Proposed RAs Option for All- Island Harmonised Transmission Loss - - PowerPoint PPT Presentation

proposed ras option for all island harmonised
SMART_READER_LITE
LIVE PREVIEW

Proposed RAs Option for All- Island Harmonised Transmission Loss - - PowerPoint PPT Presentation

Proposed RAs Option for All- Island Harmonised Transmission Loss Adjustment Factors (TLAFs) System Operator Presentations 1 . Current M ethodology Pros & Cons 2. Responses to Preferred Options Paper 3. Studies into ULF and Impact on


slide-1
SLIDE 1

Proposed RAs Option for All- Island Harmonised Transmission Loss Adjustment Factors (TLAFs)

slide-2
SLIDE 2
  • 1. Current M ethodology – Pros & Cons
  • 2. Responses to Preferred Options Paper
  • 3. Studies into ULF and Impact on Constraints

System Operator Presentations

slide-3
SLIDE 3
  • 1. Current TLAF M ethodology –

Pros & Cons

(Tim Hurley)

slide-4
SLIDE 4

Outline of Presentation

  • Current M ethod – M ilestones
  • Current M ethod – Positive Aspects
  • Current M ethod – Common Issues
slide-5
SLIDE 5

Current M ethod - M ilestones

  • In place ROI (2000)
  • SEM High Level Design (2005)
  • Consultation period (2006-2007)
  • In place SEM (2007)
  • Annual consultations
slide-6
SLIDE 6

Current M ethod - Positive Aspects

  • Seeks Efficiency of Dispatch

– Real time TLAFs most efficient

  • Aims to be Cost Reflective

– Allocates, relative to location, more/ less losses

slide-7
SLIDE 7

Current M ethod - Common Issues

  • Volatility
  • Predictability
  • Transparency
  • Ex ante (6 mths to 18 mths)
  • Compatibility with large scale intermittent

generation

  • Based on current SEM /system design
  • Iterative dispatch
slide-8
SLIDE 8
  • 2. Responses to Preferred

Options Paper

(Helen M agorrian)

slide-9
SLIDE 9

Introduction

  • Preferred Options Paper - published Nov ‘09
  • Overview of Responses - published Jan ‘10
  • 20 Industry Respondents on 3 outlined

approaches

1. Compression 2. Splitting 3. Purchase of Losses

slide-10
SLIDE 10

Compression

  • Little support for compression methodology –

respondents suggested approach would result in : – Cross subsidisation – Increased regulatory risk – Inefficient dispatch – Diluted locational signal

slide-11
SLIDE 11

Compression

  • Generators beside large demand centres with TLAF

>0.98 were particularly anti compression

  • Generators with TLAF <0.98 were broadly supportive
  • f any change from existing approach which could be

demonstrated to provide real value added benefits.

  • Wind Farms were generally pro uniform loss factor
slide-12
SLIDE 12

Splitting

  • Generally respondents expressed interest in this

approach but requested greater detail on how this would be implemented

  • Concerns around the impact such changes would

have on key mechanisms such as constraints, error supply unit, SM P etc.

  • Some respondents suggested that the proposal was

not consistent with the principles of SEM

slide-13
SLIDE 13

Purchase of Losses

  • Generally respondents were in favour of this option

& suggested the focus should be on moving to this as an enduring solution rather than having a 3 step strategy of:

1. Compression – Short T erm Solution 2. Splitting – M edium T erm Solution 3. Purchase of losses – Long T erm Solution

  • Respondents felt the timeline for implementation

was too long

slide-14
SLIDE 14

Summary

  • SOs provided responses to RAs
  • Relatively little support for Compression as a Short

Term Option

  • RAs published ‘Proposed Decision’ on 18th June 2010

that losses be treated on a Uniform Basis

slide-15
SLIDE 15
  • 3. Studies into Calculation of

Uniform Loss Factor and Impact

  • n Constraints Costs

(Louise Carolan)

slide-16
SLIDE 16

Presentation Outline

Following on from ‘Proposed Decision’ paper, RAs requested that the SOs examine:

  • Average System Losses

SOs ran a number of Studies to Investigate Forecast System Losses for 2010/ 11

  • Impact of a ULF on Constraints Costs

SOs examined the impacts on the Constraints Costs when a ULF was used in place of a TLAF

slide-17
SLIDE 17

Studies into Average System Losses

slide-18
SLIDE 18

Studies into Average System Losses

  • 1. PSSE Losses LookUp Table
  • 2. Plexos Generation Forecast run through PSSE

AC Load Flow

Load Loss Factor M ethodology used for Validation

slide-19
SLIDE 19
  • 1. PSSE Losses Look-up Table
  • No. of PSSE Study Cases at different demand

levels – look up table

  • Forecast demand estimates generation for

study period

  • Losses related to generation levels
slide-20
SLIDE 20
  • 2. Plexos Forecast Generation & AC Load Flow
  • Constraints Forecast M odel run through

Plexos

– Forecast of generation for the year (8,760

cases)

  • 8,760 Cases run through AC Load Flow
  • Output Losses for every Period
  • Average Losses as % of Sent Out Units
slide-21
SLIDE 21

Load Loss Factor - Validation

  • Load Loss Factor (LLF) calculated based on

total load and peak load:

  • LLF = (LF)k+(LF)2(1-k)
  • LLF used to validate calculated approximate

annual losses

slide-22
SLIDE 22

Results

  • Studies yielding approximately 2.0% Average

System Losses

slide-23
SLIDE 23

Considerations

  • Offset between PSSE Losses and Actual Losses

– voltage profiles

  • Assumptions for the Constraints Forecast

M odel based on a Locational Loss Factor M ethodology

slide-24
SLIDE 24

Studies into Effects of ULF on Constraints Forecast

slide-25
SLIDE 25

Constraints Costs

  • No systematic reason for impact on Constraints

Forecast

  • Constraints Forecast may increase or decrease

depending on circumstances at a point in time

  • Impact on Constraints Forecast inherently

bounded by the Loss Factor Differentials

slide-26
SLIDE 26

Study

  • Using SO models used for the Constraints Forecast

Analysis, replaced TLAF with Uniform Loss Factor

  • SO model assumptions based on a Locational Loss

Factor M ethodology

  • No increase in demand modelled
slide-27
SLIDE 27

Results

  • Indicative Studies for 2010/ 2011

– Forecasting small increase in Constraints Costs – No systematic reason for increase

slide-28
SLIDE 28

Thank Y

  • u