piner er s stad adium f fiel eld lights
play

Piner er S Stad adium F Fiel eld Lights Project Status Update - PowerPoint PPT Presentation

Piner er S Stad adium F Fiel eld Lights Project Status Update Backgr kgrou ound This project consists of: Stadium Lighting PA system and speakers Sound wall Required by Environmental Impact Report (EIR) Site


  1. Piner er S Stad adium F Fiel eld Lights Project Status Update

  2. Backgr kgrou ound  This project consists of:  Stadium Lighting  PA system and speakers  Sound wall – Required by Environmental Impact Report (EIR)  Site improvements:  Site Paving (ADA Requirements) and Landscaping  The project is partially Owner Furnished-Contractor Installed, which means that the District will direct purchase the lighting and appurtenant equipment and a contractor will install it.  The balance of the work; site work and landscaping, PA/speaker system and concrete sound wall will be included in the bidding contractor’s scope of work.

  3. Statu tus a s as of 5/ 5/10 10/1 /17  The Musco Lighting for this project was board approved.  The construction documents are 80% complete.  DSA submission scheduled for May 24, 2017  Tentative date range for DSA approval is July 12 – August 16.  Bidding schedule is as follows; ◦ 1 st Advertisement June 6 ◦ 2 nd Advertisement June 13 ◦ Pre-Bid Job Walk June 15 ◦ Contractor Q&A/Addenda June 15 – 20 ◦ Bids Due June 27

  4. Lightin ing (Example le)

  5. Pre reca cast st C Concrete Fe Fence  Required by Environmental Impact Report  Used to deflect sound from neighborhood homes  Average wall height 12’  Meets California Environmental Quality Act BASE SCOPE: 10-13 FT HIGH FENCE LOCATION (CEQA) requirements ADJACENT TO TRACK & FOOTBALL FIELD

  6. Prec ecas ast C Concrete F e Fence ( e (Exam ample) e) Samples – For Illustrative Purposes

  7. Mileston ones es Completion of Construction Documents May 23 DSA Submission May 24 Bidding Process June 6 – 22 Estimated DSA Approval July 12 – August 16 Board Approval for Contract Award TBD after DSA Approval Construction Timeframe 2-3 Months

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend