Project Management Page 1 of 12 21 April 2004 rev 1.3 Why Plan? ! - - PowerPoint PPT Presentation

project management
SMART_READER_LITE
LIVE PREVIEW

Project Management Page 1 of 12 21 April 2004 rev 1.3 Why Plan? ! - - PowerPoint PPT Presentation

Project Management Page 1 of 12 21 April 2004 rev 1.3 Why Plan? ! Eliminate or reduce uncertainty ! Improve efficiency of the operation ! Obtain a better understanding of the objectives ! Provide a basis for monitoring and controlling work !


slide-1
SLIDE 1

rev 1.3 Page 1 of 12 21 April 2004

Project Management

slide-2
SLIDE 2

rev 1.3 Page 2 of 12 21 April 2004

Why Plan?

! Eliminate or reduce uncertainty ! Improve efficiency of the operation ! Obtain a better understanding of the objectives ! Provide a basis for monitoring and controlling work ! Focus team in the same direction

A project without a plan is like a boat without a rudder. It will go, but where?

slide-3
SLIDE 3

rev 1.3 Page 3 of 12 21 April 2004

Time, Objectives and Resources

Resources + Time = Objectives

Resources Time Objectives

slide-4
SLIDE 4

rev 1.3 Page 4 of 12 21 April 2004

Cultural Planning Styles

French Japanese American

slide-5
SLIDE 5

rev 1.3 Page 5 of 12 21 April 2004

Statement of Work (SOW)

! Narrative description of the work – Specifications – Objectives – Scope – Funding limits ! Causes for misinterpretations – No structure - tasks, specifications, approvals, and special instructions mixed together – Imprecise language (nearly, optimum, and approximately) – No pattern, structure or chronological order – Wide variation is size of tasks – Wide variation in level of detail – No third party review

slide-6
SLIDE 6

rev 1.3 Page 6 of 12 21 April 2004

Work Breakdown Structure (WBS)

! Breakdown of the total project into smaller task – Level 1: Total program – Level 2: Project – Level 3: Task – Level 4: Sub task – Level 5: Work Package – Level 6: Level of effort ! WBS provides the basis for: – Responsibility matrix – Network scheduling – Costing – Risk analysis – Organizational structure – Coordination of objectives – Control

slide-7
SLIDE 7

rev 1.3 Page 7 of 12 21 April 2004

Work Breakdown Structure

slide-8
SLIDE 8

rev 1.3 Page 8 of 12 21 April 2004

Network (PERT Chart) & Slack Time

4 3 5 6 3 7 Slack = 4 Slack = 1

slide-9
SLIDE 9

rev 1.3 Page 9 of 12 21 April 2004

PERT & Critical Path

  • 1. Create Work Breakdown Structure
  • 2. Sequence WBS activities (arrow chart)
  • 3. Review arrow chart with line managers (experts)
  • 4. Estimate activity duration by line managers

(experts)

  • 5. Look at/adjust Critical Path
  • 6. Place calendar dates on each event and insure

resources are available

slide-10
SLIDE 10

rev 1.3 Page 10 of 12 21 April 2004

Management Cost and Control System

! Am I on schedule? ! Am I on budget? ! Am I meeting the project objectives? ! How do I get back on track? ! How do I get the information to evaluate the above

items?

! How do I communicate the project's status to the

rest of the world?

slide-11
SLIDE 11

rev 1.3 Page 11 of 12 21 April 2004

Getting the Information

! Team is the key, the person doing the work is in the

best position to know how their part of the project is going.

! Education about the Management Cost and Control

System for the whole team

! MBWA - Management by working around - phone

calls, e-mail, video conferencing, face to face, time card input, status reports

! Trade off between status reporting and doing the

work

slide-12
SLIDE 12

rev 1.3 Page 12 of 12 21 April 2004

Am I on schedule and on budget?

! Gantt Charts ! Network Charts ! Plan vs. Actual vs. Revised Plan ! Identify why things went faster or slower than

planned

! You can get lost in the tracking system

slide-13
SLIDE 13

rev 1.3 Page 13 of 12 21 April 2004

Crash Times & Mythical Man Month

by Frederick P. Brooks, Jr.

1 2 3 4 5 6 7 8 9 1 2 4 6 8 1 0 1 2 14 1 6 1 8 2 0

People Months Perfectly Partionable Tasks

1 2 3 4 5 6 7 8 9 1 1 3 5 7 9 1 1 1 3 1 5 1 7 1 9

People Months Unpartionable Tasks Tasks with complex interrelationships

Months

5 1 1 5 2 2 5 1 2 3 4 5 6 7 8 9 1 1 1 1 2 1 3

People Months

slide-14
SLIDE 14

rev 1.3 Page 14 of 12 21 April 2004

Failures of plans

! Corporate goals not understood at lower

  • rganizational levels

! Plans encompass too much in too little time ! Poor financial estimates ! Plans based upon insufficient data ! No planning methodology ! Planning performed by a planning group ! Management assumes that all activities will be

completed on schedule

slide-15
SLIDE 15

rev 1.3 Page 15 of 12 21 April 2004

Stopping a project

! Final achievement of the objectives ! Poor initial planning and market prognosis ! A better alternative is found ! A change in the company strategy ! Allocated time is succeeded ! Budgeted costs are exceeded ! Key people leave the organization ! Personal whims of management ! Problem too complex for the resources available

slide-16
SLIDE 16

rev 1.3 Page 16 of 12 21 April 2004

Task Specific Leadership Style

! Matrix Dimensions – Task Behavior – Relationship Behavior ! Other's Readiness – Ability – Motivation ! Leadership Style – Directing – Guiding, Coaching – Supporting, Participating – Delegating

slide-17
SLIDE 17

rev 1.3 Page 17 of 12 21 April 2004

Team development stages

! Forming

" Initial awareness - why are we here? " Will I be accepted? " Leadership: Dependence

! Storming

" Sorting-out process - bidding for control and power " Will I be respected? " Leadership: Independence

! Norming

" Self-organization " How can I help the group? " Leadership: Interdependence

! Performing

" Maturity and mutual acceptance " How can we do better? " Leadership: Interdependence

slide-18
SLIDE 18

rev 1.3 Page 18 of 12 21 April 2004

Sources of Conflict

Perceived divergence of interests

Perceived Benefit to Other P O Benefit to Self *A *B *C *D P = Party's Aspirations O = Other's Aspirations

slide-19
SLIDE 19

rev 1.3 Page 19 of 12 21 April 2004

Conflict Handling Modes

! Inaction (Withdrawal) – Retreating from an actual or potential disagreement. Termination of efforts to resolve the conflict. ! Yielding (Smoothing) – Lowering one's aspirations. ! Contending (Forcing) – Any effort to resolve a conflict on one's own terms without regard to the

  • ther party's interests. Making threats, imposing penalties, preemptive

actions. ! Problem Solving (Confrontation, Compromising) – Any effort to identify the issues dividing the parties and to develop and move toward a solution that appeals to both sides.

slide-20
SLIDE 20

rev 1.3 Page 20 of 12 21 April 2004

Strategic Choices - Handling Conflict

Concern about

  • ther's outcomes

Concern about own outcomes Contending Yielding Inaction Problem Solving