIENT

Constructor Designer 3rd Party Design Review

EA Safer Construction Guideline

slide-78
SLIDE 78

The Project Life cycle

Deloitte

slide-79
SLIDE 79

The Project Life cycle – 4 Stages:

  • 1. Planning

After Deloitte

slide-80
SLIDE 80

The Project Life cycle – 4 Stages:

  • 1. Planning
  • 3. Construction

After Deloitte

slide-81
SLIDE 81

The Project Life cycle – 4 Stages:

  • 1. Planning
  • 3. Construction
  • 4. Post Construction

After Deloitte

slide-82
SLIDE 82

The Project Life cycle – 4 Stages:

  • 1. Planning
  • 2. Design
  • 3. Construction
  • 4. Post Construction

After Deloitte

slide-83
SLIDE 83

83

slide-84
SLIDE 84

Office of the Federal Safety Commissioner

8 PRINCIPLES

1.Commitment to a Safety Culture 2.Demonstrate Safety Leadership 3.Develop cooperative relationships 4.Promote Design for Safety 5.Communicate Safety Information 6.Manage Safety Risks 7.Continuously Improve Safety Performance 8.Entrench Safety Practices

slide-85
SLIDE 85

The Project Life cycle

Planning Design Construction Post Construction Construction Principle 1. Commitment to a Safety Culture . Principle 2. Demonstrate Safety Leadership . Principle 3. Develop cooperative relationships . Principle 4. Promote Design for Safety . Principle 5. Communicate Safety Information . Principle 6. Manage Safety Risks . Principle 7. Continuously Improve Safety Performance Principle 8. Entrench Safety Practices . After Deloitte

slide-86
SLIDE 86

The Project Life cycle

Planning Design Construction Post Construction Construction Principle 1. Commitment to a Safety Culture . Principle 2. Demonstrate Safety Leadership . Principle 3. Develop cooperative relationships . Principle 4. Promote Design for Safety . Principle 5. Communicate Safety Information . Principle 6. Manage Safety Risks . Principle 7. Continuously Improve Safety Performance Principle 8. Entrench Safety Practices . After Deloitte

slide-87
SLIDE 87

2000

The Law

slide-88
SLIDE 88

2000

The Law

slide-89
SLIDE 89

2000 2004

The Law

slide-90
SLIDE 90

2000 2004 2010

The Law

slide-91
SLIDE 91

2000 2004 2010 2012

The Law

slide-92
SLIDE 92

2000 2004 2010 2012

The Law

slide-93
SLIDE 93

Background – Safe Design

PERSONS CONDUCTING A BUSINESS OR UNDERTAKING Must:

  • Provide appropriate signage
  • Provide the WHS management plan
  • Ensure compliance with regulations
  • Manage risks re: materials, plant, traffic, essential services.
  • Ensure provision, compliance, revision, maintenance of the SWMS
  • Manage risks to health and safety during excavation work
  • Comply with WHS Regulations regarding the excavation of trenches
  • Provide general construction induction training
slide-94
SLIDE 94

2006

STEP 1: Planning STEP 2: Preparing to approach the market STEP 3: Evaluating submissions STEP 4: Contract negotiation and award STEP 5: Contract management STEP 6: Termination/transition STEP 7: Contract evaluation

Procurement

slide-95
SLIDE 95

Contractor Management Phases

This framework for Contractor Management simplified into 4 stages.

2

Selection

3

Implementation

4

Review

1

Pre-selection

slide-96
SLIDE 96

Contractor Management Framework

2

Selection

3

Implementation

4

Review

1

Pre-selection

Project/contract design/definition and specification of compliance requirements

slide-97
SLIDE 97

Contractor Management Framework

2

Selection

3

Implementation

4

Review

1

Pre-selection

Project/contract design/definition and specification of compliance requirements Review of contractor proposals, standards and references.

slide-98
SLIDE 98

Contractor Management Framework

2

Selection

3

Implementation

4

Review

1

Pre-selection

Project/contract design/definition and specification of compliance requirements Review of contractor proposals, standards and references. Monitoring/Supervising & recording of contractor on the job compliance and performance.

slide-99
SLIDE 99

Contractor Management Framework

1

Pre-selection

Project/contract design/definition and specification of compliance requirements

2

Selection

Review of contractor proposals, standards and references.

3

Implementation

Monitoring/Supervising & recording of contractor on the job compliance and performance.

4

Review

Review of contractor

  • verall compliance

and performance.

slide-100
SLIDE 100

Contractor Management Framework

1

Pre-selection

Project/contract design/definition and specification of compliance requirements

2

Selection

Review of contractor proposals, standards and references.

3

Implementation

Monitoring/Supervising & recording of contractor on the job compliance and performance.

4

Review

Review of contractor

  • verall compliance

and performance.

slide-101
SLIDE 101

Contractor Management POLICY BASICS

Typical

2

Selection

3

Implementation

1

Pre-selection

4

Review

Minor Contract

Phase OUTCOMES

Major Contract

OR STANDARD of COMPLIANCE Induction Supervision Inspection Consider OHS Outcomes and safety issues for consideration in future contract work. Verify satisfaction and record.

slide-102
SLIDE 102

Contractor Management Flow Chart

Major Contract Minor Contract Value > $100k OR Duration > 12 months OR Risk – High Risk Work OR Complexity – Sub-contract YES No Pre-design – Facts and contract Schematic design – Hazard identification Design Development – Hazard Assessment and control

1

Pre-selection

Project/contract design/definition and specification of compliance requirements

In Consultation with users

slide-103
SLIDE 103

Contractor Management - Project Risk

1

Pre-selection

Project/contract design/definition and specification of compliance requirements

slide-104
SLIDE 104

Contractor Management – Evaluating Submissions

1

Pre-selection

Project/contract design/definition and specification of compliance requirements

  • Examine the Safety Management System
  • Verify the operation of the Safety Management System:

Third party certification and examination

  • Evaluate safety performance:

Infringements, fines or improvement notices

  • Conduct meetings with the contractor to confirm their

understanding of contract WHS requirements and their ability to comply/respond

slide-105
SLIDE 105

Contractor Management Decision Tree

No Accredited OHSMS Yes No OHS Coordination plan Acceptable No OHSMS Questionnaire Acceptable No Project Risk Assessment Acceptable

2

Selection

Review of contractor proposals, standards and references. Major Contract Site Access Permitted Contractor not acceptable

slide-106
SLIDE 106

No Accredited OHSMS Yes Optional OHS Coordination plan Acceptable No

OHSMS Questionnaire Evaluation

Acceptable No Project Risk Assessment Acceptable Site Access Permitted Minor Contract Resubmit Checklist

Contractor Management Decision Tree

2

Selection

Review of contractor proposals, standards and references. It is up to the Project managers discretion as to the level of information they require from the contractor

slide-107
SLIDE 107

Contractor Management Decision Tree

Induction Supervision Inspection

3

Implementation

Monitoring/Supervising & recording of contractor on the job compliance and performance. High Risk Work Construction Work YES No Type of contract & Contractor High Risk Work Construction Work YES No Type of contract & Contractor High Risk Work Construction Work YES No Type of contract & Contractor

slide-108
SLIDE 108

INDUCTION, TRAINING & SUPERVISION

slide-109
SLIDE 109

Contractor Management Decision Tree

Induction

High Risk Work Construction Work YES No Type of contract & Contractor

  • Contractors shall complete an OHS induction.

The extent of induction shall be determined for each contract and may include:

  • Outline of the Business OH&S program, including relevant policies

and procedures;

  • Provision of Contractor OH&S guidelines;
  • Confirmation of risk assessment control measures; and
  • Recorded on the Contractor Induction Form

For construction contracts covered by regulations provide construction induction training

  • Contractors shall complete an OHS induction.

The extent of induction shall be determined for each contract and may include:

  • Outline of the Business OH&S program, including relevant policies

and procedures;

  • Provision of Contractor OH&S guidelines;
  • Confirmation of risk assessment control measures; and
  • Recorded on the Contractor Induction Form

AND Provide construction induction training

slide-110
SLIDE 110

INDUCTION, TRAINING & SUPERVISION

Adequate supervision must be provided, taking into account where workers are unfamiliar with the site or the nature of the work. Workers in a supervisory role (e.g. leading hand or foreman) should be trained and authorised to ensure the work is carried out in accordance with relevant policies, procedures and the SWMS.

slide-111
SLIDE 111

Contractor Management Decision Tree

Supervision

High Risk Work Construction Work YES No Type of contract & Contractor To ensure:

  • Compliance with OH&S policies and procedures;
  • Conformance with the project risk assessment and OH&S plans;
  • Compliance with OH&S legislation.

The extent of supervision will depend on a number of factors associated with the works including:

  • Nature of hazards/risks;
  • Level of interaction with other parties;
  • Duration of contract; and
  • High risk tasks.

For OHS breaches Project Manager shall notify the contractor. Where an issue is considered to be significant in terms of serious injury or loss of life, the General or Project Manager may suspend the work until the issue is adequately resolved. Non Conformances shall be recorded by the Project Manager and issued to the Contractor to rectify. Upon correction, the Project Manager shall sign the form to verify completion.

slide-112
SLIDE 112

Contractor Management Decision Tree

Supervision

High Risk Work Construction Work YES No Type of contract & Contractor The Project Manager shall ensure that the contractor:

  • Complete a project risk assessment prior to commencing (for specific

works that may pose a risk to OH&S);

  • Holds a current licence(s) and/or qualifications (if required);
  • Performs work on site safely;
  • Maintains equipment to an appropriate standard; and
  • Performs works in accordance with appropriate legislation and

standards; Project OH&S Coordination Plan Principal contractors shall be required to prepare, communicate and maintain a OH&S coordination plan (Coordination Plan) including:

  • Specific OHS responsibilities
  • OHS Coordination including any arrangements for the management of

OHS incidents

  • Site safety rules and communication
  • Coordination Plan available for inspection. and
  • Everyone on site is aware of the Coordination Plan
  • Project Signage to be displayed for contracts > $250k
slide-113
SLIDE 113

Contractor Management Decision Tree

Inspection

High Risk Work Construction Work YES No Type of contract & Contractor Auditing shall be conducted on a scheduled and random basis. To ensure:

  • Compliance with OH&S policies and procedures;
  • Conformance with the project risk assessment and OH&S plans;
  • Compliance with OH&S legislation.
slide-114
SLIDE 114

Contractor Management Decision Tree

Induction Supervision Inspection

3

Implementation

Monitoring/Supervising & recording of contractor on the job compliance and performance. High Risk Work Construction Work YES No Type of contract & Contractor High Risk Work Construction Work YES No Type of contract & Contractor High Risk Work Construction Work YES No Type of contract & Contractor

slide-115
SLIDE 115

Contractor Management Decision Tree

4

Review

Review of contractor

  • verall compliance

and performance. Persons responsible for receiving goods or services shall have available to them the particular standard or specification referred to in the order or supply request. Verification: The person receiving the goods or services shall complete the Purchased Goods Evaluation Checklist. The local health and safety representatives may need to be involved. Keep records: Forms, purchase orders, risk assessments, and any information provided by the supplier on goods purchased. All identified risks need to be entered on the Risk Register. An OHS Purchased Goods Evaluation Checklist shall be completed upon receiving purchased goods.

slide-116
SLIDE 116

Villa Maria 116

Project Design Stage Risk Management Worksheet

slide-117
SLIDE 117

117

Contractor OHSMS Worksheet

slide-118
SLIDE 118

118

Contractor OHSMS Worksheet

slide-119
SLIDE 119

119

Contractor OHSMS Worksheet

slide-120
SLIDE 120

Contractor Selection Criteria

Commonwealth Procurement Guidelines

slide-121
SLIDE 121

Contractor Selection Criteria

Commonwealth Procurement Guidelines

slide-122
SLIDE 122

Villa Maria 122

Implementation Risk Management Worksheet

slide-123
SLIDE 123

123

Project Review Risk Management Worksheet

slide-124
SLIDE 124

124

Contractor – Consultant Register

slide-125
SLIDE 125

Example Risk Matrix

slide-126
SLIDE 126

Example Risk Matrix

Supplemented with Risk Scores

slide-127
SLIDE 127

Assessment of Tenders

Blank Risk Summary Table

slide-128
SLIDE 128

Assessment of Tenders

Example of populated Risk Summary Table Tender is for $27,000 over 5 days with a risk rating of 18.

slide-129
SLIDE 129

Mobile Crane Collapse

slide-130
SLIDE 130

Mobile Crane Collapse

slide-131
SLIDE 131

131

Mobile Crane Collapse

slide-132
SLIDE 132

132

slide-133
SLIDE 133

133

Mobile Crane Collapse

slide-134
SLIDE 134

134

slide-135
SLIDE 135

135

Mobile Crane Collapse

slide-136
SLIDE 136

136

Mobile Crane Collapse

slide-137
SLIDE 137

137

Mobile Crane Collapse

slide-138
SLIDE 138

138

Mobile Crane Collapse

slide-139
SLIDE 139

139

Mobile Crane Collapse

slide-140
SLIDE 140

140

Mobile Crane Collapse

slide-141
SLIDE 141

141

Mobile Crane Collapse

slide-142
SLIDE 142

Safety Case Guideline, 3rd Edition

– How to engineer safety due diligence under the provisions of the Model WHS Act,

Geoff Hurst 0426 881 322 ghurst10@live.com

slide-143
SLIDE 143

143

slide-144
SLIDE 144

144

slide-145
SLIDE 145

145

slide-146
SLIDE 146

Statutes - Acts Regulations Common Law Codes Formal Standards Industry Standards Body of Knowledge Guidance notes Operating manuals Maintenance manuals Procedure manuals Custom and practice Practices and rules

WHS Law and the Safety Case

slide-147
SLIDE 147

Management of Risks

17 Management of risks A duty imposed on a person to ensure health and safety requires the person: (a) to eliminate risks to health and safety, so far as is reasonably practicable; and (b) if it is not reasonably practicable to eliminate risks to health and safety, to minimise those risks so far as is reasonably practicable.

slide-148
SLIDE 148

Legal Implications

  • Penalties
  • Negligence
  • Causation
  • Foreseeability
  • Preventability
  • Reasonableness
  • Due Diligence

Due diligence – The effort made by an

  • rdinarily prudent or

reasonable party to avoid harm to another party.

slide-149
SLIDE 149

Duties of Designer

22 Duties of persons that design plant, substances or structures The designer must ensure, so far as is reasonably practicable, that the plant, substance or structure is designed to be without risks to the health and safety of persons: (a) who, at a workplace, use the plant, substance or structure for a purpose for which it was designed; or (b) who handle the substance at a workplace; or (c) who store the plant or substance at a workplace; or (d) who construct the structure at a workplace; or (e) who carry out any reasonably foreseeable activity at a workplace in relation to: (i) the manufacture, assembly or use of the plant for a purpose for which it was designed, or the proper storage, decommissioning, dismantling or disposal of the plant; or (ii) the manufacture or use of the substance for a purpose for which it was designed or the proper handling, storage or disposal of the substance; or (iii) the manufacture, assembly or use of the structure for a purpose for which it was designed or the proper demolition or disposal of the structure;

slide-150
SLIDE 150

Duties of manufacturer

22 Duties of persons that manufacture plant, substances or structures The manufacturer must ensure, so far as is reasonably practicable, that the plant, substance or structure is manufactured to be without risks to the health and safety of persons: (a) who, at a workplace, use the plant, substance or structure for a purpose for which it was designed; or (b) who handle the substance at a workplace; or (c) who store the plant or substance at a workplace; or (d) who construct the structure at a workplace; or (e) who carry out any reasonably foreseeable activity at a workplace in relation to: (i) the manufacture, assembly or use of the plant for a purpose for which it was designed or manufactured, or the proper storage, decommissioning, dismantling or disposal of the plant; or (ii) the manufacture or use of the substance for a purpose for which it was designed or manufactured or the proper handling, storage or disposal

  • f the substance; or

(iii) the manufacture, assembly or use of the structure for a purpose for which it was designed or manufactured or the proper demolition or disposal

  • f the structure;
slide-151
SLIDE 151

151

slide-152
SLIDE 152

Purpose of Safety Case

The Safety Case has been utilised in the high hazard process industries for over 3 decades. Its use is being more widely accepted and provides an ideal way to collate and present the Safety Case argument for any design or installation, project or task. Constructing a viable Safety Case can draw upon Risk Management and Risk Engineering tools.

slide-153
SLIDE 153

Purpose of Safety Case

The Safety Case document goes someway toward recording the Organisation and Workplace climate at the time decisions are made. It then provides a process for maintaining the currency of this document.

slide-154
SLIDE 154

Why We Need a Safety Case

The aim of all engineering tasks or projects is always to achieve

  • ptimum safety or level of risk.

When safety is improved we have a productive and efficient workplace. The process used to prepare a Safety Case ensures that superior safety remains the focus.

slide-155
SLIDE 155

Why We Need a Safety Case

  • 1. Legal Requirement:

In a growing number of jurisdictions, it is a legal requirement to prepare a Safety Case, (Safety Plan or a Safety Report). The Safety Case clarifies how and if the level of risk is tolerable or acceptable to the particular legislated requirements.

slide-156
SLIDE 156

Why We Need a Safety Case

  • 2. To provide a systematic process:

for the review of safety requirements throughout the life of a project, facility

  • r enterprise.

This can assist with identifying and then focusing on areas of higher risk to improve safety performance of the system, process, plant or enterprise/organisation.

slide-157
SLIDE 157

Why We Need a Safety Case

  • 3. To record: (or log)

all decisions made so that WHS due diligence, residual risk and risk controls (engineering practice) are recorded for future scrutiny and update.

slide-158
SLIDE 158

Why We Need a Safety Case

  • 4. Legal Defence:

To ensure that records of due diligence (engineering practice) are available should the need arise to demonstrate that decisions were made throughout the life of the project or facility with diligence. The Safety Case forms an audit trail throughout the life of a project or facility/process.

slide-159
SLIDE 159

Why We Need a Safety Case

  • 4. Legal Defence:

If decisions have been made with diligence then it becomes much more problematic for prosecuting authorities to prove negligence.

slide-160
SLIDE 160

Why We Need a Safety Case

  • 5. Change Management:

To provide for a rational basis for making improvements to equipment, plant items, people processes, systems or their components. It helps document change when and as it happens throughout the

  • lifecycle. The Safety Case can also

assist with the communication of change.

slide-161
SLIDE 161

Why We Need a Safety Case

  • 6. Communication & marketing:

Safety is often publically scrutinised. This can be before a project is implemented or after an event. The Safety Case can assist with communication to the public and help manage outrage.

slide-162
SLIDE 162

Why We Need a Safety Case

  • 6. Communication & marketing:

Safety also sells and is utilised by many manufacturers to provide a sales edge over competitors. A Safety Case can provide a resource to support such representations.

slide-163
SLIDE 163

Why We Need a Safety Case

It can also be said, that for a project to be handled with diligence, then all these factors are covered in any case. The project file will contain all the necessary information and can be collated to meet the needs of the Safety Case over time.

slide-164
SLIDE 164

Why We Need a Safety Case

The Safety Case is to both ensure safety and to record compliance with the law.

slide-165
SLIDE 165

Safety Case Content

Communication The Safety Case is about communication: communicating well about the safety of the plant/equipment/facility/enterprise being engineered.

slide-166
SLIDE 166

– Safety Case Content

3 Areas:

  • 1. Description:
  • 2. Safety Management System:
  • 3. Assessment:
slide-167
SLIDE 167

Level of Detail

Due diligence Approach:

Step 1. Hazard Identification – Identify all Credible Critical Issues Step 2. Criticality – Establish Critical Hazards. Step 3. Preventability – Identify all Practicable Precautions Step 4. Reasonableness – Determine which Practicable Precautions are Reasonable Step 5. Implementation – Precaution Implementation Step 6. Monitoring and Review – Quality Assurance

slide-168
SLIDE 168

Structure/Layout Executive Summary Description:

Introduction or Summary of engineered plant/equipment/facility Assumptions and boundaries Progress (Where applicable)

Safety Management System (SMS) Assessment:

Safety Case Steps 1 – 6 Emergency/Contingency preparedness Any independent reports or audits/scrutiny/review/legal opinion

Conclusions/recommendations/outstanding issues/concerns References Appendices

Level of Detail

slide-169
SLIDE 169
slide-170
SLIDE 170
slide-171
SLIDE 171

SAFETY CASE -

The Role of Contractual Due Diligence Specifications for an Engineering Project.

Townsville Regional Group

Geoff Hurst 0426 881 322 ghurst10@live.com

slide-172
SLIDE 172

Top-down

THREATS

OPPORTUNITIES

EXTERNAL /INTERNAL FACTORS

slide-173
SLIDE 173

Top-down - SWOT

THREATS

OPPORTUNITIES

EXTERNAL /INTERNAL FACTORS

VULNERABILITIES

ORGANISATION

STRENGTHS

VALUE ADDS

WEAKNESSES

STRATEGY

slide-174
SLIDE 174

CHAIR

Construction and Demolition Maintenance and Repair

slide-175
SLIDE 175

CHAIR

slide-176
SLIDE 176

CHAIR

slide-177
SLIDE 177

CHAIR

slide-178
SLIDE 178

CHAIR

slide-179
SLIDE 179

Managing Construction Safety Risk

Geoff Hurst 0426 881 322 ghurst10@live.com

slide-180
SLIDE 180

180

slide-181
SLIDE 181

181

slide-182
SLIDE 182

182

slide-183
SLIDE 183

183

slide-184
SLIDE 184

184

slide-185
SLIDE 185

185

slide-186
SLIDE 186

186

slide-187
SLIDE 187

187

slide-188
SLIDE 188

188

slide-189
SLIDE 189

189

slide-190
SLIDE 190

190

slide-191
SLIDE 191

191

slide-192
SLIDE 192

192

slide-193
SLIDE 193

Due Diligence vs Risk Assessment/Target

Precaution based due diligence (WHS Act) ≠ Hazard based risk assessment (ISO 31000)

SFAIRP ALARP

Precaution focused by testing all practicable precautions for reasonableness, that is, on the balance of the significance of the risk is disproportionate when considering the effort required to reduce it. Hazard focused by comparison to acceptable or tolerable target levels

  • f risk.

From the definition in AS/NZS ISO 31000: 2.24 risk evaluation process of comparing the results

  • f risk analysis (2.21) with risk criteria (2.22) to

determine whether the risk (2.1) and/or its magnitude is acceptable or tolerable.”

Establish the context Risk assessment (precaution based): Identify credible, critical issues Identify precautionary options Risk-effort balance evaluation Risk action (treatment) Establish the context Risk assessment (hazard based): (Hazard) risk identification (Hazard) risk analysis (Hazard) risk evaluation Risk treatment Criticality driven Usual interpretation of WHS Act & common law. Risk (likelihood and consequence) driven Usual interpretation of AS/NZS ISO 31000 After Robinson 2013