Conten ents 1 Canal 2 PCCP pipe 3 Tunnel 1 Canal The middle - - PowerPoint PPT Presentation

conten ents
SMART_READER_LITE
LIVE PREVIEW

Conten ents 1 Canal 2 PCCP pipe 3 Tunnel 1 Canal The middle - - PowerPoint PPT Presentation

South South-to to-No North rth Water Dive ivers rsion ion mid iddle dle r rout oute e China Institute of Water Resources and Hydropower Research IWHR Conten ents 1 Canal 2 PCCP pipe 3 Tunnel 1 Canal The middle route


slide-1
SLIDE 1

South

South-to to-No North rth Water Dive ivers rsion ion( mid iddle dle r rout

  • ute

e )

China Institute of Water Resources and Hydropower Research(IWHR)

slide-2
SLIDE 2

Conten ents

1 Canal 2 PCCP pipe 3 Tunnel

slide-3
SLIDE 3

The middle route runs from Danjiangkou Reservoir to Beijing, on the Han river, a tributary of the Yangtze River. The elevation of canal is 147m to 61m by gravity flow. The completed canal route is approximately 1432 km long, initially providing 9.5 km3 of water annually. By 2030, water transfers is expected to increase to 12 to 13 km3 annually。

Main canal gravity flow 1432km Danjiangkou Reservoir

1 Canal

slide-4
SLIDE 4

1432km canal by gravity flow 27.3 km South main canal of Beijing Danjiangkou Reservoir Beijing

1 Canal

Huinanzhuang Pumping station PCCP pipe 2×4.0m 57km

slide-5
SLIDE 5

1 Canal

place Design discharge(m3/s) Design water elevation(m) Canal head~Fang cheng 630 147.2~137.8 Pass the Yellow river 500 119.5 Entry Hebei province 415 106.0~91.3 Beijing 50 61.1 Slope is 1/25000 in the south of Yellow River, and 1/30000~1/15000 in the north of Yellow River. Design depth is 9.5m to 3.5m, and Bottom width is 56m~ 7m.

slide-6
SLIDE 6

1 Canal   Pass through aross theYellow River

Pass under Yellow River , length 4250m, discharge 500m3/s,tunnel diameter 2×7m. By TBM(tunnel boring machine)

slide-7
SLIDE 7

1 Canal    flume

Duan he flum, length 1030m, discharge 350m3/s,increase discharge 420m3/s

slide-8
SLIDE 8

2 PCCP pipe

PCCP pipe 2×4.0m 57km Huinanzhuang pumping station South Main Canal in Beijing 27.3km Daning pressure regulating pool

slide-9
SLIDE 9

The main canal in Beijing is 2×4.0PCCP(inner diameter 4.0m, maximum

  • utside diameter 4852mm), and total length is 57km. The design discharge

is 50m3/s, increase discharge is 60m3/s, and the gravity flow is 20m3/s. Operations are the follows: discharge Q <20m3/s by gravity flow , and Q > 20m3/s by pump at Huinanzhuang Pumping Station.

2 PCCP pipe

PCCP 2×4.0m

slide-10
SLIDE 10

2 PCCP pipe    factory

Formwork of PCCP PCCP factory

slide-11
SLIDE 11

2 PCCP pipe    structure

slide-12
SLIDE 12

2 PCCP pipe   standard

single rubber ring double rubber ring

slide-13
SLIDE 13

2 PCCP pipe   Production process

Curing

Steel wiring

Paint Spray Tube core curing Tube core forming Welding repair Cylinder production Socket making Cylinder test

Technological process

slide-14
SLIDE 14

There 101 air inbreathe-release valve well in 57km water supply pipeline, diameter 400mm.

2 PCCP pipe   air inbreathe-release valve

Standard Drawing Valve well air inbreathe-release valve

slide-15
SLIDE 15

Design discharge 60 m3/s, head of delivery 58.2m, total installed capacity 58.4 MW. installed 8 pump, discharge 10 m3/s , head of delivery 58.2m, capacity 7.3 MW.

2 PCCP pipe  Huinanzhuang pumping station

slide-16
SLIDE 16

The function of Daning pressure regulating pool is pressure regulation and diversion.

2 PCCP pipe  Daning pressure regulating pool

Daning reservoir Daning pressure regulating pool

slide-17
SLIDE 17

2 PCCP pipe  Daning pressure regulating pool

Daning pressure regulating pool, diameter 80m, depth 16m, volume 78000m3.

slide-18
SLIDE 18

2 PCCP pipe  Daning reservoir

The function of Daning reservoir is regulating water quantity, storage capacity 37 million m3, total area 1.34km2,

slide-19
SLIDE 19

3 Tunnel   Beijing south main canal

The length of Beijing south main canal is 27.3km, up section 11.02km designed in shallow buried excavation method, and down section 15.980km by TBM(tunnel boring machine)

up section 11.302km Shallow Shallow buried excavation buried excavation method method Daning reservoir South Main 15.980km TBM method

slide-20
SLIDE 20

3 Tunnel   Beijing south main canal

up section 11.302km Shallow buried excavation method Daning reservoir South Main 15.980km TBM method The structures of Beijing south main canal

slide-21
SLIDE 21

Up section 11.302km 2×DN3400 tunnel, Shallow buried excavation method Design discharge 30m3/s Increase discharge35m3/s

3 Tunnel   Shallow buried excavation method

slide-22
SLIDE 22

After the completion of construction excavation, reinforced concrete lining is constructed by trolley, inner lining thickness 300mm~350mm.

3 Tunnel   Shallow buried excavation method

slide-23
SLIDE 23

3 Tunnel   Shallow buried excavation method

Outside lining construction

Excavation Outside lining complete Joint

slide-24
SLIDE 24

Down section 15.980km DN4700 tunnel, Inner lining thickness 300mm TBM(tunnel boring machine )method, Design discharge 27m3/s Increase discharge32m3/s。

3 Tunnel    TBM(tunnel boring machine)

Design section TBM

slide-25
SLIDE 25

TBM Construction TBM control room Outside lining concrete block

3 Tunnel    TBM(tunnel boring machine)

Outside lining complete

slide-26
SLIDE 26

Flow control valve can control the discharge precisely for water supply plant

3 Tunnel   flow control valve

Controller Structure drawing Flow control valve Drawing

slide-27
SLIDE 27

Thank you