watkins glen cs d capital proj ect 2017 agenda
play

Watkins Glen CS D Capital proj ect 2017 Agenda Capital Proj ect - PowerPoint PPT Presentation

Watkins Glen CS D Capital proj ect 2017 Agenda Capital Proj ect 2017 Planning S cope of Work Building Condition S urvey (BCS ) S ite Work Financing Timeline Capital proj ect 2017: Planning NYS ED Requirements


  1. Watkins Glen CS D Capital proj ect 2017

  2. Agenda • Capital Proj ect 2017 • Planning • S cope of Work • Building Condition S urvey (BCS ) • S ite Work • Financing • Timeline

  3. Capital proj ect 2017: Planning • NYS ED Requirements • 2015 Building Condition S urvey (BCS ) • Five-Y ear Plan • Board of Education Facilities Committee studied needs of the District. • S uperintendent of S chools, Facilities Director and HUNT Engineers & Architects all met to review committee work and 5-Y ear BCS

  4. Capital Proj ect 2017: BCS Work • General Building Work (Phase 1): • Replace Floor Finish in ES Library & Kindergarten Corridor • Interior & Exterior Masonry Repair at ES • Replace Exterior Concrete S tair At ES Mechanical Room • HS Boiler Pump Replacement • Replace Corridor Wall Tile • Replace Existing Bus Lift • Replace Non Code Compliant Doors • Pool Filtration Equipment Replacement • ARC Flash Labeling

  5. Capital Proj ect 2017: BCS Work • Elementary Gymnasium Renovations (Phase 1): • Floor Finish Replacement • Wall Pad Replacement • Masonry Wall Repair • Mechanical Equipment Replacement • Lighting Replacement • Elementary Nurse S uite Improvements (Phase 1): • Casework Upgrades • Floor Finish Replacement • Ceiling Replacement

  6. Capital Proj ect 2017: BCS Work • Classroom Improvements (Phase 1): • S ecurity Hardware • Casework Upgrades • Floor Finish Replacements • Ceiling Replacements • Wall Tile Wainscot Replacement

  7. Capital Proj ect 2017: BCS Work • General Building Work (Phase 2): • Provide Office Ventilation • Provide Broadcasting Capabilities at Field House & Auditorium • Provide Additional S mall Vehicle Lift • Classroom Improvements (Phase 2): • Upgrade to IP Paging & Clock S ystem • Elementary TV S tudio Improvements (Phase 2): • Renovate S pace to Meet Curriculum Needs • Update Equipment

  8. Capital Proj ect 2017: BCS Work • Elementary Kitchen Improvements (Phase 2): • Equipment Replacement • Repair Existing Hood and Provide Additional Hood for Oven • Modify S erving Line to Accommodate S tudent Flow • Elementary Auditorium Improvements (Phase 2): • Ceiling Replacement • Provide Additional Equipment

  9. Capital Proj ect 2017: S ite Work • S ite Work (Phase 1): • Update Exterior Lighting at Bleachers • S ynthetic Turf at S tadium, Baseball & S oftball Fields • Pave Utility Access Road • S tadium Fence Improvements • Additional Tennis Court • S idewalk Repairs • Playground S urfacing Improvements

  10. Capital Proj ect 2017: Financing • Phase 1 Total: $5,895,383 • Phase 2 Total: $1,647,266 • Phase 3 Total: $1,446,063 • Phase 4 Total: $3,650,467 • Total Cost of Proj ect: $12,640,000 • S tate Aid Ratio: 80.9% • Capital Reserve: $1,400,000 • Existing Capital Aid: $2,545,170 • Additional Tax Impact: Zero

  11. Capital Proj ect 2017: Timeline S EQR Approval/ Resolution by BoE February 6, 2017 Vote March 28, 2017 Construction S tart Dates: Phase 1: Level 1 Work S pring 2018 Phase 2: Level 2 Work Fall 2018 Phase 3: Roof Replacement 2021 Phase 4: Roof Replacement 2023

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.