Project Introduction Tuesday 28 January 2020 Aims of todays meeting - - PowerPoint PPT Presentation

project introduction
SMART_READER_LITE
LIVE PREVIEW

Project Introduction Tuesday 28 January 2020 Aims of todays meeting - - PowerPoint PPT Presentation

Project Introduction Tuesday 28 January 2020 Aims of todays meeting Meet you and introduce the Awel y Mr team Introduce the project location, scale, timeline Opportunity to have your say Key contacts and future points of


slide-1
SLIDE 1

Project Introduction

Tuesday 28 January 2020

slide-2
SLIDE 2

Aims of today’s meeting

  • Meet you and introduce the Awel y Môr team
  • Introduce the project – location, scale, timeline
  • Opportunity to have your say
  • Key contacts and future points of communication
  • Next steps
slide-3
SLIDE 3

innogy Renewables UK Ltd

  • Long presence in Wales – offshore, onshore & hydro
  • Produce 1/3 of Wales’ renewable electricity (550k homes)
  • 130+ permanent employees across 4 offices in Wales
  • Operate 3 offshore wind farms off North Wales coast:
  • Gwynt y Môr, 576MW
  • Rhyl Flats, 90MW
  • North Hoyle, 60MW
  • + extension proposal: Awel y Môr
  • Operate 2 (soon to be 3) onshore wind farms
  • Six hydro sites – Dolgarrog over 100 years old!
  • Significant contribution to Welsh Government’s targets:
  • 70% electricity from Welsh renewable sources by 2030
  • “Net-zero” by 2050

Largest renewable energy operator in Wales

slide-4
SLIDE 4

Awel y Môr Offshore Wind Farm

Project Overview

slide-5
SLIDE 5

Project key messages

  • The Crown Estate offered an Agreement for Lease (AfL) for extension of

Gwynt y Môr Offshore Wind Farm in October 2019. One of seven UK extension sites.

  • ‘Sister’ project to Gwynt y Môr – called Awel y Môr Offshore Wind Farm

(“breeze of the sea”). Great opportunity to help Wales’ net zero targets.

  • Innogy is proud to be leading the development on behalf of its partners
  • The project is in its very early stages. Exact size and capacity still to be
  • determined. Initial consenting work is just beginning with early stakeholder

and community engagement programme to help determine the project details – a process due to take up to three years.

  • The project is a Nationally Significant Infrastructure Project (NSIP) and

therefore requires a Development Consent Order (DCO). Being in Welsh waters, it will also require a separate Marine Licence.

slide-6
SLIDE 6

Site characteristics

Location:

  • 11km north of Llandudno and 10km off the Welsh coast in the Irish Sea
  • West of existing Gwynt y Môr Wind Farm

Wind Turbine Generators (WTGs):

  • Unconfirmed but, at time of

construction, 12-22MW turbines possible Foundation types:

  • Monopile/multi-leg

Extension area:

  • 106km²

Grid connection point:

  • Bodelwyddan (still TBC)

Shareholders / project owners:

  • Discussions still ongoing
slide-7
SLIDE 7

High level project timeline

slide-8
SLIDE 8

Planning Inspectorate: DCO application process

c.2 yrs 28 days c.4 m 6 m 6 m 6 wks

slide-9
SLIDE 9

Planned Stakeholder Engagement

Offshore, onshore & combined topic engagement

Local community & local businesses

slide-10
SLIDE 10

www.awelymor.co.uk

Thank you

slide-11
SLIDE 11

Awel y Môr Project Team

11

Role Contact Email Senior Consents Manager Paul Carter paul.carter@innogy.com Offshore Consents Manager Alex Herbert alex.herbert@innogy.com Onshore Consents Manager Karen Algate karen.algate@innogy.com Stakeholder & Consents Manager Helen Thomas helen.thomas@innogy.com Project Manager Tamsyn Rowe tamsyn.rowe@innogy.com Public Relations Ffion Davies ffion.davies@innogy.com