Rio Tabasara Pedestrian Bridge TJ Jaksa Erin Lau Ryan Olsen - - PowerPoint PPT Presentation

rio tabasara pedestrian bridge
SMART_READER_LITE
LIVE PREVIEW

Rio Tabasara Pedestrian Bridge TJ Jaksa Erin Lau Ryan Olsen - - PowerPoint PPT Presentation

Rio Tabasara Pedestrian Bridge TJ Jaksa Erin Lau Ryan Olsen Nathan Priest December 13, 2018 Michigan Technological University 1400 Townsend Drive Houghton, MI 49931 -1295 Outline Site Visit Community Background


slide-1
SLIDE 1

TJ Jaksa Erin Lau Ryan Olsen Nathan Priest

December 13, 2018

Rio Tabasara Pedestrian Bridge

Michigan Technological University

1400 Townsend Drive Houghton, MI 49931 -1295

slide-2
SLIDE 2

Outline

  • Site Visit
  • Community Background
  • Data Collection
  • Design

○ Assumptions ○ Details ○ Alternate Considerations

  • Cost Estimate
  • Construction Schedule
  • Looking Forward
slide-3
SLIDE 3

Site Visit

  • Traveled to Vigui

○ 7 hour duration

  • Took a Chiva to Llano

Nopo ○ 1 hour duration

  • Hiked to Llano Miranda

○ 1.5 hour duration

  • Hosted by Peace Corps

Volunteer

slide-4
SLIDE 4

Site Visit

slide-5
SLIDE 5

Site Visit

  • Scoped out potential locations for

the bridge ○ Accessibility ○ Flood Areas

  • Community Meeting

○ Needs ○ Ideas

  • Tour from Ubaldo

Llano Miranda Bajo Mosquito

slide-6
SLIDE 6

Community Background

  • Very few jobs within the Comarca
  • Many men live in a bigger city

during the week

  • Problems with HIV and Dysentery
  • No electricity, running water, or

latrines

  • First Peace Corps Volunteer on-

site

slide-7
SLIDE 7

Data Collection

  • Surveying
  • Soil Analysis
  • Flow Rate
  • Preliminary Calculations
  • Design Decisions
slide-8
SLIDE 8

Data Collection

Approximate Watershed Drainage Area: 24,840 hectares Surveyed Points: Plan View

Flow

slide-9
SLIDE 9

Llano Ñopo

  • Developed City 2 hours away
  • Hospital
  • School
  • Markets
  • Electricity
  • Bridge
slide-10
SLIDE 10

Llano Ñopo

Attribute Measurement Length 277.5 ft. Width 6.0 ft. Deck to Water Level 37.3 ft. Bottom of Cable Sag to Water Level 40.8 ft. Cable Sag 15 ft. Cable Diameter 1.25 in. Llano Ñopo Suspension Bridge

slide-11
SLIDE 11

Preliminary Design

  • Needs

○ Carry children to school ○ May carry animals ○ Minimum span ~270 ft ○ Survive river flooding

  • Design Choices

○ Suspension bridge ○ Ramps to raise bridge above floodplain ○ 4 feet wide to allow people to pass ○ Design for animal hoof-loads ○ Consider 100 mph wind load

Suspended bridge example - Bridges to Prosperity Manual

slide-12
SLIDE 12

Alternate Designs

  • Three-cable bridge considered
  • Still must stay above the water
  • Dangerous for children
  • Ramps would be too large
  • Considering safety and cost, better

to build suspension bridge

Photo Credit: Cameron Speirs

slide-13
SLIDE 13

Overall Design

  • 270 foot span
  • 25 foot cable sag
  • 5 foot hanger spacing
  • 10 foot freeboard (height above water)
slide-14
SLIDE 14

Superstructure Design

  • Designed for 65 lb/ft² or 500lb at any point
  • Minimum of ⅜” steel for corrosion and wear
  • Decking: 4x12 native wood planks
  • Cables: 1 ⅝” 6x25 Galvanized Wire Rope
  • Towers: 30’ Tall 14x0.375 Round HSS
  • Cables and hangers designed with large

factor of safety, preventing progressive failure

Tower Structure

slide-15
SLIDE 15

Tower Foundation Design

  • Uncertainty in exact soil properties

○ Not able to conduct detailed soil tests

  • Designed for approximate worst-case clay
  • Large factors of safety used
  • Large mat foundations for towers: 6x12 feet
  • 14” Thick Reinforced Concrete

Tower Foundation

slide-16
SLIDE 16

Anchor Block Design

  • Deep concrete anchor blocks for cables

○ 6x10x12 feet, deep to resist sliding ○ Embedded steel beam to connect to cable ○ Skin reinforcement to control cracking ○ Entirely embedded in the ground

Cable Anchor Block 12’ 6’

slide-17
SLIDE 17

Cost Estimation

Cost (USD) Materials 115,929 Labor 14,480 Equipment 36,668 General Requirements 28,101 Profit 29,277 TOTAL 225,000

slide-18
SLIDE 18

Construction Schedule

  • Construction window

○ January-April (Dry Season)

  • Three month expected duration
  • 8 hour work days
  • 5 day work weeks
slide-19
SLIDE 19

Looking Forward

  • Documents to Peace Corps. Volunteer
  • Ministry of Public Works
  • Other forms of Funding
  • Construction
slide-20
SLIDE 20

Thank You!