Private Provider RFP UPDATE February 27, 2017
1
Private Provider RFP UPDATE February 27, 2017 1 Executive Summary - - PowerPoint PPT Presentation
Private Provider RFP UPDATE February 27, 2017 1 Executive Summary Providers submitting proposals: 6 Charter met financial threshold requirements Proposal for six towns Requests additional funding for 3 towns Requires all
1
Providers submitting proposals: 6 Charter – met financial threshold requirements
Comcast – met financial threshold requirements
Charter;
Mid-Hudson – did not meet minimum financial requirements
Crocker – did not meet minimum financial requirements
requires 75% take rate / cover 96% of town at $3000 per subscriber Fiber Connect – did not meet minimum financial requirements
Westfield Gas & Electric
2
3
Municipality Requested Grant Funding MBI Construction Allocation Additional Funding Requested Proposed Coverage % of Total Premises Egremont $660,000 $303,276 96% of 920 Monterey $680,000 $613,150 96% of 874 New Salem $400,000 $547,239 96% of 464 Hancock $480,000 $0 96% of 682 Princeton $910,000 $0 100% of 1,325 Shutesbury $510,000 $0 96% of 845 Total $3,640,000 $1,463,665
4
Municipality Requested Grant Funding MBI Construction Allocation Additional Funding Requested Proposed Coverage % of Total Premises Goshen $450,000 $1,010,000 96% of 585 Montgomery $300,000 $725,000 96% of 360 Princeton $910,000 $640,000 100% of 1,344 ** Shutesbury $510,000 $1,145,000 96% of 845 Total $2,170,000 $3,520,000
*Also provides an offering of 10 Mbps/1 Mbps service for $9.95/month to families with a child eligible for National School Lunch Program. **Based on Comcast’s own data collected from a physical walk-out within the Town.
5
Municipality Requested Grant Funding MBI Construction Allocation Additional Funding Requested Proposed Coverage % of Total Premises Tyringham $260,000 $71,500 ** 97% of 308 Total $260,000 $71,500 **
*Will offer three separate speed packages available to wireless subscribers ranging from 10mb to 24mb download. Prices for wireless packages not specified. **Estimated cost to town for building of 1.4 miles of infrastructure to link Main St. to Goose Pond via fiber optic cabling. Estimate includes installation of 30 -35
6
Municipalities Requested Grant Funding MBI Construction Allocation Additional Funding Requested Proposed Coverage % of Total Premises 38 Towns $18,330,000 $22,869,000 * 70% of 21,201 38 Towns $18,330,000 $51,455,250 ** 96% of 21,201
*Shows projected total additional funding for 38 towns if 50% presubscription threshold is reached with $2K contribution from each subscriber. **Shows projected total additional funding for 38 towns if 75% presubscription threshold is reached with $3K contribution from each subscriber.
financial information shared.
Marlborough, Otis, Tolland, Tyringham)
7
Municipality Requested Grant Funding MBI Construction Allocation Additional Funding Requested Proposed Coverage % of Total Premises Monterey * $680,000 $585,000 98% of 798 Egremont * $660,000 $100,000 98% of 922 Alfrod $270,000 $468,000 96% of 342 Becket $1,290,000 $3,132,000 96% of 1,823 New Marlborough $920,000 $2,384,000 96% of 1,086 Otis $1,080,000 $1,680,000 96% of 1,687 Tolland $430,000 $964,000 96% of 537 Tyringham $260,000 $536,000 96% of 308 Total $5,590,000 $9,849,000
*Fiber Connect has begun Make-Ready work in Monterey and Egremont.
8
9
Brief Governor's Office 1/19/2017 Brief Western MA Legislative Delegation 1/20/2017 Post Private Provider Submissions 1/23/2017 MBI Community Liaison and PM’s Engage Towns w/ Viable Path to Discuss Options w/ Selectboard Member 1/23/2017 – 3/21/2017 Public Open Meeting In Western MA 2/16/2017 Brief MBI Board of Directors – Town Preference & PP RFP 2/27/2017 Towns Selectboards Must Notify MBI to Opt out or Opt in to the MBI Private Providers Offering – Recommend a Select board vote following a public meeting or Town meeting vote Friday 3/24/2017 Issue Final Recommendations to MBI Board 3/28/2017
10