Presentation of the Power Supply Plan BURNS~ DONNELL. Grand Haven - - PowerPoint PPT Presentation

presentation of the power supply plan
SMART_READER_LITE
LIVE PREVIEW

Presentation of the Power Supply Plan BURNS~ DONNELL. Grand Haven - - PowerPoint PPT Presentation

Presentation of the Power Supply Plan BURNS~ DONNELL. Grand Haven Board of Light & Power November 2018 Agenda Power Supply Plan Highlights Industry Overview and Trends Utility Planning Requirements Planning Efforts from


slide-1
SLIDE 1

BURNS~ £DONNELL.

Grand Haven Board of Light & Power

Presentation of the Power Supply Plan

November 2018

slide-2
SLIDE 2

BURNS~M~DONNELL"

Agenda

► Power Supply Plan Highlights ► Industry Overview and Trends ► Utility Planning Requirements ► Planning Efforts from 2012 to Present ► Power Supply Options ► Economic Analysis ► Conclusions & Recommendations

1

slide-3
SLIDE 3

BURNS~M~DONNELL"

Agenda

► Power Supply Plan Highlights ► Industry Overview and Trends ► Utility Planning Requirements ► Planning Efforts from 2012 to Present ► Power Supply Options ► Economic Analysis ► Conclusions & Recommendations

2

slide-4
SLIDE 4

Integrated Resource Planning Studies Replacement Plant Siting Studies

BURNS~M~DONNELL~

Internal & Independent Condition Assessment of Existing Plant MISO Network Compatibility Assessment

Supply Portfolio Paths Economic Screening/ Cost­ Benefit Evaluation

Power Supply Plan

What is a power supply plan?

Primary goal of a power supply plan is to provide an economic evaluation

  • f a utility’s power supply portfolio
  • ver both short-term and long-term

planning horizons. Need to focus on short-term decisions that position utility for long-term success.

3

slide-5
SLIDE 5

BURNS~M~DONNELL"

Power Supply Plan Highlights

► GHBLP has evaluated its power supply comprehensively since 2012 ► Within the electric utility industry, older, less efficient steam plants are now higher cost. This is true for J.B. Sims Unit 3. There are less expensive resources available. ► Having Network Integrated Transmission Service (NITS, full service transmission rights), the GHBLP electrical system will be more reliable and also provide the opportunity to access low cost capacity and energy. ► Maintaining appropriate level of on­system generation allows GHBLP to retain local generating capacity while taking advantage of low MISO power prices. ► Snowmelt system can be operated in a “decoupled” configuration with a new natural gas­fired heat generator and electric pumps. A combination of local on-system resources, market capacity, and renewables would provide GHBLP a well diversified power portfolio.

4

slide-6
SLIDE 6

BURNS~M~DONNELL"

Agenda

► Power Supply Plan Highlights ► Industry Overview and Trends ► Utility Planning Requirements ► Planning Efforts from 2012 to Present ► Power Supply Options ► Economic Analysis ► Conclusions & Recommendations

5

slide-7
SLIDE 7

BURNS~M~DONNELL"

Industry Overview and Trends

► Many coal­fired power plants have retired due to economics, more are expected ► Natural gas prices are low, expected to stay low ► Relatively low overall load growth across the U.S. ► Increasing amounts of renewable power, especially wind in the Midwest ► Wholesale electricity prices remain low

6

slide-8
SLIDE 8

BURNS~M~DONNELL"

Municipal Utility Trends

► Municipal utilities are retiring uneconomic generation

  • Mainly small­scale coal plants

► Membership in municipal joint action agencies provides economies of scale and additional reliability for small communities ► Low wholesale electricity prices support “relying on the market” for capacity ► Low load growth along with increases in energy efficiency reduce need for new on­system generation ► Municipal utilities are increasingly installing reciprocating engines as a source of new­build capacity in cooperation with renewable energy purchases

7

slide-9
SLIDE 9

Historical Wholesale Energy Price

$90

$80 [ $70

:::!!:

­

~ ;$60 CJ

·;::

~

$50

IO

.5

~$40

:::!!:

~

$30

..

IO

g

$20

...I

$10 $0

<D

I'­­ 00 0)

.....

N

(") s:::t LO <D

I'­­ 00

..... ..... ..... ..... ..... ..... ..... ..... .....

N N N N N N N N N N N N N

BURNS~M~DONNELL~

Wholesale Energy Market Prices (2006-2018)

► Prior to 2009, market energy prices significantly higher than today

  • Recession reduced demand
  • Natural gas fracking lowered

fuel price

  • Increased energy efficiency
  • Increased renewables

► Post 2009, market prices have been lower ► J.B. Sims Unit 3 is unprofitable at current market prices Polar Vortex Average $48/MWh Average $33/MWh

8

slide-10
SLIDE 10

BURNS~M~DONNELL"

Agenda

► Power Supply Plan Highlights ► Industry Overview and Trends ► Utility Planning Requirements ► Planning Efforts from 2012 to Present ► Power Supply Options ► Economic Analysis ► Conclusions & Recommendations

9

slide-11
SLIDE 11

BURNS~M~DONNELL~

Pillars of Utility Mission Statement

► Low cost energy ► Reliable energy ► Safe energy ► Environmentally compliant energy

10

slide-12
SLIDE 12

BURNS~M~DONNELL"

GHBLP Key Considerations

► Previous studies recommended the following actions:

  • Retire Sims Unit 3 on an economic basis
  • Invest in transmission and distribution to prepare for increase reliance on

market imports

  • Most economical option for on­system generation is a small, quick­start

natural gas resource such as reciprocating engines

► Community and policy drivers:

  • Maintain some form of on­system generation
  • Move away from coal­fired generation
  • Shift toward a more sustainable power supply and increase usage of

renewable resources

  • Continue operation of snowmelt system regardless of J.B. Sims retirement

Ideal power supply plan for Grand Haven balances economics and community drivers

11

slide-13
SLIDE 13

BURNS~M~DONNELL~

GHBLP’s Obligations

► Provide sufficient capacity (MW) to meet demand

  • Based on NERC rules, MISO sets capacity requirement based on

GHBLP’s load forecast

  • Capacity comes from units that GHBLP builds, contracts through bi­

lateral agreement, or demand side management

  • Capacity typically has to be dispatchable, renewables are intermittent

and don’t provide significant capacity

► Provide sufficient energy (MWh) to meet customers’ needs

  • Electrical energy comes from units that GHBLP builds, contracts, net

metering, conservation, or MISO market

► Energy must be compliant with regulations

  • Renewable and solar mandates
  • Environmental regulations

12

slide-14
SLIDE 14

BURNS~M~DONNELL~

90 80 70

  • 60
~ !.

50

::,

  • ~ 40
C.

"'

  • 30

20

10

4

21 21

20 20 20

­ . . . .

a, ~ N C")

v

N N N N N N N N N N N ­ JBSims:3 ­ Beebe 1 B \Mnd Project

Path 1 - Sims Operational

19 19 18 17 17 6 6

I I

ri

5 5

Capacity Surplus I (Deficit)

4 4 4 3 3 f'J

~ .. r. ..

  • r. .. r. .. r

···························

  • ~ .

.

Lt) <O r­­­ co a, N C")

v

Lt) <O r­­­ co N N N N N C") C") C") C") C") C") C") C") C") N N N N N N N N N N N N N N ­ MPPA Landfill Gas Project MPPA Solar Project ­ Pegasus Wind Project ­ CMS Energy Contract Market Capacity Purchases ­ System Peak
  • • • • System Peak+ Reserve

Balance of Loads & Resources (BLR)

► MISO requires utilities to maintain capacity reserves

  • f 7.8% in excess of demand

► GHBLP must secure “firm” capacity to meet its demand plus reserve requirements ► Renewables do not get full credit due to intermittency (i.e. non­firm)

  • Wind receives 15.6%
  • Solar receives 50%
  • Dependent on actual generation

13

slide-15
SLIDE 15

BURNS~M~DONNELL"

Agenda

► Power Supply Plan Highlights ► Industry Overview and Trends ► Utility Planning Requirements ► Planning Efforts from 2012 to Present ► Power Supply Options ► Economic Analysis ► Conclusions & Recommendations

14

slide-16
SLIDE 16

S&L Integrated Resource Plan

2012

B&V Natural Gas Generation Siting Study

2013 I

20141

B& V Natural Gas Generation Siting Study Supplement

BURNS~M~DONNELL~

Board Approved Policy Statements

2015

l

Organization Check Up

I

2016

Key Policy Statements GHBLP Strategic Plan Sims Plant Closure Recommendation Report MISO Report I RP Considerations.....,_ Sims Internal Condition Assessment Snowmelt Study

2017 2018,

Sims Staffing Report

1

B&V Sims Life Assessment Report

Power Supply Planning Efforts

GHBLP has completed numerous comprehensive studies over the past several years assessing its power supply plan.

15

slide-17
SLIDE 17

S&L Integrated Resource Plan

2012

B&V Natural Gas Generation Siting Study

2013 I

20141

B& V Natural Gas Generation Siting Study Supplement

BURNS~M~DONNELL~

Board Approved Policy Statements

2015

l

Organization Check Up

I

2016

Key Policy Statements GHBLP Strategic Plan Sims Plant Closure Recommendation Report MISO Report I RP Considerations.....,_ Sims Internal Condition Assessment Snowmelt Study

2017 2018,

Sims Staffing Report

1

B&V Sims Life Assessment Report

Power Supply Planning Efforts

16

slide-18
SLIDE 18

BURNS~M~DONNELL"

Initial Planning Efforts

► Since 2012, GHBLP has been gathering information to address the need to replace aging power supply resources ► Sargent & Lundy (S&L) Integrated Resource Plan (April 2012)

  • Formulated a long­term plan to meet GHBLP’s future power supply

requirements

  • Performed condition assessment and environmental compliance

evaluation of J.B Sims Unit 3 and Diesel Plant

  • Identified that Unit 3 and the diesel plant would retire in 2020
  • Extensive evaluation of power supply options

Identified that Sims Unit 3 and the diesel plant would retire in 2020

17

slide-19
SLIDE 19

BURNS~M~DONNELL"

S&L 2012 IRP Resource Options

► S&L evaluated the following resource options in the 2012 Integrated Resource Plan:

  • Continued operation of J.B. Sims Unit 3
  • Combined Cycle Gas Turbine
  • Nuclear Plant
  • Dual­unit, AP1000
  • Small Modular Reactor
  • Circulating Fluidized Bed Boiler
  • Advanced pulverized coal
  • Single­unit and dual­unit options
  • Steam power plant
  • Dual­fueled coil and biomass boiler
  • Biomass­fueled boiler
  • Gas fired boiler
  • Geothermal
  • Dual Flash and binary
  • Natural Gas Plants
  • Aeroderivative combustion turbine
  • Reciprocating internal combustion

engines

  • Wind Farms
  • Onshore
  • Offshore
  • Landfill gas
  • Solar thermal
  • With and without storage
  • Solar photovoltaic
  • Small­scale solar
  • Large­scale solar
  • Hydroelectric
  • Conventional
  • Pumped storage
  • Compressed air energy storage

18

slide-20
SLIDE 20

BURNS~M~DONNELL"

Initial Planning Efforts Continued

► S&L 2012 IRP Conclusions

  • Recommended obtaining Network Integrated Transmission Service

(NITS) to increase wholesale market purchases

  • Recommended retirement of Sims 3 and Diesel Unit 1 in 2020
  • Most economic option would be combination of 80 percent power from

market and quick start generation installed as self­build option

  • Consider installation of a quick start generation facility or purchase a

share in a natural gas facility

► Black & Veatch (B&V) Natural Gas Generation Siting Study (April 2013)

  • Recommended replacing Sims with a natural gas peaking plant placed

at the Sims site

  • Supplemental study evaluated conversion of Unit 3 to natural gas, but

determined that it was uneconomical

19

slide-21
SLIDE 21

S&L Integrated Resource Plan

2012

B&V Natural Gas Generation Siting Study

2013 I

20141

B& V Natural Gas Generation Siting Study Supplement

BURNS~M~DONNELL~

Board Approved Policy Statements

2015

l

Organization Check Up

I

2016

Key Policy Statements GHBLP Strategic Plan Sims Plant Closure Recommendation Report MISO Report I RP Considerations.....,_ Sims Internal

  • ndition Assessment

Snowmelt Study

2017 2018,

Sims Staffing Report

1

B&V Sims Life Assessment Report

Power Supply Planning Efforts

20

slide-22
SLIDE 22

BURNS~M~DONNELL"

Continued Planning Efforts

► Key Policy Statement (October 2014)

  • GHBLP stated intention to reduce reliance on coal and transition to

alternative sources of fuel

► Key Policy Statement (August 2015)

  • Continue to evaluate alternative generation options to Sims
  • Complete transmission and interconnection studies to prepare for increased

reliance on wholesale imports

  • Avoid “overbuilding” or market speculation to meet customer needs

► Organization Check Up (January 2016)

  • Determined Sims is no longer an economical power supply option
  • Recommended capital transmission investments and network membership

in MISO to prepare for Sims retirement

  • Sims debt retirement provides GHBLP with additional capital for investment

in transmission and distribution systems

  • GHBLP has little power supply ownership diversification and therefore has

higher risk than most utilities of similar size

21

slide-23
SLIDE 23

S&L Integrated Resource Plan

2012

B&V Natural Gas Generation Siting Study

2013 I

20141

B& V Natural Gas Generation Siting Study Supplement

BURNS~M~DONNELL~

Board Approved Policy Statements

2015

l

Organization Check Up

I

2016

Key Policy Statements GHBLI Strategic Pia, Sims Plant Closure Recommendation Report MISO Report ­ I RP Considerations.....,_ Sims Internal _ Condition Assessment Snowmelt Study

2017 2018,

Sims Staffing Report

1

B&V Sims Life Assessment Report

Recent Planning Efforts

22

slide-24
SLIDE 24

BURNS~M~DONNELL"

Recent Planning Efforts

► IRP Considerations (February 2018)

  • Emphasized importance of supply diversification and future adaptability and

flexibility of GHBLP’s power supply

► MISO Transmission Report (February 2018)

  • Recommended GHBLP obtains NITS status to enhance reliability of supply

imports, as recommended in previous power supply studies

  • Increased transmission and distribution capacity will increase reliability

► Sims Internal Condition Assessment (February 2018)

  • Conducted condition assessment as recommended in previous power

supply studies

  • Results indicated that capital expenditures exceeded benefits of continued

long­term operation of Unit 3

  • Recommended avoiding any additional capital expenditures on Sims plant,

reducing position in coal markets, prepare a staff succession plan, and working with MPPA to develop reduced run­time plan for Sims

23

slide-25
SLIDE 25

BURNS~M~DONNELL"

Recent Planning Efforts Continued

► Sims Staffing Report (March/June 2018)

  • Normal staffing level at Sims is 39 employees
  • New power facility will need approximately 13 to 15 employees
  • Staffing levels can be reduced through attrition with no terminations of

steam plant employees

  • Replacing Sims with smaller plant estimated to save $2.7M on labor

expenses annually

► Sims Power Plant Closure Report (April 2018)

  • Determined Sims operation does not impact GHBLP customer reliability
  • Sims cannot operate beyond 2020 in a safe, reliable, economic manner

without substantial capital expenditure

  • Ancillary benefits of Sims operation cannot be justified

24

slide-26
SLIDE 26

BURNS~M~DONNELL"

Recent Planning Efforts Continued

► B&V Sims Life Assessment Report (June 2018)

  • The assessment found that Unit 3 has reached the end of useful life
  • Capital expenditures of $35M are required to keep Sims safe and

reliable, but the costs exceed the benefits of long­term operation

  • B&V recommended the retirement of Sims by June 2020 and to conduct

production cost modeling to identify the most economical power supply portfolio to optimize internally owned generation options.

► City Council resolution stating local generation and snow melt system is important to the community

25

slide-27
SLIDE 27

BURNS~M~DONNELL"

Snowmelt System

► Current system is coupled to Sims plant using heat energy supplied from the boiler ► Two independent studies were performed to evaluate alternatives after Sims retirement

  • First study determined amount of heat and energy required to operate the

snowmelt system

  • Second study determined what would be required to “decouple” the

snowmelt system from Sims

► New system would likely require natural gas­fired heat generators and electric pumps

  • Costs are largely dependent on system location

Snowmelt should not be the driver in deciding power supply path for the electric customers

26

slide-28
SLIDE 28

BURNS~M~DONNELL"

Agenda

► Power Supply Plan Highlights ► Industry Overview and Trends ► Utility Planning Requirements ► Planning Efforts from 2012 to Present ► Power Supply Options ► Economic Analysis ► Conclusions & Recommendations

27

slide-29
SLIDE 29

BURNS~M~DONNELL"

Key Components of the Power Supply Plan

► Review of completed studies ► Combine previous studies into a singular plan ► Identify power supply options available to GHBLP ► Economic cost­benefit evaluation Objective: Determine the “best” mix of resources that provides safe, reliable, environmentally compliant, low cost capacity and energy to GHBLP’s customers.

28

slide-30
SLIDE 30

BURNS~M~DONNELL"

Power Supply Options

► Keep Sims 3 operational

  • Requires full staffing level and $35M in capital expenditure to maintain

safe and reliable operation

  • While option is not economical, nor has it been recommended in

previous studies, it was provided as a method of comparison

► Build replacement generation

  • Previous studies recommended quick start, natural gas plants as an

alternative to Sims located at Harbor Island.

  • Burns & McDonnell agrees with previous study results indicating quick

start generation would be the preferred replacement of Sims Unit 3.

► Purchase capacity from the market

  • NITS provides clear economic benefits of lower cost energy and

capacity

  • Transmission and distribution upgrades in­progress enhance reliability

29

slide-31
SLIDE 31

BURNS~M~DONNELL"

Power Supply Paths

► Based on previous studies and technical evaluation, four power supply paths were determined and modeled for further evaluation:

  • Path 1 - Business­as­usual with continued Sims operation
  • Path 2 - Retire Sims and replace with 4x9 MW (36 MW total) reciprocating

engines

  • Path 3 - Retire Sims and replace with 6x9 MW (54 MW total) reciprocating

engines

  • Path 4 - Retire Sims and replace with market capacity

► All paths, specifically Paths 2, 3, and 4, include snow melt

  • alternatives. Costs have been included for “decoupling” the

snowmelt system from Sims and operational expenses associated with a new system. ► All paths interact with the wholesale energy market by selling and purchasing from MISO.

30

slide-32
SLIDE 32

90 80

70

_60 3:

~50

~

~

40

C.

ca

O 30

20 10

Path 1 - Sims Operational

Capacity Surplus I (Deficit)

4

21 21

20 20 20 19 19 18 17 17 6 6

5 5 4 4 4 3 3

0)

.....

N ..­

N N N N N N N

­ JBSims:3

('I')

v

N N

N N ­ Beebe 1 B Wind Project Market Capacity Purchases

­system

Peak

LO

N N

<O

r--

N N

N N

00 0) N N N N .....

('I') ('I')

N N

N

('I')

N

('I')

v

('I') ('I')

N N

LO ('I')

N

­ MPPA Landfill Gas Project MPPA Solar Project ­ Pegasus Wind Project ­ CMS Energy Contract

  • • • • System Peak + Reserve
<O

r--

('I') ('I')

N N 00

('I')

N

BURNS~M~DONNELL~

Path 1 BLR - Continue to Operate Sims

31

slide-33
SLIDE 33

4 90 80 70

_60

3:

~50

~

~

40

C.

ca

O 30

20 10

0)

..-

N

Path 4 - MISO Market

Capacity Surplus I (Deficit)

(49) (49) (49) (49) (50) (50) (51) (51) (53) (53) (63) (63) (64) (65) (65) (65) (66) (66) (66)

  • ..-

N

('I')

v

LO <O

r--

00 0)

..-

N

('I')

v

LO <O

r--

00 N N N N N N N N N N

('I') ('I') ('I') ('I') ('I') ('I') ('I') ('I') ('I')

N N N N N N N N N N N N N N N N N N N

  • JBSims:3
  • MPPA Landfill Gas Project

MPPA Solar Project

  • Beebe 1

B Wind Project

  • Pegasus Wind Project
  • CMS Energy Contract
  • system

Peak

  • • • • System Peak + Reserve

BURNS~M~DONNELL~

Path 4 – Retire Sims Unit 3

32

slide-34
SLIDE 34

90 80 70

_60

3:

~50

~

  • ~ 40

C.

ca

O 30

20 10 4

Path 4 - MISO Market

Capacity Surplus I (Deficit)

(49) (49) (49) (49) (50) (50) (51) (51) (53) (53) (63) (63) (64) (65) (65) (65) (66) (66) (66)

  • 0)

,.-

N

('I')

v

LO <O

I'-

00 0) ,.- N

('I')

v

LO <O

I'-

00 ,.- N N N N N N N N N N

('I') ('I') ('I') ('I') ('I') ('I') ('I') ('I') ('I')

N N N N N N N N N N N N N N N N N N N N

  • JBSims:3
  • MPPA Landfill Gas Project

MPPA Solar Project

  • Beebe 1

B Wind Project

  • Pegasus Wind Project
  • CMS Energy Contract

Market Capacity Purchases

  • system

Peak

  • • • • System Peak + Reserve

BURNS~M~DONNELL~

Path 4 – Retire Sim & Build Nothing

33

slide-35
SLIDE 35

90 80 70

_60

3:

~50

~

  • ~ 40

C.

ca

O 30

20 10

Path 2 - 4x9 MW RICE Plant

Capacity Surplus I (Deficit)

(49) (49) (49) (15) (15) (16) (16) (17) (18) (19) (29) (29) (30) (30) (31) (31) (31) (32) (32) 4

  • 0)

,.-

N

('I')
  • .:t-
LO <O

r--

00 0) ,.- N

('I')
  • .:t-
LO <O

r--

00 ,.- N N N N N N N N N N

('I') ('I') ('I') ('I') ('I') ('I') ('I') ('I') ('I')

N N N N N N N N N N N N N N N N N N N N

  • JBSims:3
  • MPPA Landfill Gas Project

MPPA Solar Project

  • Beebe 1

B Wind Project

  • Pegasus Wind Project
  • CMS Energy Contract
  • 4x9 MW RICE Engines

Market Capacity Purchases

  • system

Peak

  • • • • System Peak + Reserve

BURNS~M~DONNELL~

Path 2 BLR – Retire Sims & Build 36 MW of Recips

34

slide-36
SLIDE 36

Path 3 - 6x9 MW RICE Plant

Capacity Surplus I (Deficit)

(0) (1) (1) (12) (12) (13) (13) (14) (14) (14) (15) (15)

90 80

70

_60 3:

~50

~

  • ~ 40

C.

ca

O 30

20 10

4 (49) (49) (49) 2

2

0)

.....

N

  • ..-

N N N N N N N

  • JBSims:3
('I') 'st"

N N

N N

  • Beebe 1

B Wind Project

  • 6x9 MW RICE Engines
  • system Peak

BURNS~M~DONNELL~ 1 1

............ ~

  • .

~

  • .

~

  • .

~

  • .

~

  • .

~

  • .

~

  • .

:....:_·

LO

N N

<O

r--

00 0) N N N N N N N N .....

('I') ('I')

N N

N

('I')

N

('I') 'st" ('I') ('I')

N N

LO ('I')

N

  • MPPA Landfill Gas Project

MPPA Solar Project

  • Pegasus Wind Project
  • CMS Energy Contract

Market Capacity Purchases

  • • • • System Peak + Reserve
<O

r--

("I') ('I')

N N 00

('I')

N

Path 3 BLR – Retire Sims & Build 54 MW of Recips

35

slide-37
SLIDE 37

70 60

_so

~

::E

  • "C

~

40

...J

u

·.::::

  • u

.!! 30

w

>, .::::

:::,

:I: 20

10

GHBLP 2017 Hourly Load Profile

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec BURNS~M~DONNELL~

GHBLP Hourly Load Profile

GHBLP must have enough capacity to meet peak demand. But a majority of the energy need is much lower.

36

slide-38
SLIDE 38

70 60 50 ~

:E:

  • 40

"C

C'l:I

...J

(J

"i: 30

Q)

w

20 10

2017 Load Duration Curve

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Percent of Time Above Load (%)

BURNS~M~DONNELL~

GHBLP Load Duration Curve

Sims Unit 3 is 70 MW. It is too big for GHBLP load requirements.

37

slide-39
SLIDE 39

80%

"C 70%

.c:

(/)

~

60%

.c:

t-

~

50%

.c <t

~

40%

(1)

>

~30%

(1)

E

i= 20%

  • ?fl.10%

0%

BURNS~M~DONNELL~

Distribution of Historical Grand Haven Electric Demand

  • 2011 • 2012 • 2013 • 2014 • 2015 • 2016 • 2017 1

I I

111

1 1 1

■I■

... -·

>30 >35 >40 >45 >50 Electrical Demand (MW)

  • ·

>55 ----- >60

Distribution of GHBLP Electrical Demand

38

slide-40
SLIDE 40

BURNS~M~DONNELL"

Agenda

► Power Supply Plan Highlights ► Industry Overview and Trends ► Utility Planning Requirements ► Planning Efforts from 2012 to Present ► Power Supply Options ► Economic Analysis ► Conclusions & Recommendations

39

slide-41
SLIDE 41

BURNS~M~DONNELL"

Economic Evaluation

► Objective: Assess the cost-benefits of individual resources to determine how GHBLP’s overall power supply portfolio can meet customers’ needs both short-term and long-term ► Utilize costs for resources as described previously ► Develop forecasts for fuel and market energy prices ► Economic evaluation includes:

  • Fixed expenses
  • Variable expenses
  • Fuel costs
  • Debt service expenses
  • Credit for market revenue
  • Snowmelt system costs

40

slide-42
SLIDE 42

BURNS~M~DONNELL"

Economic Evaluation – Methodology

► Utilized pre-screed alternatives and existing resources to determine optimized portfolio ► Sophisticated software that simulates power generation resources’ interaction with the MISO market over a 20-year horizon

  • Software dispatches resources every hour of the year

► Forecasts an “all­in” cost to GHBLP for serving customer’s needs over the 20­year horizon ► Sensitivities evaluate portfolios across different natural gas and market capacity price forecasts

41

slide-43
SLIDE 43

Flexible Dispatch Provides Value in the Market

Energy Price = Fuel + Variable Costs Sims Energy Cost Coal units are not flexible. Sims energy cost is more expensive than the market. It is difficult to turn off the unit. Does not include fixed or capital costs Recip Energy Cost Recip engines are extremely flexible. If prices are low, they turn

  • ff. If prices are high, they

dispatch and “cherry pick.”

Average Daily Wholesale Energy Price in 2017

$70 $60

  • .c:

3:

~

$50

~ -

Q)

~

$40

>,

C)

...

Q)

ifi $30

Q)

cu

~

$20

.c:

3:

$10 $0

r-- .....

I C

co

...,

r-- r-- r--

..... ..... .....

I I I

.0

.... ....

Q)

co

CL

LL

~ <(

BURNS~M~DONNELL~

r-- r-- r-- r-- r-- r--

..... ..... ..... ..... ..... .....

I I I I I I

>,

C 0) CL

_.

co

:::::, :::::, :::::, Q) (.)

~

..., ...,

<(

(f)

r-- r--

..... .....

I I

>

(.) Q)

z

42

slide-44
SLIDE 44

BURNS~M~DONNELL"

Financial Assumptions

► 20-year planning horizon: 2019 through 2038 ► Interest rate: 4% ► Financing term: 20 years ► General inflation: 2.5% ► Discount rate: 4% ► Demolition costs have been included ► Snowmelt costs included in all paths

43

slide-45
SLIDE 45

BURNS~M~DONNELL~

Numerous Scenarios Considered

► Sensitivity analysis was completed as part of the economic evaluation

  • Aimed to evaluate the robustness of

power supply paths across uncertain variables

► Sensitivities on natural gas price and market capacity price ► Four scenarios were considered within the economic evaluation

  • Low Natural Gas & Low Capacity
  • Low Natural Gas & High Capacity
  • High Natural Gas & Low Capacity
  • High Natural Gas & High Capacity

Natural Gas Price Low Low High Capacity Price High

44

slide-46
SLIDE 46

BURNS~M~DONNELL~

Economic Evaluation – Portfolio Analysis Results

Grand Haven Board of Light & Power

Power Supply Path Path 1 J.B. Sims Unit 3 Path 2 4x 9 MW Recips Path 3 6x 9 MW Recips Path 4 MISO Market 2019 2020 Retire J.B. Sims Retire J.B. Sims Retire J.B. Sims 2021 2022 2023 36 MW Recips 54 MW Recips 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 NPV Low Gas/High Capacity $450,121,714 $407,701,944 $406,609,640 $386,185,943 Delta $ $63,935,770 $21,516,000 $20,423,697 $0 Delta % 16.6% 5.6% 5.3% 0.0% Low Gas/Low Capacity $453,384,057 $388,717,345 $395,052,209 $352,347,011 Delta $ $101,037,046 $36,370,335 $42,705,198 $0 Delta % 28.7% 10.3% 12.1% 0.0% High Gas/High Capacity $443,735,429 $440,092,581 $438,938,872 $418,780,959 Delta $ $24,954,470 $21,311,622 $20,157,913 $0 Delta % 6.0% 5.1% 4.8% 0.0% High Gas/Low Capacity $446,997,772 $421,107,982 $427,381,441 $384,942,027 Delta $ $62,055,746 $36,165,956 $42,439,415 $0 Delta % 16.1% 9.4% 11.0% 0.0%

45

slide-47
SLIDE 47 (/) $500 C:

~

:E

  • ' '

$450

'"

J

;

!

  • ~
C0

II ....

N

$400

'I

·,

  • C1'
::::,

ii

~ -

)

C: \ I

C1'

Ill

$350

C1'

'-::,/

lo.

ll.

  • C1'

z

$300 $250

Path 1 Path 2 Path 3 Path 4 J.B. Sims Unit 3 4x 9 MW Recips 6x 9 MW Recips MISO Market

Low Gas/Low Capacity $453,384,057 $388,717,345 $395,052,209 $352,347,011 Low Gas/High Capacity $450,121 ,714 $407,701 ,944 $406,609,640 $386,185,943

High Gas/Low Capacity $446,997,772 $421 ,107,982 $427,381,441 $384,942,027

High Gas/High Capacity $443,735,429 $440,092,581 $438,938,872 $418,780,959

BURNS~M~DONNELL~

Economic Evaluation – Net Present Value Results

Sims locks in high costs Provides opportunity to lower costs, and provides local resource. Opportunity for lower costs, but lacks local resource How large should the local resource be?

46

slide-48
SLIDE 48

80%

"C 70%

.c:

(/)

~

60%

.c:

t-

~

50%

.c <t

~

40%

(1)

>

~30%

(1)

E

i= 20%

  • ?fl.10%

0%

BURNS~M~DONNELL~

Distribution of Historical Grand Haven Electric Demand

  • 2011 • 2012 • 2013 • 2014 • 2015 • 2016 • 2017 1

I I

>30 >35

  • >60

Why Not Replace All of Sims with a Large Plant?

Building smaller enhances flexibility, allows for future expansion, covers approximately 50% of load Very rarely is load above 50MW. Building too big reduces long-term flexibility.

47

slide-49
SLIDE 49

BURNS~M~DONNELL"

Agenda

► Power Supply Plan Highlights ► Industry Overview and Trends ► Utility Planning Requirements ► Planning Efforts from 2012 to Present ► Power Supply Options ► Economic Analysis ► Conclusions & Recommendations

48

slide-50
SLIDE 50

BURNS~M~DONNELL"

Conclusions

► Continued operation of Sims provides the most expensive power supply path with the least amount of flexibility.

  • Burns & McDonnell does not recommend this option, which is consistent with both Sargent &

Lundy’s and Black & Veatch’s previous results and recommendations as well.

  • Burns & McDonnell agrees with the Board’s decision to cease operations in June 2020

► Relying only on market capacity and energy provides the lowest cost option in all scenarios

  • While this is the lowest cost option, it does expose GHBLP to potential rising prices in energy

and capacity

  • This is a viable path for GHBLP

► New on­system generation provides lower cost than continued operation of Sims, but higher cost than relying only on the market

  • This is a higher cost option than relying solely on the market based on current forecasts for

both energy and capacity

  • This is a viable path for GHBLP

► Either of the viable paths provides flexibility to allow for the use of emerging technologies such as local solar and energy storage

49

slide-51
SLIDE 51

BURNS~M~DONNELL"

Conclusions & Recommendations

► Based on the combination of economics, public feedback to date, and Board & Council policy statements, Burns & McDonnell concludes the following:

  • Ongoing operation of Sims Unit 3 is higher cost than other options; Sims

Unit 3 should be retired by June 2020.

  • The installation of a 35 to 40 MW reciprocating engine plant on Harbor

Island will provide a local generation resource while allowing increased flexibility and should be pursued.

  • GHBLP should meet additional capacity requirements through market

purchases or agreements.

  • This path provides GHBLP enhanced flexibility to be both proactive and

reactive to changes within the power industry regarding advances in technology and power prices.

  • If market conditions change in the future, additional generating units can

be added to the Harbor Island plant while avoiding the risk of

  • verbuilding today.

50

slide-52
SLIDE 52

BURNS~M~DONNELL"

Action Plan

  • 1. Address public input/feedback and present to the Board for review.
  • 2. Finalize the power supply plan report
  • 3. Move from planning to engineering phase
  • a. Conduct a Project Definition Report (PDR) for the new plant: includes demolition plan
  • f existing site, preliminary engineering, site layout, cost estimates, interconnection

studies, permitting, execution schedules

  • b. Engineer replacement for snow melt system both during the transition and

permanently

  • c. The PDR will be needed to meet the requirements of the City Council’s Resolution

passed on September 4, 2018.

  • d. Develop remediation plans for Sims facility and coordinate with PDR execution

schedules.

  • 4. Secure short-term capacity and energy during the transition from Sims

Unit 3 to the new plant

  • 5. Begin building a long-term diversified portfolio, through the joint action

agency, that will complement and supplement the new generating facility on Harbor Island that offers cost competitive power supply for electric customers.

51

slide-53
SLIDE 53

BURNS~M~DONNELL"

Opportunity for Feedback

► Open the floor to the public for questions and feedback. ► Each speaker needs to provide their name and address for the record. ► Each speaker will be limited to approximately 3 minutes to provide ample time for everyone to have the opportunity to speak or ask questions. ► Questions will either be addressed 1) verbally during the meeting or 2) with written responses within the final report.

52

slide-54
SLIDE 54