PENNDOT PROJECT INFORMATION U.S. 30 / Lincoln Highway Culvert - - PowerPoint PPT Presentation

penndot project information
SMART_READER_LITE
LIVE PREVIEW

PENNDOT PROJECT INFORMATION U.S. 30 / Lincoln Highway Culvert - - PowerPoint PPT Presentation

PENNDOT PROJECT INFORMATION U.S. 30 / Lincoln Highway Culvert Replacement SR 0030 Section B22 Independence Township, Beaver County Please complete the survey at the end of the presentation. PROJECT TEAM Design Division Direct questions


slide-1
SLIDE 1

PENNDOT PROJECT INFORMATION

U.S. 30 / Lincoln Highway Culvert Replacement

SR 0030 Section B22 Independence Township, Beaver County

Please complete the survey at the end of the presentation.

slide-2
SLIDE 2

PROJECT TEAM

Design Division

Direct questions to:

Thomas Wilkinson - Project Manager at 412.429.4913

  • r twilkinson@pa.gov

Mark Young- District Environmental Manager

Tyler Mercer, P.E. - Assistant District Environmental Manager

Press Office

Steve Cowan-District Press Officer

slide-3
SLIDE 3

PURPOSE OF PRESENTATION & PROJECT INTRODUCTION

SR 0030, Section B22 (Lincoln Highway) Project

The purpose of this PowerPoint presentation is to introduce the project to the public, gather feedback, and present the detour information.

The purpose of the project is to maintain a safe and reliable crossing for U.S. 30 over a branch of Raccoon Creek in Independence Township, Beaver County.

Full replacement of the existing reinforced concrete arch culvert and reconstruction of immediate roadway and embankments.

slide-4
SLIDE 4

PROJECT LOCATION

slide-5
SLIDE 5

PROPOSED PROJECT IMPROVEMENTS

Culvert replacement

Current culvert is a reinforced concrete arch culvert constructed in 1930

Replacement will be a reinforced concrete box culvert

Project will be built under a full detour

Detour will be in place for one weekend extending up to four days

Guiderail will be updated across the structure and on both approach roadways

Minor Right-of-Way involvement, including mostly Temporary Construction Easements

Construction anticipated in summer of 2019

Example of a concrete box culvert

slide-6
SLIDE 6

NATIONAL ENVIRONMENTAL POLICY ACT (NEPA)

Public outreach begins with the NEPA (National Environmental Policy Act) process.

NEPA requires agencies to integrate environmental values into their decision-making processes by considering the environmental impacts of their proposed actions and reasonable alternatives to those actions.

As a part of NEPA, the Section 106 Process seeks to accommodate historic preservation concerns by identifying historic properties potentially affected by the project, assess the effects and seek ways to avoid, minimize,

  • r mitigate any adverse effects on historic properties.

NEPA also includes public involvement activities and gathering feedback from the public

Image courtesy of MDOT

slide-7
SLIDE 7

Detour Route

slide-8
SLIDE 8

SURVEY

Please click HERE to fill survey