Region 5 Upcoming Proj ects

S ummer/ Fall 2018

slide-2
SLIDE 2

The budget amount provided does not reflect the construction costs for projects. The amounts may include ROW, engineering, design, and utility costs. The projects in this presentation are not guaranteed to go to advertisement.

slide-3
SLIDE 3

Projects located in Archuleta, La Plata, Montezuma and Mineral Counties

slide-4
SLIDE 4

US 160 Resurfacing on Elmore’s East; 22010

Planned Ad Date: December 14, 2017

Approximate Budget: $6 million budget

County: La Plata

Work: This surface treatment proj ect will resurface the roadway on US 160 from MP 91.42-102.72 from the Jct of US 172 to Bayfield.

slide-5
SLIDE 5

US 160 SH 84 to Treasure Falls Surface Treatment; 20705

Planned Ad Date: January 11, 2018

Approximate Budget: $8 million budget

County: Archuleta and Mineral

Work: This surface treatment proj ect will resurface the roadway from MP 114.5- 158.5, and includes a chain up and down station at MP 157.3

slide-6
SLIDE 6

SH 145 Dolores Sidewalk Ramps; 19796 ESB Restricted Project

Planned Ad Date: November 30, 2017

Approximate Budget: $400,000

County: Montezuma

Work: Proj ect work includes construction of sidewalk and ADA compliant curb ramps in Dolores at MP 9.6-10.6 on S H 145. Other work includes concrete flatwork for cross-pan curb and gutter, inlet repair, and minor landscaping repair. S igns, light poles, and a fence will be reset.

slide-7
SLIDE 7

R5 Guardrail End Treatment Replacement; 22120

Planned Ad Date: To be determined

Approximate Budget: $2 million

County: Region-wide

Work: Replace old standard guardrail end treatments throughout Region 5.

slide-8
SLIDE 8

Projects located in Fremont (Region 2) & Saguache Counties

slide-9
SLIDE 9

US 50 Passing Lanes East of Salida (Fremont County); 20401

Planned Ad Date: To be determined

Approximate Budget: $5 million

County: Fremont

Work: This proj ect located in Fremont County on US 50 between MP 227.2 and 237.4 consists of the addition of a passing lane in both directions and the addition of slow vehicle pullouts.

slide-10
SLIDE 10

US 50 Structure Replacement; 21338

Planned Ad Date: February 5, 2018

Approximate Budget: $2 million

County: S aguache

Work: This proj ect includes the replacement of a two lane bridge structure with a concrete box culvert.

slide-11
SLIDE 11

Traffic and Safety Projects

slide-12
SLIDE 12

US 550 Traffic Signal Replacement and ADA Ramp Construction; 20737

Planned Ad Date: November 30, 2017

Approximate Budget: $3.9 million budget

County: La Plata

Work: Replace signals, upgrade infrastructure and reconfigure side street approaches. Construct ADA Accessible Pedestrian S ignals and sidewalk ramps at 3 intersections in Durango.

Photo: Google Earth

slide-13
SLIDE 13

US 550 and SH 62 Striping and Rumble Strips; 21743

Planned Ad Date: January 4, 2018

Approximate Budget: $1 million

County: La Plata, Ouray, S an Juan, S an Miguel

Work: Rumble strips and restriping on US 550 MP 37.3-44 & 96.0-117.0, and S H 62 MP 9.0-16.0.

Photo: Google Earth

slide-14
SLIDE 14

US 160 Wolf Creek Pass RSA; 21744

Planned Ad Date: January 18, 2018

Approximate Budget: $2.2 million budget

County: Mineral

Work: S ignage and striping upgrades on US 160 from MP 160 to 166.5. Includes inlaid restriping, centerline rumble strips, two sign bridges, sign removal, sign panel replacements, and type 7 barrier with embankment, asphalt removal, and shoulder improvements.

slide-15
SLIDE 15

US 550 Chain Station & VMS at MP 94; 20894

  • Planned Ad Date: February 8, 2018

Approximate Budget: $750,000

County: Ouray

Work: Work includes chipseal, restriping for chain up station, roadway widening for chain down station, install lighting and VMS board.

slide-16
SLIDE 16

R5 Region-wide Re-Stripe; 22310

  • Planned Ad Date: January 4, 2018

Approximate Budget: $1.3 million

County: Region-wide

Work: Yearly restriping of highways in Region 5.

slide-17
SLIDE 17

R5 Chain Station Improvements; 22119

  • Planned Ad Date: May 18, 2018

Approximate Budget: $1.2 million

County: Region-wide

Work: Providing improvements to chain stations, adding or upgrading lighting, improving striping, and potential widening.

slide-18
SLIDE 18

US 550 Riverside Snowshed Tunnel; 20799

  • Planned Ad Date: March 18, 2018

Approximate Budget: $750,000

County: Ouray, Red Mountain Pass

Work: This proj ect includes the update of lighting in the Riverside S nowshed Tunnel.

slide-19
SLIDE 19

Local Agency Construction Projects

slide-20
SLIDE 20

Salida US 50 Sidewalks Phase 4; 20557

Local Agency: City of S alida

Planned Ad Date: S pring of 2018

Approximate Budget: $500,000

Work: This proj ect involves the construction

  • f concrete sidewalk separated from the back
  • f curb with a colored, textured concrete

buffer on both sides of US 50 from Palmer S t to the intersection of S H 291 on US 50 in S

  • alida. S
  • me curb and gutter and curb ramps

may be replaced. S

  • me accesses may be

moved or changed.

slide-21
SLIDE 21

Pagosa Springs North 8th Street SRTS; 21504

Local Agency: Town of Pagosa S prings

Planned Ad Date: S pring of 2018

Approximate Budget: $400,000

Work: This proj ect involves construction of sidewalks and curb and gutter in the north Pagosa S prings residential neighborhood on North 8t h S t and Florida S t.

slide-22
SLIDE 22

San Miguel Lawson Hill Park and Ride; 21755

Local Agency: S an Miguel County

Planned Ad Date: S pring 2018

Approximate Budget: $1.5 million

Work: This is a S enate Bill 228 funded Transit proj ect that will be advertised by S an Miguel County. This proj ect involves construction of a paved park-and-ride facility on Lot Hub-2C between S

  • ciety

Drive and S H 145 j ust west of Telluride.

slide-23
SLIDE 23

Archuleta CO Pagosa Junction BRO; 21898

Local Agency: Archuleta County

Planned Ad Date: S pring of 2018

Approximate Budget: $250,000

Work: This is an Archuleta County proj ect for the rehabilitation of bridge structure AR500-15.8-S 151 located on CR 500 (Truj illo Rd) at Pagosa Junction within the S

  • uthern Ute Indian Tribe Reservation. The

bridge is currently structurally deficient and will be rehabilitated and brought up to current standards with this proj ect.

slide-24
SLIDE 24

FY 17 Durango School Signs SRTS; 22063

Local Agency: City of Durango

Planned Ad Date: S ummer of 2018

Approximate Budget: $75,000

Work: Procurement of school signs at various locations around the City of Durango.

slide-25
SLIDE 25

Local Agency Projects for Design

slide-26
SLIDE 26

Archuleta CO Pagosa Junction BRO; 21898

Local Agency: Archuleta County

Planned Ad Date: Fall/ Winter 2017

Approximate Budget: $250,000

Work: This is an Archuleta County proj ect for the rehabilitation of bridge structure AR500- 15.8-S 151 located on County Road 500 (Truj illo Rd) at Pagosa Junction within the S

  • uthern

Ute Indian Tribe Reservation. The bridge is currently structurally deficient and will be rehabilitated and brought up to current standards with this proj ect. CDOT S taff Bridge has offered to complete Bridge Rehab Design but a Consulting Engineering Firms will be needed to complete clearances, finalize plans and specs and prepare bid package.

slide-27
SLIDE 27

Durango College Dr and E 8th Ave; 22062

Local Agency: City of Durango

Planned Ad Date: Fall/ Winter 2018

Approximate Budget: $1 million

Work: Trolley stop improvements using CDOT FAS TER Transit funding and road diet/ safety improvements using CDOT HS IP funding on College Dr from E 3rd Ave to E 8th Ave and on E 8th Ave from College Dr to 1st S t.

slide-28
SLIDE 28

Archuleta CR 600 Guardrail; 22269

Local Agency: Archuleta County

Planned Ad Date: Fall/ Winter 2017

Approximate Budget: $100,000

Work: Improvements to guardrail on Archuleta CR600 (Piedra Rd). Approximately 6 recently installed guardrail end treatments are too close to the travelled way and need to be flared away from traffic on the approach end. Design appropriate modifications and work through enviro, ROW and utility clearances and prepare bid documents.