Grenfell Tower 5th December 2013 RYD00094245/1 RYD00094245 _ 0001 - - PDF document

grenfell tower
SMART_READER_LITE
LIVE PREVIEW

Grenfell Tower 5th December 2013 RYD00094245/1 RYD00094245 _ 0001 - - PDF document

gton T'M. 0 sin. Ken . &Chelsea Grenfell Tower 5th December 2013 RYD00094245/1 RYD00094245 _ 0001 Today's agenda Introductions and Protocol of the meeting High profile of project in RBKC Client requirements: Working in


slide-1
SLIDE 1

Ken . sin. gton T'M. &Chelsea

Grenfell Tower

5th December 2013

RYD00094245 _ 0001

RYD00094245/1

slide-2
SLIDE 2

Today's agenda

  • Introductions and Protocol of the meeting
  • High profile of project in RBKC
  • Client requirements:
  • Working in occupied homes
  • Technical standards
  • The structure of the documentation
  • Reminder of the Key Dates
  • Documentation to return
  • Questions

RYD00094245 _ 0002

RYD00094245/2

slide-3
SLIDE 3

Why are we improving Grenfell Tower?

RYD00094245 _ 0003

RYD00094245/3

slide-4
SLIDE 4

Introductions

Peter Maddison Claire Williams Jenny Jackson Philip Booth Bruce Sounes Matt Smith Director, KCTMO Project Manager, KCTMO Procurement Manager, KCTMO Project Manager, Artelia Design Team Architect, Studio E M&E, Max Fordham

RYD00094245 _ 0004

RYD00094245/4

slide-5
SLIDE 5

Protocol

  • Slides will be emailed to all contractors.
  • Notes will be taken of all questions and responses.

These will be circulated, along with the questions and answers from the site visit, following the meeting.

  • We will aim to respond to any questions that we are

unable to answer this morning, via email, as soon as possible.

RYD00094245 _ 0005

RYD00094245/5

slide-6
SLIDE 6

Background

  • What services are required?

./ Exterior cladding ./ New heating system ./ Construction of 7 new

homes

./ Nursery and boxing club re-

proviSion

./ Smoke/fire system update ./ Internal cyclical decoration

RYD00094245 _ 0006

RYD00094245/6

slide-7
SLIDE 7

Properties

('

/ ,)

~

TMO

RYD00094245_0007

RYD00094245/7

slide-8
SLIDE 8

Properties

('

/ ,)

~

TMO

RYD00094245 _ 0008

RYD00094245/8

slide-9
SLIDE 9

Key Project Particulars

  • Planning status- S1 06 unilateral undertaking

been signed off by RBKC, but not been ratified by cabinet, due 13 Dec.

  • Grenfell occupancy- 120 households in 1

and 2 bed flats. 12 leaseholders.

  • Housing office, boxing club and nursery-

both due to be relocated locally for duration of

  • works. RBKC legal working on lease

arrangements for the 2 latter occupiers

RYD00094245 _ 0009

RYD00094245/9

slide-10
SLIDE 10

Key client requirements

Working in occupied homes

  • Refer to the Code of Conduct for Working in occupied

homes - good practise

  • TMO will provide a Resident Liaison Officer and also a

clerk of works Issues within tender for your attention

  • BREEAM standards, retention of £50k until certified
  • Fee for finding grant funding for energy works
  • No sectional completion

RYD00094245 _ 001 0

RYD00094245/10

slide-11
SLIDE 11

Key client requirements

Technical Standards D&B contract

  • Mechanical and

Electrical

  • Architectural

RYD00094245_0011

RYD00094245/11

slide-12
SLIDE 12

M&E Considerations

  • Brief outline of works
  • Working in occupied areas
  • Implications on hot works
  • Specification of critical components (HI Us etc.)
  • Keeping existing systems live while installing new
  • Phasing

RYD00094245 _ 0012

RYD00094245/12

slide-13
SLIDE 13

M&E Considerations

f/t)

~

TMO

~

·

~

·

~

·

.....

~

·

~

' I

.!lE

;!;.mm .. !1nl

  • ~-

h ,l

I

~

~ 11 ....-<i1

rLJ

.-:i .uJ (

RYD00094245_0013

RYD00094245/13

slide-14
SLIDE 14

Site Context

RYD00094245 _ 0014

RYD00094245/14

slide-15
SLIDE 15

Site Context

f/,)

~

TMO

RYD00094245 _ 0015

RYD00094245/15

slide-16
SLIDE 16

Cladding

f/,)

~

TMO

RYD00094245 _ 0016

RYD00094245/16

slide-17
SLIDE 17

Cladding

f/,)

~

TMO

l

11

J

§§§

RYD00094245 _ 0017

RYD00094245/17

slide-18
SLIDE 18

Walkthrough

Approach

RYD00094245 _ 0018

RYD00094245/18

slide-19
SLIDE 19

Document Structure

Part 1 Instructions to Tenderers Part 2 Employer's requirements Part 3 Requirements for Contractor's Proposals Part 4 Employer's Provisional Sums Part 5 Contract Sum Analysis Part 6 Quality Criteria and Tender Scoring Appendix A Tender Drawings and Specifications Appendix B Draft Planning Conditions Appendix C PCI and Risk Schedule Appendix D Appendix E Appendix F Appendix G Appendix H TMO Terms of Novation Model Forms Daywork Schedule BREEAM Information Land Ownership Plan

RYD00094245 _ 0019

RYD00094245/19

slide-20
SLIDE 20

Reminder of Key Dates

Tender Return Date (before midday) 31/01/2014 Interview Date w/c 10/02/2014 Contract Award 07/03/2014 Start on site 24/03/2014 Start of Cladding instalation 10/07/2014 Works in Tenant Flats Start 19/09/2014 Cladding installation complete 13/03/2015 External Works Start 16/03/2015 External Works Complete 29/05/2015 Works in Tenant Flats Complete 29/05/2015 KALC project public realm works to North and West of Grenfell and

~cademy

complete 08/08/2014 KALC project public realm works to East of Grenfell complete 19/12/2014 KALC project Leisure Centre and surrounding public realm works complete 25/11/2014 Project Completion 29/05/2015

RYD00094245 _ 0020

RYD00094245/20

slide-21
SLIDE 21

Documentation to return

Tender return 31st January 2014

  • Envelope provided
  • To Kensington High Street
  • One hard copy and one electronic

RYD00094245 _ 0021

RYD00094245/21

slide-22
SLIDE 22

Documentation to return

  • Form of Tender
  • Certificate of Non-Collusion
  • Freedom of Information Certificate
  • Responses to tender questions
  • Contract Sum Analysis; including:
  • Day works
  • Provisional Sums

RYD00094245 _ 0022

RYD00094245/22

slide-23
SLIDE 23

Documentation to return

  • RTQ I ATQ
  • State the obvious
  • Evidence, evidence, evidence
  • No images unless needed to convey

message

  • Numbering
  • Make it easy - the answer to each

question is distinct

RYD00094245 _ 0023

RYD00094245/23

slide-24
SLIDE 24

Documentation to return

  • Our commitment:
  • Team already set up to evaluate tenders
  • Evaluation will be done within a few weeks of tender

return

  • Full debrief (successful and unsuccessful)

RYD00094245 _ 0024

RYD00094245/24

slide-25
SLIDE 25

Questions

Thank you for listening. Please ask any questions that you may have regarding the project.

l

RYD00094245 _ 0025

RYD00094245/25

slide-26
SLIDE 26

Future Queries

Queries to: BusinessSupportSevenoaks@arteliagroup.com stating "Grenfell Tower" in the subject line of the email Queries will be answered as soon as possible and the answers will be issued to all contractors.

RYD00094245 _ 0026

RYD00094245/26

slide-27
SLIDE 27

Good luck

RYD00094245 _ 0027

RYD00094245/27