Region 5 Upcoming Projects Summer/Fall 2019 The budget amount provided does not only reflect the construction costs for projects. The amounts may include ROW, engineering, design, and utility costs. The projects in this presentation are not


slide-1
SLIDE 1

Region 5 Upcoming Projects

Summer/Fall 2019

slide-2
SLIDE 2

The budget amount provided does not only reflect the construction costs for projects. The amounts may include ROW, engineering, design, and utility costs. The projects in this presentation are not guaranteed to go to advertisement.

slide-3
SLIDE 3

Projects located in Archuleta, La Plata, Mineral, Montezuma, San Miguel Counties

slide-4
SLIDE 4

R5 Guardrail West; 22120

∙ Planned Ad Date: October 25, 2018 ∙ Approximate Budget: $1.25 million ∙ Counties: Archuleta, La Plata, San Miguel, Montrose ∙ Work: Replace old standard guardrail end treatments with current standard end treatments.

slide-5
SLIDE 5

SH 145 Passing Lanes at Deep Creek; 20600

∙ Planned Ad Date: December 20, 2018 ∙ Approximate Budget: $6.5 million ∙ County: San Miguel ∙ Work: The project will widen and overlay SH 145

from MM 73.9 at Illium Road to MM 75.1 at the County and CDOT facilities at Deep Creek. This work will add an uphill passing lane toward Telluride and widen

  • shoulders. There will be a stacked rockery cut wall on

the north side of the highway and a reinforced soil slope basket wall on the south side of the highway. There will be guardrail work. Drainage pipes will be replaced and a 10 x 6 box culvert will replace the existing corrugated metal pipes at Deep Creek.

slide-6
SLIDE 6

US 160 Priority Culvert; 20693

∙ Planned Ad Date: April 4, 2019 ∙ Approximate Budget: $2 million ∙ County: Archuleta, Mineral, Montezuma ∙ Work: This project consists of a box culvert repair on MM 150.40. There will be three culvert liners- MM 43.18, 156.40, 168.07.

slide-7
SLIDE 7

US 160 Mesa Verde Chipseal; 20686

∙ Planned Ad Date: October 25, 2018 ∙ Approximate Budget: $4.5 million ∙ County: Montezuma ∙ Work: This double chipseal goes from US 160 Mancos Hill (MM 41.00) to Cortez (MM 61.58). Work includes a double chipseal with some areas only requiring a single chipseal, fog seal, inlaid MMA pavement markings and temporary final high build stripes.

slide-8
SLIDE 8

US 550/160 Ped Sidewalk Ramps; 22086 ESB-Restricted Project

∙ Planned Ad Date: October 25, 2018 ∙ Mandatory Pre-Bid Meeting: November 7th at 9:00am- 3803 N Main Ave, Durango ∙ Approximate Budget: $600,000 ∙ County: La Plata ∙ Work: The work includes utility relocation, storm drain inlet modifications, placement of pavement, curb and getter, sidewalk, median cover material and concrete curb ramps conforming to the latest requirements of the American with Disabilities Act within the City limits of Durango.

slide-9
SLIDE 9

US 160 Passing Lane North of Towaoc; 20325

∙ Planned Ad Date: October 25, 2018 ∙ Approximate Budget: $11 million ∙ County: Montezuma ∙ Work: The project includes approximately 2

miles (between MM 27.75 to MM 29.75) of Full Depth Reclamation (FDR) of US 160/491. Alternating passing lane/highway widening construction, side & cross culvert replacements, slip-lining one (1) existing cross culvert, re-alignment of CR A & CR B, installation of 6"-12" HDPE waterline (possible the length of the project), seeding and striping.

slide-10
SLIDE 10

Leveling Course with HMA; 20684

∙ Planned Ad Date: October 25, 2018 ∙ Approximate Budget: $15 million ∙ County: Dolores, Montezuma ∙ Work: This project consists of the placement of a HMA leveling course followed by a stone matrix asphalt

  • verlay on US 491 from MP 36.8-MP 44.5.

There are intersection improvements at Montezuma CR S and Montezuma CR BB.

slide-11
SLIDE 11

FY 19 Bridge Repairs; 20680

∙ Planned Ad Date: May 2, 2019 ∙ Approximate Budget: $2 million ∙ County: Archuleta and La Plata ∙ Work: Bridge Preventative Maintenance including, but not limited to, overlays, waterproofing, spall repairs, rip rap.

Bridges: O-05-H Hermosa Creek Bridge US 550 O-08-A San Juan River US 160 P-07-D Piedra River SH 151 P-05-AI Drainage US 550 P-05-AH Drainage US 550

slide-12
SLIDE 12

Projects located in Alamosa, Costilla, Rio Grande, Saguache Counties

slide-13
SLIDE 13

SH 159 San Luis to Ft Garland Surface Treatment; 21559

∙ Planned Ad Date: November 8, 2018 ∙ Approximate Budget: $7 million ∙ County: Costilla ∙ Work: The project consists of a hot mix

asphalt leveling course and overlay, replacing faded signs and delineators, new pavement marking, and gravel shouldering. The project may also include upgrading the railroad crossing just south of Fort Garland. MP 19.5 to 34.5 (the US 160 and SH 159 intersection in Fort Garland).

slide-14
SLIDE 14

SH 112 from US 285 to SH 17; 21317

∙ Planned Ad Date: November 8, 2018 ∙ Approximate Budget: $5 million ∙ County: Alamosa, Rio Grande, Saguache ∙ Work: The project consists of a hot mix

asphalt leveling course and overlay, replacing faded signs and delineators, new pavement marking, new gravel shouldering, and a single ADA ramp in the Town of Center. MP 13.25 to MP 27.79.

slide-15
SLIDE 15

Traffic and Safety Projects

slide-16
SLIDE 16

US 160-550 Durango Signal; 20740

∙ Planned Ad Date: December 6, 2018 ∙ Approximate Budget: $1.2 million ∙ County: La Plata ∙ Work: New detection, communications, and backplate borders at 18 traffic signals in Durango.

slide-17
SLIDE 17

R5 FY18 Tape and Pavement Markings; 22832

∙ Planned Ad Date: December 20, 2018 ∙ Approximate Budget: $1 million ∙ County: La Plata ∙ Work: Replace existing pavement markings on US 160 between MP 83.34 (just east of the CFI) to 85.76 (west end

  • f the high bridge).
slide-18
SLIDE 18

Local Agency Construction Projects

slide-19
SLIDE 19

Salida US 50 Sidewalks Phase 4; 20557

∙ Local Agency: City of Salida ∙ Planned Ad Date: Winter of 2018 ∙ Approximate Budget: $800,000 ∙ Work: This project involves the construction of concrete sidewalk separated from the back of curb with a colored, textured concrete buffer on both sides of US 50 from Palmer St to the intersection of SH 291 on US 50 in Salida. Some curb and gutter and curb ramps may be replaced. Some accesses may be moved

  • r changed.
slide-20
SLIDE 20

Buena Vista Arizona St; 17133

∙ Local Agency: City of Buena Vista ∙ Planned Ad Date: Winter of 2018/2019 ∙ Approximate Budget: $600,000 ∙ Work: This project involves the construction of bicycle lanes, shared use path, sidewalk, ADA ramps, and pedestrian bridge

slide-21
SLIDE 21

Pagosa Springs North 8th Street SRTS; 21504

∙ Local Agency: Town of Pagosa Springs ∙ Planned Ad Date: Winter of 2018 ∙ Approximate Budget: $400,000 ∙ Work: This project involves construction of sidewalks and curb and gutter in the north Pagosa Springs residential neighborhood on North 8th St and Florida St.

slide-22
SLIDE 22

San Miguel County 55P-0.2-27 Bridge Replacement; 21437

∙ Local Agency: San Miguel County ∙ Planned Ad Date: Winter of 2018/2019 ∙ Approximate Budget: $900,000 ∙ Work: The project scope involves the replacement of a bridge structure located on Juniper Village Dr. The replacement bridge will be constructed just to the SE of the existing bridge.

slide-23
SLIDE 23

Local Agency Projects for Design

slide-24
SLIDE 24

Manassa Elementary Safe Routes to School; 22531

∙ Local Agency: Town of Manassa ∙ Planned Ad Date: Winter of 2019/2020 ∙ Approximate Budget: $350,000 ∙ Work: This project involves upgrades to the existing sidewalk along 5th Street along with a bike lane. Improvements to the crossing for Main St are also included- these consist of bump outs and reconstructed curb ramps.