Roadway Improvements Parkway Drive Area Public Information Centre Date: Thursday February 16, 2017 Location: Mountainside Recreation Centre 2205 Mount Forest Drive Time: 5:30 pm to 7:30 pm Project Team Councillor John Taylor
Project Team
Councillor John Taylor John.Taylor@burlington.ca City of Burlington Scott Hamilton, Manager of Design & Construction Dave Johnson, Project Manager Aaron Kuryluk, Senior Design Technician Tom Georgiadis, Contract Administrator
Federal gas tax funds at work in your community. Les fonds de la taxe fédérale sur l’essence à l’oeuvre dans votre communauté. Design and Construction – Capital Works
Project Limits - Parkway Drive, Moss Glen Road and Niels Avenue
Design and Construction – Capital Works
Existing Conditions
Design and Construction – Capital Works
Existing Conditions
Design and Construction – Capital Works
Project Overview
Roadway Improvements – Parkway Drive Area The proposed work includes the following:
- Remove and replace existing road asphalt
- Remove and replace concrete curbs and sidewalks
- Storm sewer repairs where required
- Replace concrete street light poles, complete with LED lighting
Design and Construction – Capital Works
Project Overview Typical Road Reconstruction
Design and Construction – Capital Works
Project Schedule
Public Information Centre: February 16, 2017 Tender Period: April 2017 Construction Period: June through September 2017 (School block, July – August) Budget $ 1,725,000
Design and Construction – Capital Works
Project Team Contacts
Councillor John Taylor Phone: 905-335-7600 ext. 7459 Ward 3 Email: John.Taylor@Burlington.ca Capital Works Dave Johnson Phone: 905-335-7600 ext. 7507 Design & Construction Project Manager Email: David.Johnson@burlington.ca Aaron Kuryluk Phone: 905-335-7600 ext. 7687 Senior Design Technician Email: Aaron.kuryluk@burlington.ca Tom Georgiadis Phone: 905-335-7600 ext. 7806 Contract Administrator Email: Tom.Georgiadis@burlington.ca
Design and Construction – Capital Works
Project updates can be found at: http://www.burlington.ca/en/services-for-you/parkway-drive-area-minor-reconstruction.asp To receive email updates about this project, please "Subscribe to this page...". on the project web page. Project updates will automatically be sent to you as the pages are updated.
Design and Construction – Capital Works
please use next page if more space is required F
Thank you for your participation in this project.
Comment Sheet
Roadway Improvements – Parkway Drive Area
Please deposit on departure
- r mail/e-mail by March 2, 2017
Name: Address: Telephone: Email: Please return to: Tom Georgiadis, Contract Administrator City of Burlington, Capital Works Department 426 Brant Street, P.O. Box 5013, Burlington ON L7R 3Z6 Fax: 905-335-7822 Email: Tom.Georgiadis@burlington.ca Design and Construction – Capital Works
Design and Construction – Capital Works
Roadway Improvements – Parkway Drive Area