waste to energy feasibility report
play

Waste to Energy Feasibility Report Mark Spafford, P.E., General - PowerPoint PPT Presentation

MUNICIPALITY OF ANCHORAGE ENTERPRISE AND UTILITY OVERSIGHT COMMITTEE Waste to Energy Feasibility Report Mark Spafford, P.E., General Manager Marc Rogoff, Ph.D., Geosyntec Consultants March 12, 2020 #DoSomething Agenda 1 3 2 Next Steps


  1. MUNICIPALITY OF ANCHORAGE ENTERPRISE AND UTILITY OVERSIGHT COMMITTEE Waste to Energy Feasibility Report Mark Spafford, P.E., General Manager Marc Rogoff, Ph.D., Geosyntec Consultants March 12, 2020 #DoSomething

  2. Agenda 1 3 2 Next Steps Why WTE WTE Feasibility Report

  3. Time is running out… 01. Why WTE? All things the same… 03. Next Steps With WTE…

  4. Following the Plans…

  5. Biosolids Biosolids Issues • $100 Million Investment by AWWU • WTE Can Provide the Answer at Significantly Lower Cost • Synergy - the Public expects us to work together

  6. Alaska has garbage problems too

  7. PART 2 Presentation of Waste-to-Energy Feasibility Report Marc J. Rogoff Geosyntec Consultants | March 12, 2020

  8. Agenda The Roadmap Budget Schedule

  9. Study Steps Completed So Far  Pre-Feasibility Report and Presentation  Stakeholder Meetings  Tours of WTE Plants  Responses to Assembly Questions  Development of Feasibility Report

  10. Our Tours • Well Run and Financially Strong • Public/Private Partnerships • Longevity – 30+ Years • Exceed State and EPA Environmental Requirements • Compatible With Nearby Land Uses

  11. Feasibility Report • Based on What Has Worked Successfully Before • Public Engagement Strategy Throughout • Roadmap offers MOA Offramps and opportunities to reaffirm support for program

  12. TASK 1 Public Engagement • Need to Create a Meaningful Program • Engage a Consultant • Part of All Project Efforts

  13. TASK 2 Project Team • Draft Position Description for Program Manager • Advertise • Interview and Hire • Work Hard!

  14. TASK 3 Waste Composition Analysis Need to Know Btu Value and Composition of Fuel

  15. TASK 4 Waste Flow Negotiations • Impacts Plant Sizing • Economies of Scale • Wasteshed Study • Standard Agreement

  16. TASK 5 Energy Contract Negotiations • Waste Disposal Is Paramount But Energy Sales Defers Costs • Need for Power and Renewable • Power Purchase Agreement MOU • Chugach Electric or Other Utility Dependent on Site • Pricing Issues • State Regulatory Approval

  17. TASK 6 Siting Analysis Data collection, Develop site Prepare analysis and evaluation constraint maps mapping criteria • Comparison of Feasibility Sites • Landfill • Central Transfer Station Preliminary Identifying Evaluating and screening and potential site • Asplund Wastewater Plant selecting site areas areas candidate sites • Southcentral Power Plant • Others • Fatal Flaw Analysis • Public Engagement Site selection

  18. TASK 7 Conceptual Design • Plant Layout • Site Plan • Grading and Drainage Plan • Feeds Into Specs for Procurement Document

  19. TASK 8 Air Permitting • Approvals By ADEC • Establish Monitoring Station • Modelling • Stack Height • Application • Public Engagement • Permitting Process

  20. TASK 9 Local Permitting • Conditional Use Permit • Pre-Application • Community Meeting • Application • Planning and Zoning

  21. TASK 10 Procurement Package • Design, Build, Operate • MOA’s Front-End Documents • Specifications and MOA Needs/Desires • Contracts • Selection Process • Negotiation • Assembly Approval

  22. TASK 11 Financing • $350 to $400 Million Bonds • Preliminary Financial Plan • Short Term Debt • Long Term Bonds • Debt Paid By Revenues of System

  23. Project Schedule 3 Years+ Dependent on Air Permitting Public and Assembly Regulatory Process Critical Path Engagement

  24. Schedule

  25. WTE Project Budget

  26. Project Milestone Actions By Assembly Milestone Review Approval (Off Ramp) Public Engagement X X Waste Flow Negotiations X X Energy Contract Negotiations X X Siting Analysis X X Conceptual Design X X Air Permitting X X Local Permitting X X Project Team X X Procurement Package X X Financing Plan X X

  27. PART 3 Next Steps Mark Spafford Department of Solid Waste Services | March 12, 2020

  28. Next Steps • SWS took this effort as far as we can in 2020 with existing budget • Update Long Range Financial Plan • Complete Business Case Evaluation of landfill/recycling/WTE options • Come back to assembly July/August with this information in hand to make decision on continuing to investigate WTE, etc. • Submit FY2021 Budget for approval

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend