slide-1
SLIDE 1

PROPERTY OWNERS MEETING SEWER SERVICE CHARGE RATES

Edgewood Sewer Maintenance District Kensington Square Sewer Maintenance District Oak Knoll Sewer Maintenance District

Clifford Elementary School 225 Clifford Avenue Redwood City, CA May 21, 2007 7:00 P.M.

County of San Mateo Department of Public Works

slide-2
SLIDE 2

OVERVI EW OF TONI GHT’S MEETI NG:

  • District Information
  • District Funding
  • Elements of the Sewer Service Charge Rates
  • In District Costs
  • Out of District Costs
  • Minimum Fund Reserve Targets
  • Proposed Rates
  • Rate Setting Timeline
  • Questions and Comments
slide-3
SLIDE 3

FOSMD: Pipes ~ 81 Miles ERU – 12,597 ELHSMD:

Pipes ~ 29 Miles ERU – 1,657

CSCSD:

Pipes ~ 19 Miles ERU – 1,501

BHSMD:

Pipes ~ 7 Miles ERU - 426

DCSD:

Pipes ~ 4 Miles ERU - 293

HI SMD:

Pipes ~ 1 Mile ERU - 234

OKSMD:

Pipes ~ 2 Miles ERU - 118

KSSMD:

Pipes ~ 0.8 Miles ERU - 74

SHCSD:

Pipes ~ 2 Miles ERU - 58

ESMD:

Pipes ~ 0.3 Miles ERU - 18

slide-4
SLIDE 4

EDGEWOOD SEWER MAI NTENANCE DI STRI CT – BOUNDARY MAP:

CM: Insert district map. CM: Insert district map.

District Boundary

Sewage Flows Through City of Redwood City To South Bayside System Authority (SBSA) Treatment Plant in Redwood Shores For Treatment

Redwood Shores San Carlos Redwood City Foster City Belmont

slide-5
SLIDE 5

KENSI NGTON SQUARE SMD – BOUNDARY MAP:

Sewage Flows Through City of Redwood City To South Bayside System Authority (SBSA) Treatment Plant in Redwood Shores For Treatment

District Boundary Redwood Shores San Carlos Redwood City Belmont

slide-6
SLIDE 6

OAK KNOLL SEWER MAI NTENANCE DI STRI CT – BOUNDARY MAP:

Sewage Flows Through City of Redwood City To South Bayside System Authority (SBSA) Treatment Plant in Redwood Shores For Treatment

District Boundary Redwood Shores San Carlos Redwood City District Boundary District Boundary Belmont

slide-7
SLIDE 7

SEWER/ SANI TATI ON DI STRI CTS I N COUNTY GOVERNMENT:

EACH DISTRICT IS AN INDEPENDENT ENTITY WITH ITS OWN SEPARATE BUDGET

  • Each District’s Governing Board is the Board of Supervisors
  • The District receives Sewer Service Charges and limited

property taxes within the District boundaries to fund sewer service

  • The Sewer Service Charges are a Fee For Service, Not a Tax
  • The District collects Sewer Service Charges on the Tax Bill

because it is least costly way to collect the fee

slide-8
SLIDE 8

WHERE DOES MY PROPERTY TAX MONEY GO?

EDGEWOOD SEWER MAINTENANCE DISTRICT:

  • No Property Tax Revenue Allocation
  • District Formed After Proposition 13
slide-9
SLIDE 9

WHERE DOES MY PROPERTY TAX MONEY GO?

KSSMD Sample Property Tax Allocation (TRA 073-032)

Kensington Sq SMD 5.79% Mid Pen ROSD 1.95% General County Tax 25.14% Emerald Lake Lighting 1.70% SU High School 16.57% Air Quality Mngmnt 0.22% Sequoia Hospital Dist 1.55% County Education Tax 3.74% Mosquito Abatement 0.20% County Harbor District 0.37% SM Junior College 7.19% County Fire Protection 6.81% RWC Elem School 25.07% Free Library 3.67%

slide-10
SLIDE 10

WHERE DOES MY PROPERTY TAX MONEY GO?

OKSMD Sample Property Tax Allocation (TRA 073-008)

OKSMD 1.51% Mid Penn ROSD 2.04% General County Tax 26.29% Emerald Lake Lighting 1.78% SU High School 17.32% Air Quality Mngmnt 0.23% Sequoia Hospital Dist 1.62% County Education Tax 3.91% Mosquito Abatement 0.21% County Harbor District 0.39% SM Junior College 7.52% County Fire Protection 7.12% RWC Elem School 26.22% Free Library 3.83%

slide-11
SLIDE 11

DI STRI CT SPECI FI C STATI STI CS:

District Age (Years) * Number of Connections ** Equivalent Residential Units ** Downstream Transport Agency Treatment Facility Edgewood SMD 1 18 18 City of Redwood City South Bayside System Authority (SBSA) Kensington Square SMD 51 74 74 Oak Knoll SMD 50 114 118

District Miles of Pipe Percentage of Pipe in Easements Percentage of Pipe in Streets Edgewood SMD 0.3 28.75% 71.25% Kensington Square SMD 0.8 0.00% 100.00% Oak Knoll SMD 1.5 33.43% 66.57%

*Age based on District formation date ** Based on 2006-07 SSC Report

slide-12
SLIDE 12

ORGANI ZATI ONAL STRUCTURE OF DI STRI CTS:

BURLINGAME HILLS SMD CRYSTAL SPRINGS CSD DEVONSHIRE CSD EDGEWOOD SMD EMERALD LAKE HEIGHTS SMD FAIR OAKS SMD HARBOR INDUSTRIAL SMD KENSINGTON SQUARE SMD OAK KNOLL SMD SCENIC HEIGHTS CSD UTILITIES-FLOOD CONTROL-WATERSHED PROTECTION SECTION Ann M. Stillman, Principal Civil Engineer DEPARTMENT OF PUBLIC WORKS James C. Porter, Director COUNTY MANAGER'S OFFICE SAN MATEO COUNTY BOARD OF SUPERVISORS

slide-13
SLIDE 13

HOW DOES A SEWER SYSTEM WORK?

Image Source: Pixel-Gym

Each District Relies On Downstream Agencies To Transport The District Collected Sewage To The Treatment Plant

slide-14
SLIDE 14

DI STRI CT EXPENSES:

IN DISTRICT COSTS:

  • Operation and Maintenance
  • Regulation Compliance
  • District Capital Improvement Projects

OUT OF DISTRICT COSTS:

  • Sewage Transport and Treatment
  • Downstream Agency Capital Improvement Projects
slide-15
SLIDE 15

DI STRI CT EXPENSES:

Edgewood Sewer Maintenance District FY 07-08 Proposed Balanced Budget Rate of $900

O&M 29.9% Treatment 42.8% Fund Reserve * 26.1% Regulations 1.2%

* Contributes to Fund Reserve

In District

slide-16
SLIDE 16

DI STRI CT EXPENSES:

Kensington Square Sewer Maintenance District FY 07-08 Expenditure Per ERU of $929

(Proposed Balanced Budget Rate of $750)

O&M 9.5% Treatment 36.8% District CIP 30.9% Regulations 3.6% Fund Reserve * 0.4% Other Revenue (Tax Revenue & Interest) 18.8%

* Utilizes Fund Reserve

In District

slide-17
SLIDE 17

DI STRI CT EXPENSES:

Oak Knoll Sewer Maintenance District FY 07-08 Expenditure Per ERU of $705 (Proposed Balanced Budget Rate of $650)

O&M 14.1% Treatment 53.6% District CIP 15.4% Regulations 8.5% Fund Reserve * 0.3% Other Revenue (Tax Revenue & Interest) 8.1%

* Contributes to Fund Reserve

In District

slide-18
SLIDE 18

DI STRI CT EXPENDI TURE COMPARI SON

Fiscal Year 2005-06 and 2007-08 Expenditure Comparison

$- $10,000 $20,000 $30,000 $40,000 $50,000 $60,000 $70,000 $80,000 $90,000 Edgewood 2007-08 Kensington 2005-06 Kensington 2007-08 Oak Knoll 2005-06 Oak Knoll 2007-08 District / Fiscal Year Expenditure ($) District CIP Treatment Regulations O&M

slide-19
SLIDE 19
  • ROUTINE AND PREVENTATIVE MAINTENANCE
  • REPAIR OF DAMAGED PIPES
  • EMERGENCY RESPONSE
  • CUSTOMER ASISTANCE
  • DISTRICT ADMINISTRATION

OPERATI ON AND MAI NTENANCE:

slide-20
SLIDE 20

EMERGENCY RESPONSE 24 HOURS A DAY, 7 DAYS A WEEK

OPERATI ON AND MAI NTENANCE:

Image Source: City of Irving, Texas

slide-21
SLIDE 21

ANTICIPATED EXPENDITURES FOR FUTURE OPERATION & MAINTENANCE BASED ON 5-YEAR HISTORICAL COSTS

  • 4% annual increase for inflation
  • 3% O&M contingency to account for unanticipated expenses

OPERATI ON AND MAI NTENANCE:

slide-22
SLIDE 22

THE DISTRICTS ARE REGULATED BY:

REGULATI ON COMPLI ANCE:

The Regional Water Quality Control Board The State Water Resources Control Board The State Porter-Cologne Act The Federal Clean Water Act

slide-23
SLIDE 23

GOAL TO ELIMINATE SANITARY SEWER OVERFLOWS (SSO)

What is a SSO?

  • Raw Sewage Leaves the Pipe and Flows on the Ground Surface
  • Sewage, if Not Captured, Can Reach Storm Drains, Creeks, Lakes, the

Bay, and Ocean

REGULATI ON COMPLI ANCE:

SSO from Manhole SSO from Manhole Near Creek SSO from Cleanout

slide-24
SLIDE 24

WHAT CAUSES A SSO? Blockages, breaks, and Infiltration & Inflow in the sewer pipe will cause a SSO.

REGULATI ON COMPLI ANCE:

slide-25
SLIDE 25

WHY IS IT IMPORTANT TO ELIMINATE SSOs? UNTREATED SEWAGE IS

A THREAT TO PUBLIC HEALTH, ANIMALS, AND THE ENVIRONMENT.

REGULATI ON COMPLI ANCE:

slide-26
SLIDE 26

WHY I S I T I MPORTANT TO ELI MI NATE SSOs? AGENCIES HAVE

BEEN LEVIED STIFF PENALTIES OR PAID LARGE SETTLEMENTS IN LAWSUITS FOR SSOs.

REGULATI ON COMPLI ANCE:

Notice of Violation & Intent Notice of Violation & Intent to File Suit (60 to File Suit (60-

  • Day Notice)

Day Notice)

Plaintiffs Baykeeper, West County Toxic Coalition Lawyers for Clean Water Environmental Advocates vs. Defendants West County Wastewater District (WCWD) City of Richmond Veolia Water NA Downey Brand LLP

Settlement Agreement Fees Settlement Agreement Fees

WCWD/Richmond/Veolia WCWD/Richmond/Veolia

  • WCA NPDES Effluent Limit Violations
  • SEP Rose Foundation $80,000
  • Attorneys Fees (Plaintiff) $57,000
  • Collection System Settlement Fees
  • Attorneys Fees (Plaintiff) - $538,000
  • Oversight Cost (Plaintiff) - $100,000
  • Attorneys Fees (Defendants) - $300,000
  • Staff Resources/In-house Counsel - $50,000
  • Settlement Agreement was reached in 15 months

Collection System Settlement Agreement Collection System Settlement Agreement

WCWD WCWD

  • Collection System Capital Improvement Program
  • Commit $5M over 10 years
  • System Evaluation and Capacity Assurance Plan (SECAP)
  • Revise within 18 months
  • Update 2015
  • CCTV-Sewer Condition Grading
  • Gravity Sewer Line Cleaning Schedule
  • <12” once every 4 years
  • >12” once every 10 years
  • Design for 5 year-24/hr Storm Event
  • Continue FOG Program - Increase FSE Inspections
  • Attain SSO Reduction Goals

The San Francisco Bay Regional Water Quality Control Board imposed a $516,000 fine to the City of South San Francisco in 2006 for sewer overflows and a $626,000 administrative civil liability to the City and County of San Francisco in an impending order.

Fines!!!

slide-27
SLIDE 27

REGULATI ON COMPLI ANCE: What are the Districts required to do?

Develop Sewer System Management Plans (SSMP) Report all SSOs

slide-28
SLIDE 28

REGULATI ON COMPLI ANCE: Sewer System Management Plan (SSMP) Goals:

Maintaining or improving the condition of collection systems to provide reliable service in the future Cost-effectively minimizing infiltration/inflow (I&I) and providing adequate sewer capacity for wet weather flows Minimizing the number and impact of SSOs

slide-29
SLIDE 29

REGULATI ON COMPLI ANCE:

What are the elements of a SSMP and when do they need to be completed by?

Aug 31 2006

Legal authority for permitting flows into the system, I&I control and enforcement of proper design, installation, testing standards and inspection requirements for new and rehabilitated sewers Measures and activities to maintain the wastewater collection system Design and construction standards Collection system management goals Organization of personnel, chain of command, and communications Overflow emergency response plan Fat, Oils and Grease (FOG) control program

Aug 31 2007

Capacity Management Monitoring plan for SSMP program effectiveness Periodic SSMP Audits, periodic SSMP updates, and implementation of program Communication Program

Aug 31 2008

slide-30
SLIDE 30

REGULATI ON COMPLI ANCE:

What SSMP Elements were factored into the rates?

  • Condition Assessment through Closed Circuit Television Inspection (CCTV)
  • f pipes
  • 1/6 of system per year
  • Spot Repairs
  • Repairing sections of pipe based on CCTV findings
  • Repair 2% of televised pipe system per year
  • Equipment Upgrades
  • Replacing, upgrading, or purchasing equipment for effective

maintenance of sewer system

  • Costs associated with required reporting and SSMP development

Regulatory Requirements and Reporting

slide-31
SLIDE 31

DI STRI CT CAPI TAL I MPROVEMENT PROJECTS (CI P):

High priority CIPs identified in Sewer Master Plans completed in 1999 and 2000

  • Improvements recommended based on
  • Lack of capacity in pipe – Priority 1
  • Excessive maintenance costs – Priority 2
  • Damaged pipes – Priority 3
slide-32
SLIDE 32

DI STRI CT CAPI TAL I MPROVEMENT PROJECTS (CI P):

What is recommended in my District?

Kensington Square SMD CIP Identified in Sewer Master Plan Priority

  • No. of

Projects Identified Length of Pipe to be Upgraded Estimated Construction Cost Priority 1 – Capacity

  • Priority 2 –

Maintenance

  • Priority 3 –

Structural 1 ~ 1,350’ $250,355 Totals 1 1,350 ft. * $250,355 **

* CIP Lengths Identified Represent Approximately 33.2% of District’s Total Length of Sewer Mains (4,059 feet).

** Estimated cost includes design, administration, and inspection

slide-33
SLIDE 33

DI STRI CT CAPI TAL I MPROVEMENT PROJECTS (CI P):

What projects still need to be completed?

* Remaining CIP Lengths Represent Approximately 33.2% of District’s Total Length of Sewer Mains (4,059 feet).

**Estimated cost includes design, administration, and inspection Remaining Kensington Square SMD CIP Priority Number of Projects Length of Pipe to be Upgraded Estimated Construction Cost Priority 1 – Capacity

  • Priority 2 –

Maintenance

  • Priority 3 – Structural

1 ~ 1,350’ $250,355 Totals 1 1,350 ft. * $250,355 **

slide-34
SLIDE 34

DI STRI CT CAPI TAL I MPROVEMENT PROJECTS (CI P):

What is recommended in my District?

Oak Knoll SMD CIP Identified in Sewer Master Plan Priority

  • No. of

Projects Identified Length of Pipe to be Upgraded Estimated Construction Cost Priority 1 – Capacity

  • Priority 2 –

Maintenance

  • Priority 3 –

Structural 2 ~ 810’ $133,425 Totals 2 810 ft. * $133,425 **

* CIP Lengths Identified Represent Approximately 10% of District’s Total Length of Sewer Mains (8,107 feet).

** Estimated cost includes design, administration, and inspection

slide-35
SLIDE 35

DI STRI CT CAPI TAL I MPROVEMENT PROJECTS (CI P):

What projects still need to be completed?

* Remaining CIP Lengths Represent Approximately 10% of District’s Total Length of Sewer Mains (8,107 feet).

**Estimated cost includes design, administration, and inspection Remaining Oak Knoll SMD CIP Priority Number of Projects Length of Pipe to be Upgraded Estimated Construction Cost Priority 1 – Capacity

  • Priority 2 –

Maintenance

  • Priority 3 – Structural

2 ~ 810’ $133,425 Totals 2 810 ft. * $133,425 **

slide-36
SLIDE 36

DI STRI CT CAPI TAL I MPROVEMENT PROJECTS (CI P):

How were the CIP costs factored into the rates?

Costs for CIPs were spread over 10 years 5% contingency applied for capital work Districts pipes are approx. 50 years old

slide-37
SLIDE 37

OUT OF DI STRI CT COSTS:

  • Sewage Transport
  • Treatment and Disposal
  • Downstream Agency Capital Improvement

Projects

slide-38
SLIDE 38

SEWAGE TRANSPORT, TREATMENT, AND DISPOSAL:

  • Each District has an Agreement with the

downstream agency for sewage transport, treatment, and disposal

  • ESMD, KSSMD, and OKSMD have agreements

with the City of Redwood City

slide-39
SLIDE 39

SEWAGE TRANSPORT, TREATMENT, AND DISPOSAL:

  • The District will pay the City of Redwood City:

What do the Agreements specify?

  • for transporting, treating, and disposing of

sewage from the Districts

  • an equivalent amount to the Sewer Service

Charge rate established by the City for the same type of structure in the City

slide-40
SLIDE 40

SEWAGE TRANSPORT, TREATMENT, AND DISPOSAL:

Payments to the City include reimbursing the City for the use of their sewer system and the operation and maintenance costs associated with the usage

  • The 2006-07 SSC average rate in the City is $396
  • The City increased their rates by 26% this year

(2006-07)

  • The City is planning to increase their rates for the

2007-08 fiscal year to $428

slide-41
SLIDE 41

SEWAGE TRANSPORT, TREATMENT, AND DISPOSAL:

  • Capital Improvement Projects within the City
  • Capital Improvement Projects at the South Bayside

System Authority (SBSA)

What affects the rates the District pays the City?

  • SBSA is planning capital improvements worth multi-

million dollars

  • The capital improvements will replace equipment

which have reached the end of their useful lives

  • SBSA will be charging the member agencies

(Redwood City, San Carlos, Belmont, and West Bay Sanitary District) for the improvements

slide-42
SLIDE 42

SEWAGE TREATMENT AND DISPOSAL PROCESS

SERVI CES PROVI DED BY DI STRI CTS:

Image Source: SBSA

slide-43
SLIDE 43

SEWAGE TRANSPORT, TREATMENT, AND DISPOSAL:

A portion of the SSC rates were calculated to pay for transport, treatment, and disposal and anticipated increases in treatment costs and capital improvements

  • Based on information from downstream

agencies or assumed increases based on historical data

  • 3% contingency applied
slide-44
SLIDE 44

MINIMUM FUND RESERVE TARGETS:

50% of Operations and Maintenance Costs (6 mo.) and 3% of the replacement value (Best Management Practices)

  • r $100,000 for small districts

District Replacement Value * Minimum Fund Reserve Target Edgewood SMD $475,000 $100,000 Kensington Square SMD $470,100 $100,000 Oak Knoll SMD $881,300 $100,000

*Replacement value includes construction costs only

slide-45
SLIDE 45

PROPOSED RATES:

  • SSC Rates determined to meet anticipated

expenditures immediately

Balanced Budget Phased Increase

  • SSC Rates determined to steadily increase to meet

future expenditures

  • Phased Increase may rely on Fund Reserve to meet

future expenditures

slide-46
SLIDE 46

PROPOSED RATES:

Sewer Service Charge Rate ($/Year Per Residential Unit) 2006-07 Proposed Rates 2007-08 2008-09 2009-10 2010-11 2011-12 E SMD Balanced Budget

$655 $900 $950 $1,000 $1,050 $1,100

Phased Increase

$750 $800 $850 $900 $950

KS SMD Balanced Budget

$373 $750 $850 $900 $950 $1,000

Phased Increase

$500 $750 $850 $900 $975

OK SMD Balanced Budget

$412 $650 $700 $750 $800 $900

Phased Increase

$500 $600 $700 $800 $900

slide-47
SLIDE 47

SSC vs FUND RESERVE:

Edgewood Sewer Maintenance District Sewer Service Charge Options and Fund Reserve

$27,205 $13,705

$3,000 $23,000 $43,000 $63,000 $83,000 $103,000 $123,000

2007-08 2008-09 2009-10 2010-11 2011-12 Fiscal Year Fund Reserve ($) $700 $750 $800 $850 $900 $950 $1,000 $1,050 $1,100 $1,150 Sewer Service Charge Rate ($) Balanced SSC Phased SSC Fund Reserve (Balanced) Fund Reserved (Phased) Min Target Fund Reserve

slide-48
SLIDE 48

Kensington Square Sewer Maintenance District Sewer Service Charge Options and Fund Reserve

$151,522 $113,028 $80,000 $90,000 $100,000 $110,000 $120,000 $130,000 $140,000 $150,000 $160,000 2007-08 2008-09 2009-10 2010-11 2011-12 Fiscal Year Fund Reserve ($) $400 $500 $600 $700 $800 $900 $1,000 $1,100 Sewer Service Charge Rate ($) Balanced SSC Phased SSC Fund Reserve (Balanced) Fund Reserved (Phased) Min Target Fund Reserve

SSC vs FUND RESERVE:

slide-49
SLIDE 49

Oak Knoll Sewer Maintenance District Sewer Service Charge Options and Fund Reserve

$125,349 $86,274 $80,000 $90,000 $100,000 $110,000 $120,000 $130,000 2007-08 2008-09 2009-10 2010-11 2011-12 Fiscal Year Fund Reserve ($) $400 $500 $600 $700 $800 $900 $1,000 Sewer Service Charge Rate ($) Balanced SSC Phased SSC Fund Reserve (Balanced) Fund Reserved (Phased) Min Target Fund Reserve

SSC vs FUND RESERVE:

slide-50
SLIDE 50

RATE SETTING PROCESS:

Key Dates Actions May 2, 2007 Sent all property owners information about sewer systems and what their sewer service charge pays for. Early/Mid May Sent all property owners information about proposed rates and timing

  • f meetings with property owners.

May 15 District staff provided Board with status update on proposed sewer service charge rates and received approval of proposed process and elements of the rates. Mid/End of May Meetings with property owners of each district to discuss the proposed rates, factors involved in establishing rates, and seek property owner input. June 5 Introduce Ordinance with proposed sewer service rates for 2007-08 through 2011-2012 fiscal years and set Public Hearing for July 24 at 9:15am. June 8 Send Prop 218 notice (45 days prior to public hearing) to property

  • wners with proposed rates.

July 24 Hold public hearing, adopt Ordinance setting rates, and adopt 2007-08 Sewer Service Charges Report based on the adopted rates.

slide-51
SLIDE 51

QUESTIONS & INPUT

District Services Rate Development Rate Adoption Process and Schedule Others

slide-52
SLIDE 52

CONTACT INFORMATION

Please e-mail your comments and questions to: sewers@co.sanmateo.ca.us Information is available on our website at: http://www.co.sanmateo.ca.us/sewers