RETHINK FOLLY ALTERNATIVES ANALYSIS PART 2 Ellis Creek to Prescott - - PowerPoint PPT Presentation
RETHINK FOLLY ALTERNATIVES ANALYSIS PART 2 Ellis Creek to Prescott - - PowerPoint PPT Presentation
RETHINK FOLLY ALTERNATIVES ANALYSIS PART 2 Ellis Creek to Prescott Street CONTENTS Original Alternatives Challenges Review of Previously Recommended Alternative Design Criteria Alternative 5 Overview Alternative 2b Overview Alternatives
CONTENTS
Original Alternatives Challenges Review of Previously Recommended Alternative Design Criteria Recommendation Alternative 5 Overview Alternative 2b Overview Alternatives Comparison
ORIGINAL ALTERNATIVES
1
A L T
5’ ~2’
curb & gutter planting12’
multi-use path12’
travel lane~3.5’
bike lane5’ ~2
curb & gutter planting12’
multi-use path12’
travel lane~3.5’
bike lane~2’
curb & gutter8’
sidewalk12’
travel lane~3.5’
bike lane5’ ~2’
curb & gutter sidewalk12’
travel lane2
A L T
3
A L T
4
A L T
ROW Line
5’ Sidewalk 8’ Sidewalk Multi-Use Path + Bike Lane Multi-Use Path, No Bike Lane
CHALLENGES
- Before 1962 Folly Road was two lanes
with a 50’ ROW, then SCDOT expanded to a ~70’ ROW
- Generally 35’ feet along the west side
- f Folly Road
- 32.5’ pavement
- 1.5’ curb & gutter
- Approximate cost of ROW purchase =
$40/sq. ft
- Utility poles are a major challenge along the
corridor for each alternative
- There will not be a significant impact on below
ground utilities
- Telephone pedestals, gas monuments,
backflow preventers would need to be relocated
- Existing site drainage would be impacted for 3
businesses
- Eliminating existing bike lane requires
upgrades to Folly Road drainage system
- Most businesses along Folly Road have
signs that are typically at ROW edge
- Signs are expensive and difficult to
relocate
- Relocation Costs:
- Monuments signs: $10,000
- Post signs: $5,900
- Traffic signs: $500
RIGHT OF WAY
UTILITIES/STORMWATER MONUMENTS/SIGNAGE
2
A L T
8’ Sidewalk – previously recommended alternative
Sumter’s Landing Roadside Seafood Live Oak Doctor’s Care
Ellis Creek to Prescott Street
RISK PROFILE
LIKELIHOOD IMPACT TO COSTS
LOW LOW MEDIUM MEDIUM HIGH HIGH
1
A L T
3
A L T
4
A L T
CHALLENGE
ROW UTILITIES/ STORMWATER MONUMENTS/ SIGNAGE
SEGMENT 1
2
A L T
5’ Sidewalk 8’ Sidewalk Multi-Use Path + Bike Lane Multi-Use Path No Bike Lane $ 984,691 $ 1,431,690 $ 3,301,264 $ 4,012,945
COST ESTIMATE
DECISION MATRIX REVIEW - why we recommended Alternative 2
DESIGN CRITERIA
NACTO SCDOT AASHTO ADA FHWA SCDOT
Ellis Creek to Prescott Street
SEGMENT 1
Areas of Interest
Sumter’s Landing Roadside Seafood Huff’s Seafood Doctor’s Care
1 2 3 4
5
A L T
5’ Sidewalk + 5’ Separation
5
A L T
5’ Sidewalk + 5’ Separation
Sumter’s Landing Roadside Seafood Huff’s Seafood Doctor’s Care
Ellis Creek to Prescott Street
SEGMENT 1
Areas of Interest
Sumter’s Landing Roadside Seafood Huff’s Seafood Doctor’s Care
1 2 3 4
2b
A L T 8’ Sidewalk + Utility Relocation + Future Bike Improv.
~4.5’
bike lane
~2’
curb & gutter
8’
sidewalk
12’*
travel lane
2b
A L T
8’ Sidewalk + Utility Relocation + Future Bike Improv.
Sumter’s Landing Roadside Seafood Huff’s Seafood Doctor’s Care
5
A L T 5’ Sidewalk + 5’ Separation
ALTERNATIVES COMPARISON 1
A L T
3
A L T
4
A L T
Pedestrian Access Bike Access FHWA/NACTO Compliance
2
A L T 5’ Sidewalk 8’ Sidewalk Multi-Use Path + Bike Lane Multi-Use Path No Bike Lane
2b
A L T 8’ Sidewalk + Utility Relocation + Future Bike Improv.
Budget
$ 984,691 $ 1,431,690 $ 3,301,264 $ 4,012,945
Cost Estimate
$ 1,694,590 $ 2,087,210*
($ 400,000 – 1.1M)
RECOMMENDATION
2b
A L T
8’ Sidewalk + Utility Relocation +
Future Bike Improvements
Install 8’ sidewalk at back of curb & relocate overhead power lines (approx. 2.1M) Restripe Folly Road & paint bike path to provide proper bike path width (approx. $400,000 - $1.1M) Request SCDOT perform a speed study to lower the speed limit