preparations for itaac
play

Preparations for ITAAC - Vogtle 3&4 Experience Chuck Pierce - PowerPoint PPT Presentation

Preparations for ITAAC - Vogtle 3&4 Experience Chuck Pierce Southern Nuclear Operating Company Nuclear Development Licensing Manager August 30, 2011 Preparations for ITAAC Closure Constructive public interactions with NRC


  1. Preparations for ITAAC - Vogtle 3&4 Experience Chuck Pierce Southern Nuclear Operating Company Nuclear Development Licensing Manager August 30, 2011

  2. Preparations for ITAAC Closure • Constructive public interactions with NRC (SECY-11-0111) – NRC Construction Inspection Program – NRC Region II – Simulated ITAAC Closure and Verification Demonstration sponsored by DOE • ITAAC closure process development and oversight – Contractor interactions and oversight – Ongoing development of process 8/30/2011 2

  3. Early Construction Experience • LWA value – Limited scope construction program development – Early exercise of ITAAC process • Contractual alignment – Licensee is Responsible – Licensee oversight 8/30/2011 3

  4. Vogtle 3 and 4 Status • ITAAC Underway – RPV charpy – Type tests – Backfill shear wave velocity – Waterproof membrane • First ITAAC Closure Notification submittal soon 8/30/2011 4

  5. ITAAC Process – The Challenge Ahead 700 225 Day Letter Estimated ITAAC 600 Closures Schedule 500 Unit 3 ITAAC Closures 400 Unit 4 ITAAC 300 Closures 200 Combined 3 & 4 Closures 100 0 2010 2011 2012 2013 2014 2015 2016 2017 8/30/2011 5

  6. ITAAC Process – The Challenge Ahead ITAAC Type Assessment ~806 AP1000 ITAAC ~63 Site Specific ITAAC 48 63 127 Engineering Analysis Components 301 Construction Type Test Pre-Operational Tests Site Specific 330 8/30/2011 6

  7. ITAAC Process – The Challenge Ahead • 20% of ITAAC have higher levels of complexity Design Commitment Inspections, Tests, Acceptance Criteria or Analyses The Class 1E equipment Type tests, analyses, or a A report exists and concludes that identified in Table 2.1.2-1 combination of type tests the Class 1E equipment identified as being qualified for a and analyses will be in Table 2.1.2-1 as being qualified harsh environment can performed on Class 1E for a harsh environment …. withstand the equipment located in a environmental conditions harsh environment. that would exist before, during, and following a design basis accident …. 8/30/2011 7

  8. ITAAC Process – Recent Lessons Learned • Waterproof membrane ITAAC Design Commitment Inspections, Tests, Acceptance Criteria Analyses The friction coefficient to Testing will be A report exists and documents resist sliding is 0.7 or performed to confirm that the as-built waterproof higher that the mudmat- system (mudmat-waterproofing- waterproof-mudmat mudmat interface) has a interface beneath the minimum coefficient of friction Nuclear Island basemat of 0.7 as demonstrated through has a minimum material qualification testing. coefficient of friction to resist sliding of 0.7 8/30/2011 8

  9. 9 Mudmat Cross Section

  10. Moving Forward • Major area of focus between industry and NRC • Progress continues to be made – Closure process maturing – Maintenance process developing • Future demonstration projects may be appropriate to obtain greater clarity • ITAAC lead plant approach for standard plant inspections 8/30/2011 10

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend