regulation of offshore electricity transm ission
play

Regulation of Offshore Electricity Transm ission External Com m - PowerPoint PPT Presentation

Regulation of Offshore Electricity Transm ission External Com m unication Session # 2 10 August 2007 Agenda I ntroduction - Duarte Figueira, BERR Overview of July Policy Statem ent - Robert Hull, Ofgem Transitional Offshore


  1. Regulation of Offshore Electricity Transm ission External Com m unication Session # 2 10 August 2007

  2. Agenda • I ntroduction - Duarte Figueira, BERR • Overview of July Policy Statem ent - Robert Hull, Ofgem • Transitional Offshore Regim e and tender process – Colin Green, Ofgem • An I ntroduction to GB Transm ission Charging Arrangem ents – Hêdd Roberts, National Grid Offshore Transm ission Charging I ssues – Tom I reland, • National Grid • Coffee Break • Enduring Offshore Regim e - Graham Know les, Ofgem Other issues – Panel Q&A • Next Steps/ Concluding rem arks • Lunch • 2

  3. I ntroduction Duarte Figueira Director, Renewables Deployment Team BERR

  4. Purpose of today • Provide additional clarity on: – the framework set out in the Joint policy document – the scope of further work to be undertaken – the key stages and dates in the implementation process • Encourage discussion • Answer preliminary queries • Enable stakeholders to submit a fully informed response. • Further external communication sessions are planned. 4

  5. Overview of the Joint Policy Statem ent Robert Hull Director, Transmission Ofgem

  6. W here are w e in the process? • July 2 0 0 7 Joint Policy Statem ent – builds upon the Government decision on licensing and Ofgem’s Second Scoping Document in March 2007 (informed by industry responses); • Objective of the docum ent – our policy proposals provide greater detail and clarity on the proposed regime and its implementation for further consultation. Views are sought to inform development of the regime; • Next steps – we welcome responses and continued industry engagement over the coming weeks and months. A policy update document is planned for October 2007 and a final proposals document for January 2008; and • I m plem entation – we envisage the new regime will commence in October 2008 (‘go active’ date) so the process for awarding licences can commence. We then expect the new regime would come into force in October 2009 (‘go-live’ date). 6

  7. Policy principles for the offshore regim e • In the context of Government renewable targets, to ensure the efficient and effective connection of offshore renewable generation to the onshore Grid; • A regulatory regime which strikes an appropriate balance between protection of consumers’ interests and promoting connection of renewable generation; • Developing an effective competition for the appointment of OFTO’s which will deliver value for money and fit for purpose infrastructure; • Designing a regime to attract prospective OFTO’s by providing sufficient clarity and certainty in terms of risk and rewards; • Ensuring that industry process operate effectively to support the proposed regulatory framework 7

  8. Key proposals from the joint policy statem ent ( 1 ) Design of the regulatory regim e • Offshore Transmission Owner (OFTO) is responsible for the design, construction, financing and maintenance of the offshore transmission assets; • OFTO is appointed by competitive tender and awarded a transmission licence. This will set out the obligations and entitlements of the OFTO, including 20 year revenue stream and performance requirements; Design of the OFTO tender process • It would be run by Ofgem; • Triggered by offshore Generator application; • Annual tender windows to co-ordinate the process and minimise costs; • Competition to select preferred bidder. 8

  9. Key proposals from the joint policy statem ent ( 2 ) Transitional arrangem ents • Transitional projects that reach full financial close by ‘go-active’ will enter transitional tender process at that time; • Transitional projects that reach financial close after ‘go-active’ but by ‘go-live’ can enter a transitional tender process that will begin shortly after ‘go-live’; and • We will provide comfort for transitional schemes that they will receive the greater of 75% of Ofgem’s ex-ante estimate of the efficient capital cost and the full ex-post efficient level of cost. Other policy proposals • Onshore connection application process • Charging access and compensation arrangements • Technical rules 9

  10. Next steps in the process • Presentations today will focus on the key aspects of the joint policy statement: – Transitional and tender arrangements; – Charging; and – Development of the enduring framework; • We welcome feedback on our current proposals; • We recognise that designing a regime of this nature has several dimensions and interactions – but by considering the issues in detail as we do onshore, we are aiming to provide certainty to all parties seeking to benefit from it; • Work continues to develop the licences, codes, tender documentation and regulations necessary to implement the regime – we need industry support in these processes. 10

  11. Transitional Offshore Projects Colin Green Head of Offshore Transmission & Projects Ofgem

  12. I ntroduction • Key issues • Tender process • Comfort on costs • Pre-conditions for tender • Issues to be resolved 12

  13. Transitional Offshore Projects – Key issue • Any assets constructed, or under construction, before the new regime is in place will have to be “adopted” by licensed TO’s into the new regime. These are referred to as “transitional offshore transmission assets”; • Second Scoping Document set out our initial thoughts: – Transitional assets would be adopted – i.e. an OFTO would be appointed to maintain the assets constructed; – An OFTO would be selected by competitive tender process – but modified to reflect the different stage of development; – There would be comfort that projects would receive the greater of 75% of Ofgem’s ex-ante estimate of the capital costs of the project or 100% of the efficient ex-post cost; – That projects should reach full financial close by the ‘go-active’ date to qualify for this process; • Joint policy document set out our further thoughts in these areas. 13

  14. Sum m ary of the Tender Process ( 1 ) • Tender Process will be established in the form of Tender Regulations (once section 92 of the Energy Act is activated); • Tender will be for the award of an offshore transmission licence – bidders will not be pre-licensed, must meet a prequalification criteria; • Standardised tender documentation will be provided; • Tender process over the following stages: – Prequalification and expression of interest – Invitation to Tender (ITT) and evaluation of bids (optional best and final offer stage) – Preferred bidder and appointment of OFTO • Ofgem to manage the process and approve each stage of bidder selection – Welcome views. 14

  15. Sum m ary of Tender Process – Transitional Schem es( 2 ) • Three classifications of transitional projects: – Projects constructed by ‘go-active’ – Projects that are not constructed, but achieve financial close by ‘go-active’; and – Projects that achieve financial close after ‘go-active’ but before ‘go-live’; • Two tender processes would commence at ‘go-active’ and ‘go-live’ for the appointment of an OFTO to adopt transitional projects; • Enduring tender process will also commence at ‘go-active’ for those seeking the early appointment of an OFTO; • Developer would be the OFTO of last resort; Projects that do not achieve financial close by the ‘go-live’ date w ill be deem ed to fall w ithin the enduring regim e 15

  16. Pre-conditions for com fort on costs ( 1 ) • Ofgem intends to assess the value of the assets to be adopted by an appointed OFTO: – Projects that are fully constructed would be subject to an ex- post assessment of the efficient capital costs of the project and tender on the basis of 100% of this ex-post value; – Projects that reach financial close but not fully constructed: • would be given comfort (i.e. greater of 75% of ex-ante estimate and 100% of the ex-post efficient cost); and • be tendered on the basis of 100% of the ex-ante estimate of the projects capital value; • Why only 75% of ex-ante estimate? – Recognises the less rigorous process that Ofgem will undertake and the scope for detailed assessment to identify inefficiency 16

  17. Pre-conditions for com fort on costs ( 2 ) • Developers will need to show: – It has an onshore connection agreement; – It has all necessary property rights; – Entered into contacts for construction of the offshore transmission assets; – Evidence of full financial close (or equivalent); – All financial and technical data necessary to undertake an efficiency assessment of the cost of construction • It is also important that developers can demonstrate that they are able to separate agreements and property rights, where necessary, to achieve a clean separation between generation and transmission activities. 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend