Retrofit of the Pukalani WWTP Water Reuse in Paradise May 17, 2013 - - PowerPoint PPT Presentation

retrofit of the pukalani wwtp water reuse in paradise
SMART_READER_LITE
LIVE PREVIEW

Retrofit of the Pukalani WWTP Water Reuse in Paradise May 17, 2013 - - PowerPoint PPT Presentation

Retrofit of the Pukalani WWTP Water Reuse in Paradise May 17, 2013 Project Location 2 Project Location 3 Project Location 4 Project Location Central Maui Pukalani hole in the sky Variable Rainfall (15-80 in/year) 5 Service


slide-1
SLIDE 1

Retrofit of the Pukalani WWTP Water Reuse in Paradise

May 17, 2013

slide-2
SLIDE 2

Project Location

2

slide-3
SLIDE 3

Project Location

3

slide-4
SLIDE 4

Project Location

4

slide-5
SLIDE 5

Project Location

Central Maui Pukalani – “hole in the sky” Variable Rainfall (15-80 in/year)

5

slide-6
SLIDE 6

Service Area

787 Connections

 200,000 gpd

Possible expansion to double existing size (400,000 gpd)

6

slide-7
SLIDE 7

Reuse Area

Pukalani Golf Course 160 Acres 105 in/year ET 25-90 in/year of irrigation demand 330 to 1200 AF/year

  • f irrigation demand

7

slide-8
SLIDE 8

Regulatory Reference

HDOH “Guidelines for the Treatment and Use of Recycled Water” = CA Title 22 Water Recycling Criteria HDOH R-1 water = Disinfected Tertiary Recycled Water HDOH R-2 water = Disinfected Secondary-23 Recycled Water

8

slide-9
SLIDE 9

The Problem?

Existing Pukalani WWTP Produced R-2 water

 No filtration  Ineffective disinfection

Provided supplemental irrigation water to 180- acre Pukalani Golf Course In violation of HDOH Guidelines

 R-2 water can only be applied to golf courses

subsurface (it was being sprinklered)

 Access was not controlled and overspray into yards

and on the public was quite possible

 R-2 water, even if allowed in sprinkler systems isnot

allowed within 500 feet of residences or parks.

9

slide-10
SLIDE 10

The Challenge

Aging infrastructure

 30 year old Oxigest  Salt corrosion

No redundancy At capacity Very little space

10

slide-11
SLIDE 11

Space Challenge

11

slide-12
SLIDE 12

Existing Facility

R-2 (Secondary-23) facility

12

Treatment Process Performance

Bar Rack Removal of Large Screenings Oxigest Package WWTP Secondary Treatment (Aeration/Clarification) Storage Reservoir (2-MG) Chlorine Contact, Storage on Non- Irrigation Days

slide-13
SLIDE 13

New Facility

R-1 (Tertiary-2.2) facility

13

Treatment Process Performance

1 mm fine screens Removal of Large Screenings Flow Equalization Shave Daily Peaks Anaerobic /Aerobic Bioreactor Secondary Treatment Membrane Filtration 0.2-0.4 micron Kubota flat plate Effluent turbidity < 0.2 NTU 95%

  • f the time

UV disinfection 80 mJ/cm2 dose, 65% min UVT Storage Reservoir (2-MG) Storage on Non-Irrigation Days

slide-14
SLIDE 14

Fine Screens

14

slide-15
SLIDE 15

Equalization

15

slide-16
SLIDE 16

Bioreactor

16

slide-17
SLIDE 17

Membranes

17

slide-18
SLIDE 18

Mechanical Room

18

slide-19
SLIDE 19

UV Reactors

19

slide-20
SLIDE 20

Design Flows

Phase 1 Design Membrane Design Flow Duration Phase 2 Design

WWTP Design Flow (mgd) Membrane Design Flow (mgd) WWTP Design Flow (mgd) Membrane Design Flow (mgd)

Average Daily

0.200 0.200 0.400 0.400

Average Day Maximum Month

0.230 0.230 0.460 0.460

Maximum Day

0.400 0.56 8-days (non- consecutive) 0.800 1.125

Peak Hour

0.843 0.56 4 hours 1.500 1.125

20

slide-21
SLIDE 21

Out with the Old

21

slide-22
SLIDE 22

Cost?

$7M for 200,000 gpd ($35/gpd) Expansion to 400,000 gpd possible for < $1M (total of approximately $20/gpd)

22

slide-23
SLIDE 23

Performance is Good

23

slide-24
SLIDE 24

Performance is Good

24

slide-25
SLIDE 25

Project Success

25

slide-26
SLIDE 26

Questions

26