Region 5 Upcoming Projects Summer/Fall 2019 The budget amount provided does not only reflect the construction costs for projects. The amounts may include ROW, engineering, design, and utility costs. The projects in this presentation are not
The budget amount provided does not only reflect the construction costs for projects. The amounts may include ROW, engineering, design, and utility costs. The projects in this presentation are not guaranteed to go to advertisement.
Projects located in Archuleta, La Plata, Mineral, Montezuma, San Miguel Counties
R5 Guardrail West; 22120
∙ Planned Ad Date: October 25, 2018 ∙ Approximate Budget: $1.25 million ∙ Counties: Archuleta, La Plata, San Miguel, Montrose ∙ Work: Replace old standard guardrail end treatments with current standard end treatments.
SH 145 Passing Lanes at Deep Creek; 20600
∙ Planned Ad Date: December 20, 2018 ∙ Approximate Budget: $6.5 million ∙ County: San Miguel ∙ Work: The project will widen and overlay SH 145
from MM 73.9 at Illium Road to MM 75.1 at the County and CDOT facilities at Deep Creek. This work will add an uphill passing lane toward Telluride and widen
- shoulders. There will be a stacked rockery cut wall on
the north side of the highway and a reinforced soil slope basket wall on the south side of the highway. There will be guardrail work. Drainage pipes will be replaced and a 10 x 6 box culvert will replace the existing corrugated metal pipes at Deep Creek.
US 160 Priority Culvert; 20693
∙ Planned Ad Date: April 4, 2019 ∙ Approximate Budget: $2 million ∙ County: Archuleta, Mineral, Montezuma ∙ Work: This project consists of a box culvert repair on MM 150.40. There will be three culvert liners- MM 43.18, 156.40, 168.07.
US 160 Mesa Verde Chipseal; 20686
∙ Planned Ad Date: October 25, 2018 ∙ Approximate Budget: $4.5 million ∙ County: Montezuma ∙ Work: This double chipseal goes from US 160 Mancos Hill (MM 41.00) to Cortez (MM 61.58). Work includes a double chipseal with some areas only requiring a single chipseal, fog seal, inlaid MMA pavement markings and temporary final high build stripes.
US 550/160 Ped Sidewalk Ramps; 22086 ESB-Restricted Project
∙ Planned Ad Date: October 25, 2018 ∙ Mandatory Pre-Bid Meeting: November 7th at 9:00am- 3803 N Main Ave, Durango ∙ Approximate Budget: $600,000 ∙ County: La Plata ∙ Work: The work includes utility relocation, storm drain inlet modifications, placement of pavement, curb and getter, sidewalk, median cover material and concrete curb ramps conforming to the latest requirements of the American with Disabilities Act within the City limits of Durango.
US 160 Passing Lane North of Towaoc; 20325
∙ Planned Ad Date: October 25, 2018 ∙ Approximate Budget: $11 million ∙ County: Montezuma ∙ Work: The project includes approximately 2
miles (between MM 27.75 to MM 29.75) of Full Depth Reclamation (FDR) of US 160/491. Alternating passing lane/highway widening construction, side & cross culvert replacements, slip-lining one (1) existing cross culvert, re-alignment of CR A & CR B, installation of 6"-12" HDPE waterline (possible the length of the project), seeding and striping.
Leveling Course with HMA; 20684
∙ Planned Ad Date: October 25, 2018 ∙ Approximate Budget: $15 million ∙ County: Dolores, Montezuma ∙ Work: This project consists of the placement of a HMA leveling course followed by a stone matrix asphalt
- verlay on US 491 from MP 36.8-MP 44.5.
There are intersection improvements at Montezuma CR S and Montezuma CR BB.
FY 19 Bridge Repairs; 20680
∙ Planned Ad Date: May 2, 2019 ∙ Approximate Budget: $2 million ∙ County: Archuleta and La Plata ∙ Work: Bridge Preventative Maintenance including, but not limited to, overlays, waterproofing, spall repairs, rip rap.
Bridges: O-05-H Hermosa Creek Bridge US 550 O-08-A San Juan River US 160 P-07-D Piedra River SH 151 P-05-AI Drainage US 550 P-05-AH Drainage US 550
Projects located in Alamosa, Costilla, Rio Grande, Saguache Counties
SH 159 San Luis to Ft Garland Surface Treatment; 21559
∙ Planned Ad Date: November 8, 2018 ∙ Approximate Budget: $7 million ∙ County: Costilla ∙ Work: The project consists of a hot mix
asphalt leveling course and overlay, replacing faded signs and delineators, new pavement marking, and gravel shouldering. The project may also include upgrading the railroad crossing just south of Fort Garland. MP 19.5 to 34.5 (the US 160 and SH 159 intersection in Fort Garland).
SH 112 from US 285 to SH 17; 21317
∙ Planned Ad Date: November 8, 2018 ∙ Approximate Budget: $5 million ∙ County: Alamosa, Rio Grande, Saguache ∙ Work: The project consists of a hot mix
asphalt leveling course and overlay, replacing faded signs and delineators, new pavement marking, new gravel shouldering, and a single ADA ramp in the Town of Center. MP 13.25 to MP 27.79.
Traffic and Safety Projects
US 160-550 Durango Signal; 20740
∙ Planned Ad Date: December 6, 2018 ∙ Approximate Budget: $1.2 million ∙ County: La Plata ∙ Work: New detection, communications, and backplate borders at 18 traffic signals in Durango.
R5 FY18 Tape and Pavement Markings; 22832
∙ Planned Ad Date: December 20, 2018 ∙ Approximate Budget: $1 million ∙ County: La Plata ∙ Work: Replace existing pavement markings on US 160 between MP 83.34 (just east of the CFI) to 85.76 (west end
- f the high bridge).
Local Agency Construction Projects
Salida US 50 Sidewalks Phase 4; 20557
∙ Local Agency: City of Salida ∙ Planned Ad Date: Winter of 2018 ∙ Approximate Budget: $800,000 ∙ Work: This project involves the construction of concrete sidewalk separated from the back of curb with a colored, textured concrete buffer on both sides of US 50 from Palmer St to the intersection of SH 291 on US 50 in Salida. Some curb and gutter and curb ramps may be replaced. Some accesses may be moved
- r changed.