primary project team primary project team
play

Primary Project Team Primary Project Team COLLEGE TOWNSHIP, CENTRE - PDF document

328 INNOVATION BUILDING 328 INNOVATION BUILDING Primary Project Team Primary Project Team COLLEGE TOWNSHIP, CENTRE COUNTY, PA COLLEGE TOWNSHIP, CENTRE COUNTY, PA ` Owner of Record: RMP Co . Anthony Pacitti Jr. Development Of Record :


  1. 328 INNOVATION BUILDING 328 INNOVATION BUILDING Primary Project Team Primary Project Team COLLEGE TOWNSHIP, CENTRE COUNTY, PA COLLEGE TOWNSHIP, CENTRE COUNTY, PA ` Owner of Record: RMP Co . Anthony Pacitti Jr. Development Of Record : Innovation Capital Partners, LP Structural Emphasis Architect : Robert L. Kimball & Associates Engineer: Robert L. Kimball & Associates General Contractor : Poole Anderson Spring 2005 Senior Thesis MEP : Subcontracted by Poole Anderson Department of Architectural Engineering Consultant: Dr. Memari Existing Conditions Existing Conditions Existing Floor System Existing Floor System Typical Bay Consists of: Typical Bay Consists of: � Location: Location: � College Township, Centre County, Pennsylvania College Township, Centre County, Pennsylvania � � 3- 3 -W16 X 26 Interior Beams W16 X 26 Interior Beams � � � Cost: Cost: � 2- 2 - W24 x 26 Girders W24 x 26 Girders � � $10.1 Million for all onsite work, including tenant fit up allowances of $9.80 ances of $9.80 $10.1 Million for all onsite work, including tenant fit up allow 1- 1 - W16 x 26 , 1 W16 x 26 , 1- - W18 x 40 W18 x 40 � � � � Connecting Into Columns per rentable square foot per rentable square foot Connecting Into Columns 3 inch Slab + 3 inch Deck 3 inch Slab + 3 inch Deck � � Size: Size: � � 3 stories with 73,943 sq. ft 3 stories with 73,943 sq. ft of tenant space of tenant space � � � Functions: Functions: � Research and Development Research and Development 10,000 sq. ft 10,000 sq. ft � � Laboratories Laboratories 20,000 sq. ft 20,000 sq. ft � � Corporate Office Space Corporate Office Space 43,943 sq. ft 43,943 sq. ft � � � Project Delivery Method Project Delivery Method: : � Negotiated firm price with a General Contactor, including a share of cost Negotiated firm price with a General Contactor, including a shar e of cost � � savings, provided the cost is lower than an established bench mark. savings, provided the cost is lower than an established bench ma rk. Figure 2--Typical bay (30’-0” -39’-0”) Existing Roof Structure Existing Roof Structure Existing Foundation Existing Foundation K Joist Roof System K Joist Roof System � Square Footing and Strip Footing Square Footing and Strip Footing � Square Footings Ranging in size from Square Footings Ranging in size from � � 3 3’ ’- -0 0” ” x 3 x 3’ ’- -0 0” ” to 12 to 12’ ’- -0 0” ” x 12 x 12’ ’- -0 0” ” 22 K 4 Joists supported by W24 x 68 22 K 4 Joists supported by W24 x 68 � � Girder Strip Footing Ranging in size from Strip Footing Ranging in size from Girder � � 1’ ’- -2 2” ” to 2 to 2’ ’- -0 0” ” 1 W16 x 26 Exterior Beam W16 x 26 Exterior Beam � � 1- 1 -1/2 1/2” ” 20 Gauge Type B Deck 20 Gauge Type B Deck � � 2 W 24 x 55 Beams Were Added to 2 W 24 x 55 Beams Were Added to � � Support the VAV Mechanical Systems Support the VAV Mechanical Systems Typical Bay of Roof Existing Foundation Plan 1

  2. Existing Lateral System Redesigned Building Outline Existing Lateral System Redesigned Building Outline � Structural System Structural System � � 6 Braced Frames 6 Braced Frames � � Flat Plate System without beams Flat Plate System without beams � � 4 4- -North/South Direction North/South Direction � • Floor system Floor system • � 2 2- -West/East Direction West/East Direction • Columns • Columns � � Seismic Controls Seismic Controls • • Shear Walls Shear Walls � Typical Frames Are Composed of : � Typical Frames Are Composed of : � � Construction Schedule � Construction Schedule � 2 2- -W 10 Columns W 10 Columns � Rescheduled for Concrete System Rescheduled for Concrete System � � � Variety of W12, W16, W21, W24 Variety of W12, W16, W21, W24 � and HSS Compression and Tension and HSS Compression and Tension � Electrical System Electrical System � Members Members � Resize Main Distribution Panel Resize Main Distribution Panel � Existing Lateral System � Resize BUS Resize BUS- -DUCT to Each Floor and In the Main Distribution Panel DUCT to Each Floor and In the Main Distribution Panel � � Resize Breakers Resize Breakers � Goals for New Design Goals for New Design Redesigned Building Size Redesigned Building Size � Direct Effect on the Schedule Direct Effect on the Schedule � 5 5- -Story Building Story Building � � � Total Height = 75 Total Height = 75’ ’- -0 0” ” � Lower Overall Cost Lower Overall Cost � � � 14 14’ ’- -0 0’ ’ Floor to Floor Height Floor to Floor Height � � More tenant Space with the More tenant Space with the � � Additional 50,000 sq. ft of Floor Area Additional 50,000 sq. ft of Floor Area � Additional 2 Stories Additional 2 Stories � Increase Floor to Floor Height Increase Floor to Floor Height � Design Loads Direct Design Criteria Design Loads Direct Design Criteria � � MINIMUM OF THREE CONTINUOUS SPANS IN EACH MINIMUM OF THREE CONTINUOUS SPANS IN EACH DIRECTION DIRECTION � DEAD LOAD = 165 PSF � DEAD LOAD = 165 PSF � LONG � LONG- -SPAN/ SHORT SPAN/ SHORT- -SPAN RATIO NOT GREATER SPAN RATIO NOT GREATER THAN 2 THAN 2 (12” ”/12)(150PSF)+(15PSF) /12)(150PSF)+(15PSF) FLOORING (12 FLOORING � SUCCESSIVE SPAN LENGTHS IN EACH DIRECTION SUCCESSIVE SPAN LENGTHS IN EACH DIRECTION � � � LIVE LOAD = 80 PSF LIVE LOAD = 80 PSF SHALL NOT DIFFER BY MORE THAN ONE 1/3 THE SHALL NOT DIFFER BY MORE THAN ONE 1/3 THE LONGER SPAN LONGER SPAN � Fy = 60,000 PSI � Fy = 60,000 PSI � ALL LOADS MUST BE DUE TO GRAVITY ONLY ALL LOADS MUST BE DUE TO GRAVITY ONLY � � � SERVICE LIVE LOAD SHALL EXCEED TWO TIMES THE SERVICE LIVE LOAD SHALL EXCEED TWO TIMES THE � F F’ ’c = 4,000 PSI c = 4,000 PSI SERVICE DEAD LOAD SERVICE DEAD LOAD � 2

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend