Protection & Slope Stabilisation Scheme NOVEMBER 2016 - - PowerPoint PPT Presentation

protection
SMART_READER_LITE
LIVE PREVIEW

Protection & Slope Stabilisation Scheme NOVEMBER 2016 - - PowerPoint PPT Presentation

Scarborough Spa Coast Protection & Slope Stabilisation Scheme NOVEMBER 2016 Contents Context Slope Stabilisation, Geology and Engineering Landscape Management Ecology Trees Cultural Heritage Noise, Vibration,


slide-1
SLIDE 1

Scarborough Spa Coast Protection & Slope Stabilisation Scheme

NOVEMBER 2016

slide-2
SLIDE 2

Contents

  • Context
  • Slope Stabilisation, Geology and Engineering
  • Landscape Management
  • Ecology
  • Trees
  • Cultural Heritage
  • Noise, Vibration, Dust
  • Access
  • Next Steps
slide-3
SLIDE 3

Slope Stability

The South Cliff upon which the proposed works area lies is inherently unstable. As a result the area has witnessed major landslides, including in 1737, when the cliff collapsed destroying the spa buildings. In 1993, approximately 1km to the south

  • f the proposed works area, the Holbeck

Hotel was destroyed with a substantial part of the Holbeck Gardens removed

  • also. The cliff retreated 70m inland,

whilst the mud/debris flow overran the sea wall to project 135m onto the beach. Numerous smaller scale landslides have

  • ccurred within the Spa Gardens,

resulting in the closure of footpaths. Furthermore, investigations in the 1970s and 1980s found that several locations in The Spa Complex were being adversely affected by earth pressure and soil movements, probably caused by water

  • pressure. Wells were sunk to manage

water pressure, but these were found to be no longer effective in the 1990s.

slide-4
SLIDE 4

Deep seated multiple rotational landslide mainly developed in till Coastal slopes developed in glacial till and underlying bedrock. Currently affected by small-scale shallow landslides

The north east coastline of England has a history of slips. Many people will remember the famous landslip that caused Holbeck Hall to fall into the sea. However, the particular mechanism of how the coast slips depends on numerous factors. This includes:

  • If the area has previously slipped
  • The local ground conditions (or geology).
  • The depth to rock head or competent material
  • The local ground water conditions

At Scarborough Spa, deep seated slips occur along the top of the bedrock (sandstone) through a thin layer of weak sandstone. The engraving above , is of a large slip that destroyed the original spa building in 1737. By considering the history, geology and groundwater conditions at the site, we can develop an engineering solution to reduce the risk of future slope failure.

A A

History of slope failure at Scarborough Spa

slide-5
SLIDE 5

Risk of Slope failure

This poster shows a section through the Spa Building, running down from the esplanade to the Spa Building. We have carried out ground investigations and conducted engineering analysis that has helped us to quantify the risk of slope failure behind the Spa Building. Our analysis has shown there is risk of two types of slope failure in this particular section: The first is a deep slip occurring from the Esplanade, passing beneath the Spa building and surfacing in front of the building but behind the sea-wall (See the red line on the Image to the right). The second is shallow slips occurring from the mid-way down the slope and surfacing in the bottom third of the slope above the lower paths (See the blue line on the image above the deep slip line to the right ) In addition there is also the risk of lots of very shallow slips occurring at the surface.

Spa Building Esplanade

slide-6
SLIDE 6

Proposed Solution: Deep Slips

To resist the deep seated slip (shown in Red) it is proposed to install a number of steel piles embedded into the bed rock below (Sandstone). The piles terminate in the Sandstone as it is a strong competent layer that slips cannot easily pass through. The steel piles prevent slips occurring above the Sandstone by reinforcing the soil in that area. The piles will have a diameter of approximately 0.4m (or just over a foot). The piles will be installed by widening the existing path to make room for a piling platform. To ensure the path is stable during construction the piling platform will be constructed using soil nails above and below the path, and a shotcrete (sprayed concrete) face. After construction, the path will be returned to its original

  • width. This will be achieved by placing

engineered fill in front of the shotcrete face and then finishing off with a traditional stone wall.

Soil nails in lower slope to allow installation of piles Pile to resist deep slips

slide-7
SLIDE 7

Proposed Solution for Shallow Slips

The steel piles are installed deep into the sandstone to arrest the risk of deep slips, however

  • n their own they do not prevent all the possible
  • slips. There is still the risk of shallow slips occurring

between the top of the slope and the piles (as shown by the blue line). To resist the shallow slips above the piles it is necessary to install soil nails above the pile and re-grade the soil profile. The soil nails penetrate potential slip circles, by acting like reinforcement elements. For the soil nails to work they must be installed in conjunction with a facing system. The facing system consists of steel head plates and a steel mesh, which help to transfer the weight of the soil between the nails back into the soil nails. Soil nail heads and mesh can look unsightly. Therefore they have been designed with a covering (geo-cell) that will allow topsoil to be replaced and planted with seeds – see the later soil nail head

  • detail. As a result, a short time after construction

the topsoil will ‘green’ up and the soil nails and topsoil containers (geo-cell) will not be visible. Finally, between the ground and the steel mesh an erosion protection mat and a drainage layer is

  • installed. These will help to prevent surface ground

water eroding the soil and reduce the water within the slope, thus improving the stability.

(temporary construction platform)

slide-8
SLIDE 8

Creation of temporary construction platform and soil nail installation

Precise placement of nails along the length of the construction zones using anchored long arm reach excavator plant

slide-9
SLIDE 9

General Arrangement

The Proposed Development for which planning permission is sought comprises: “Slope stabilisation scheme including clearance works to remove existing trees, regrading of existing slope and use of soil nailing and soil piling measures, retention and reinstatement of masonry walls, installation of new drainage measures and subsequent landscaping works.”

  • Soil nails – to sufficient length (between 2.5m

to 25m) to extend past the active slip plane and provide shear resistance to increase the factor of safety against shallow failures. The spacing of the soil nails will vary from 1.5m to 2.5m horizontally and 1m to 1.5m vertically.

  • Nail Heads – to fix the head of the nail in

place and hence reduce local surface instability between nails. Nail heads will be of sufficient size and thickness to ensure adequate load transfer to the nails.

  • Mesh throughout area– laid beneath the nail

heads to help with erosion control and establishment of vegetation on the slope.

  • Top soil retention – where required, a geocell

system will be used over the top of the mesh to retain topsoil in place and hide the soil nails and head plates.

slide-10
SLIDE 10

Zone 1

slide-11
SLIDE 11

Zone 2A

slide-12
SLIDE 12

Zone 2B

slide-13
SLIDE 13

Zone 3

slide-14
SLIDE 14

Retained Path Network

Following the completion of the engineering activities a scheme of landscape reinstatement works would be implemented to ensure that the intrinsic character of the public space is retained and enhanced in the long term. Dense woodland would be removed to create an open parkland space from which views of the Scarborough coastline can be enjoyed. The network of footpaths would be rationalised and reduced in overall

  • extent. Any perceived adverse effect that

would arise due, primarily, to the removal of a large number of mature trees, would be offset by the creation of a more diverse and attractive garden space that would have a strong relationship with the Spa buildings and the wider public spaces of the South Cliff and Valley Gardens. The site would lie at the heart of possible future Heritage Lottery funded South Cliff and Valley Gardens scheme and could complement the future aspirations for the comprehensive restoration and enhancement of the whole of the public gardens.

slide-15
SLIDE 15

Soil Nailed Wall

Retention of existing walls Existing masonry walls will be retained if at all possible. In locations where they are not damaged and there is not considered to be a long term risk associated with keeping them it is considered that they should be preserved. Where new masonry facing is required we will design replacement masonry walls that will be sympathetic with the appearance of the existing walls. Soil Nailing Soil nailing will be adopted in areas within the gardens where the slope angles are considered significant and in line with recently completed study and recommendations made on slope stability.

slide-16
SLIDE 16

Nail Head and Vegetated Facing

slide-17
SLIDE 17

Masonry Walls and Soil Nails

slide-18
SLIDE 18

Slopes LESS THAN 45o Slopes GREATER THAN 45o

Soil Nail and Re-grading The Finished Look

slide-19
SLIDE 19

Arboricultural Survey

Detailed tree and vegetation survey undertaken to establish:

  • Vegetation structure
  • Species composition
  • Quality of trees

Overall the survey was able to demonstrate the poor quality

  • f the tree and vegetation

coverage. We will clear the site of this poor quality vegetation – with the exception of a handful of higher quality trees Phased site clearance is planned in January 2017 and is expected to be completed before the beginning of the nesting season in March 2017.

Survey as existing As proposed

slide-20
SLIDE 20

Habitat Survey

The Application Site is not covered by any international, national or local nature conservation designations. The survey area comprises a steep coastal slope supporting semi-natural habitats including broad-leaved woodland and semi-improved neutral

  • grassland. Woodland, unimproved

neutral grassland and coastal cliff mosaics are identified as Local Priority Habitats in the Scarborough Biodiversity Action Plan The site forms part of the a network of coastal gardens inland of the Scarborough Spa. The gardens form a series of public walks and parks laid

  • ut from the mid-19th century until

the 1930’s and are designated as Grade II Listed on the English Heritage Register of Parks and Gardens

slide-21
SLIDE 21

Heritage Assessment

The proposed scheme will affect the setting of Grade II* listed Spa, affecting views of The Spa Complex from the beach and across the bay, replacing the heavily wooded backdrop to The Spa with a grassed backdrop broken by planting of shrubs and trees. Initially the newly completed scheme will present bare slopes and geocell material visible to varying degrees, thereby affecting the aesthetic appreciation of The Spa. This represents a low to moderate degree of harm in the spectrum of less than substantial harm to The Spa’s significance, but this will be temporary in nature and will reduce as the new planting matures. The proposed scheme will restore views that have been lost as a result of unmanaged tree growth. The Spa’s roofscape will be better revealed, thereby improving the experience of its significance. The proposed scheme will stabilise the slope above The Spa thereby preventing landslips from adversely affecting the significance of The Spa. The proposed scheme can therefore be seen to protect The Spa from potentially substantial damage from landslips that could go so far as to destroy the heritage asset.

slide-22
SLIDE 22

Noise and Vibration

The construction noise assessment has demonstrated that the stated construction activities will not exceed noise thresholds. However, construction noise predictions have shown that noise levels at the Spa building are likely to exceed standard criteria as a result of piling and soil nailing activities. This assessment has considered a partially open window scenario for offices within the building. It should be noted that the acoustic performance of the façade with closed windows will provide significantly more attenuation. In our experience, residents of buildings and in the surrounding areas in which construction activities are being undertaken are more amenable to the resultant noise as they will ultimately benefit from the works. It is therefore our view that although the noise thresholds may be exceeded due to certain construction activities, the likelihood of a significant long term noise impact on the residents is negligible. A qualitative assessment of construction traffic noise has been undertaken. It is not predicted that increased traffic movements as a result of construction will increase traffic flow on public highways in the vicinity by more than 25%. On this basis, construction traffic is likely to result in negligible noise impacts. A vibration impact assessment has shown that due to the nature of the proposed activities, and the relative distances to the principal identified receptors, the construction activity is unlikely to result in vibration impacts of above negligible significance. Based on the assessment, the proposed construction activity associated with the Scarborough Spa slope stabilisation scheme should not result in a significant noise or vibration impact at the nearest receptor with the exception of the Spa building.

\

Monitoring Position (MP2) Monitoring Position (MP1) NVSR_1 NVSR_3 NVSR_2 NVSR_4 NVSR_5 NVSR_6

slide-23
SLIDE 23

Dust

The assessment of construction dust impacts indicates that before the implementation of mitigation and controls, the risk of dust impacts will be medium for demolition, earthworks and construction; and low for removal of waste materials. The dust control and mitigation measures recommended will result in low impacts and is classed as “not significant”. The proposed slope stabilisation works does not, in air quality terms, conflict with national or local policies. There are no constraints to the development in the context of air quality.

slide-24
SLIDE 24

Landscape Plan

slide-25
SLIDE 25

Illustrative Landscape Master Plan

Following the completion of the engineering works a landscape reinstatement project would be implemented to ensure that the intrinsic character of the public space is retained and enhanced in the long term. Dense woodland would be removed to create an open parkland space from which views of the Scarborough coastline can be

  • enjoyed. The network of

footpaths would be rationalised and reduced in overall extent. Any perceived adverse effect that would arise due, primarily, to the removal of a large number of mature trees, would be offset by the creation of a more diverse and attractive garden space that would have a strong relationship with the Spa buildings and the wider public spaces of the South Cliff and Valley Gardens. The proposed slope stabilisation activities will offer the

  • pportunity to introduce a

landscape scheme and management regime that will ultimately improve the character and quality of the public gardens and reverse the ongoing atmosphere of decline.”

slide-26
SLIDE 26

Typical cross section: Existing Typical cross section: Proposed

Cross Sections

There are unlikely to be any significant adverse effects on the visual amenity of the works area in the long term as the landscape proposals develop and mature. Members of the public and visitors to Scarborough using the Esplanade, residential properties and tourist accommodation immediately

  • pposite the site on the

Esplanade, outdoor areas of the Spa Complex and adjacent areas of the South Cliff and Valley Gardens would initially experience a Moderate to Minor adverse level of effect in year one which would improve to Minor or Moderately beneficial as the landscape proposals mature.

slide-27
SLIDE 27
slide-28
SLIDE 28

Proposed Landscape Outcomes

slide-29
SLIDE 29

Proposed Access Routes

The vehicles generated during the works would be of typical HGV dimensions and generally be HG Rigid vehicles of up to 12.0m long. The number generated on a daily basis is not expected to be of a level that would result in highway capacity issues. Therefore, the strategy has concentrated on the suitability of access routes by way

  • f their geometries and ability for HGVs to route along them.

Vehicular access to the works area has been identified at an existing vehicular access into the cliff area at the bottom of Ramshill Road adjacent to its roundabout junction with Valley Road and Vernon

  • Road. A welfare area will be located on Esplanade broadly between

Albion Road and Prince of Wales Terrace and consisting of staff welfare facilities and tool and small material storage. An office area consisting of site offices, staff and subcontractor parking and material storage will be created on the Oliver Street Car Park. A range of agreed routes have been identified with North Yorkshire County Council (the Highway Authority), which are suitable for HGV use and can be used at any time. The preferred route option to the works area is as follows:

  • From the north: A171, A64, A165 and Ramshill Road;
  • To the north: Ramshill Road, A165, Queen Margaret’s Road,

A64 and A171;

  • From the west: A170 / A64, A165 and Ramshill Road;
  • To the west: Ramshill Road, A165, Queen Margaret’s Road

and A170 / A64; and

  • To / from the south: A165 and Ramshill Road.

The preferred route option to the welfare area is as follows:

  • From the north: A171, A64, A165 and Albion Road;
  • To the north: Prince of Wales Terrace, A165, A64 and A171;
  • From the west: A170 / A64, A165 and Albion Road;
  • To the west: Prince of Wales Terrace, A165, A64 and A170 /

A64;

  • From the south: A165 and Albion Road; and
  • To the south: Prince of Wales Terrace and A165.
slide-30
SLIDE 30

Proposed Temporary one way system extension

  • Existing One way system
  • Proposed extension of one way

system

slide-31
SLIDE 31

Office & Car Parking

Balfour Beatty welfare office and Esplanade works area Balfour Beatty proposed main compound, storage and parking

slide-32
SLIDE 32

Site boundary Optional Balfour Beatty parking

Potential one way system extension

slide-33
SLIDE 33

Work Area

Access 1

Access 2 Access 3 Access 4 BB Office area & car parking Option 1 BB Office area & car parking Option 2

Overall access plan

slide-34
SLIDE 34

Vehicle route onto site

Ramshill Road Access

slide-35
SLIDE 35

Detailed Access Route maintaining Public access to both Spa and Esplanade

Barrier segregated footpath to ensure safe movements of pedestrians and site operations Chalet junction managed to ensure safe passage of public during plant and material deliveries Plant and material access onto site Birdcage Walk providing public access to the Spa, Esplanade and footbridge Public access Site access

slide-36
SLIDE 36

What happens next

  • Completion of pre-application consultation
  • Feedback Questionnaires Reviewed
  • Submission of Planning Application in December 2016
  • Pre Construction Clearance of Vegetation in January 2017
  • Planning Application determined by SBC in New Year
  • Works commence Spring 2017
  • Approximate construction period of 16 months
  • Draft planning information available in full at www.scarborough.gov.uk/scss
  • If you have queries in the meantime, you can email us at

southcliffscheme@scarborough.gov.uk or call us on 01723 232323 and ask to speak to a member of the Capital Projects Team.