Sales Tax/Bond Projected Allocation
2013-2015 2016-2018 2019-2021
Sales Tax $ 2,600,000 $ 2,600,000 * $ 2,600,000
*
Bond $ 8,800,000 $ 5,750,000
*
Total $ 11,400,000 $ 2,600,000 * $ 8,350,000
* * Projected Funding
CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT
CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT
Ward 2 - 2013 to 2015 Bond/Sales Tax Summary
- A total of $2,600,000 in Sales Tax funding was allocated.
- A total of $8,800,000 in Bond Issue funds was allocated.
- In the 2013 to 2015 project request list, there were 61 jobs requested.
- A total of 6 Bond Program jobs and 8 Sales Tax Program jobs were
selected and are in the process of design, bidding, and construction.
- Currently 3 jobs (21%) are in design, 7 jobs (50%) are currently in
construction, and 4 jobs (29%) are totally complete.
April 6, 2015 3
CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT
4 April 6, 2015
CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT
- Ward 2 Sales Tax Project Status
April 6, 2015 5
Request # Location Description Status
Anticipated Bid Quarter
2-5b Westminister Dr Replace curb and gutter and install underground drainage system at #45 Westminister Dr. Project Complete 2-6a Windamere Additional/continuation of drainage improvements from Windamere Dr. to Carlyle Dr. In Construction 2-9b Butler Rd Replace curb and gutter and install underground drainage system on Butler Rd at Allyson Circle. Project Complete 2-18a Tamela Dr Install additional curb inlets along Tamela Dr Between Valley and Ramona Dr. Project Complete 2-20 5919 Lancaster Improve drainage ditch along rear property lines for houses fronting Lancaster Rd and Lyndell Dr. In Construction 2-28 Woodson Rd Street reconstruction including curb, gutter, underground drainage system from Young Rd to Halifax Dr. (1270 lf) In Construction 2-32a Abigail St Replace curb and gutter, install underground drainage system from 8th to 10th In Construction 2-32d Adams St Install curb, gutter and underground drainage from W 12th St north to I- 630.
In Design – 98% complete 1st - 2015
CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT
- Ward 2 Bond Project Status
April 6, 2015 6
Request # Location Description Status
Anticipated Bid Quarter
B-2a Geyer Springs Railroad Overpass Grant match for new overpass. In Design - 1% complete AHTD Controlled B-2b Scott Hamilton Widen and improve roadway including sidewalks. In Construction B-2c Dailey Drive Sidewalk Install sidewalk From Baseline Rd South to Pulaski County SW Health Unit (575'). Project Complete B-2d West 10th St Improve roadway section including sidewalk, curb, gutter, and underground storm drainage. In Construction B-2e Traffic Calming Install traffic calming measures along Fair Park Blvd In Design - 60% complete 3rd - 2015 B-2f Elm St and Maryland St Elm St from 8th to Maryland, Maryland St west to Lewis In Construction Overlay Program In Construction – 44% complete
CITY OF LITTLE ROCK PUBLIC WORKS DEPARTMENT
Ward 2 - 2016 to 2018 Project Request Summary
- Anticipated total of $2,600,000 in Sales Tax funding will be allocated.
- Currently there are 7 new requests.
- Deadline for Submission is May 1, 2015.
- For access to the Project Infrastructure Request form, citizens may:
1. Pick up a copy here
2. Go to website at http://www.littlerock.org/citydepartments/publicworks.aspx
Halfway down the page under “Civil Engineering”, click on “Infrastructure Request Form (Fillable)” link. 3. Send form to: City of Little Rock - Department of Public Works Infrastructure Project Requests 701 West Markham Little Rock, AR 72201 Email: PublicWorks@littlerock.org
April 6, 2015 7