R35024A SR 9 PCCP Overlay Discussion Topics Phases Traffic - - PowerPoint PPT Presentation

r35024a sr 9 pccp overlay discussion topics
SMART_READER_LITE
LIVE PREVIEW

R35024A SR 9 PCCP Overlay Discussion Topics Phases Traffic - - PowerPoint PPT Presentation

R35024A SR 9 PCCP Overlay Discussion Topics Phases Traffic Control Mix Design Construction Method Challenges Phases Completed E1 1.1 miles 2000 cy E2 1.1 miles 2000 cy D1 1.63 miles 3000 cy D2


slide-1
SLIDE 1

R35024A SR 9 PCCP Overlay

slide-2
SLIDE 2
  • Phases
  • Traffic Control
  • Mix Design
  • Construction Method
  • Challenges

Discussion Topics

slide-3
SLIDE 3

Phases Completed

  • E1

1.1 miles 2000 cy

  • E2

1.1 miles 2000 cy

  • D1 1.63 miles 3000 cy
  • D2 1.63 miles 3000 cy
  • C1 2.46 miles 4400 cy
  • C2 2.46 miles 4400 cy
  • B2.1 1.4 miles 2600 cy
  • B2.2 1.4 miles 2600 cy
slide-4
SLIDE 4

Phases

  • B1.1 0.8 miles 1400 cy 24 Hour Traffic control
  • B1.2 0.8 miles 1400 cy 24 Hour Traffic control
  • A1 1.57 miles 2900 cy
  • A2 1.57 miles 2900 cy
  • F1 1.15 miles 2100 cy 24 Hour Traffic control
  • F2 1.15 miles 2100 cy 24 Hour Traffic control
slide-5
SLIDE 5

Traffic Control

  • Two types for PCCP
  • Road Closed to thru traffic Sections E, D, C, B2, A
  • 24 hour bi-directional traffic control B1, F
slide-6
SLIDE 6

Mix Design

  • Included 4# of Macro Fibers
  • Was designed to get breaks in 30-36 hours due to the construction

timetable

  • Plant was located At US Aggregate Flat Rock Site
slide-7
SLIDE 7

Plant Site

slide-8
SLIDE 8

Basic Outline of Method

  • Shift into traffic control
  • Profile Mill
  • Shoulder Mill
  • Asphalt Patching
  • Shoulder Treatment
  • Install Bars
  • Concrete Pave 6” overlay 8” on shoulder
  • Install Shoulder Cap
slide-9
SLIDE 9

Profile Milling

slide-10
SLIDE 10

Shoulder Treatment

slide-11
SLIDE 11

Install bars

slide-12
SLIDE 12

Concrete Paving

slide-13
SLIDE 13

Concrete Paving

slide-14
SLIDE 14

Concrete Paving

slide-15
SLIDE 15

Concrete Paving

slide-16
SLIDE 16

Concrete Paving

slide-17
SLIDE 17

Concrete Paving

slide-18
SLIDE 18

Concrete Paving

slide-19
SLIDE 19

Concrete Paving

slide-20
SLIDE 20

Concrete Paving

slide-21
SLIDE 21

Concrete Paving Curing 2X

slide-22
SLIDE 22

Concrete paving Hand work fill-ins

slide-23
SLIDE 23

Finished Product

slide-24
SLIDE 24

Finished Product

slide-25
SLIDE 25

Finished Product

slide-26
SLIDE 26
  • Phases 14
  • Traffic Control: lots of thru traffic
  • Mix Design construction schedule
  • Construction Method
  • Bars installation
  • Saw-cutting 165,000 lf
  • Stable Trackline
  • Three structures with thickened transitions

Challenges

slide-27
SLIDE 27

Thank you