penndot project information
play

PENNDOT PROJECT INFORMATION South Arch Street Bridge Replacement - PowerPoint PPT Presentation

PENNDOT PROJECT INFORMATION South Arch Street Bridge Replacement SR 1037, Section B10 City of Connellsville, Fayette County PROJECT TEAM Design Division Direct questions to: Brian C. Svesnik - Project Manager at 724.415.2400


  1. PENNDOT PROJECT INFORMATION South Arch Street Bridge Replacement SR 1037, Section B10 City of Connellsville, Fayette County

  2. PROJECT TEAM Design Division  Direct questions to:  Brian C. Svesnik - Project Manager at 724.415.2400  Engineering District 12-0 | Project Delivery Unit, 825 N. Gallatin Avenue | Uniontown, PA 15401 or bsvesnik@pa.gov. Cristin Covert - District Environmental Manager  District Officials  Jay Ofsanik - Safety Press Officer  Valerie Petersen - Community Relations Coordinator  Please complete survey at end of presentation

  3. PURPOSE OF PRESENTATION & PROJECT INTRODUCTION SR 1037, Section B10 (South Arch Street) Bridge Project  The purpose of this presentation is to introduce the  project to the public, gather feedback, and present the traffic impacts that will occur during construction. The purpose of this project is to maintain a safe and  reliable crossing for vehicular and pedestrian traffic at South Arch Street over Trump Run in the City of Connellsville.

  4. PROJECT LOCATION Project Location

  5. PROPOSED PROJECT IMPROVEMENTS Bridge Replacement Project  Existing Structure is a single-span supported by concrete  encased steel beams. Scope of work includes replacement of superstructure  and abutments with a precast concrete box culvert, rock lining streambank protection, drainage improvements, approach roadway pavement resurfacing between points 115 feet south and 115 feet north of the new structure, sidewalk reconstruction, and guide rail replacement. Project will be built utilizing a full detour for vehicular  and pedestrian traffic.

  6. PROPOSED PROJECT IMPROVEMENTS Bridge Replacement Project (Cont’d)  Right-of-Way will be acquired at upstream and downstream  sides of South Arch Street for culvert construction and other related work. Additionally, channel easements will be required for rock lining placement in the stream channel, and temporary construction easements will be required to accommodate construction activities. Underground utilities will likely need relocation to allow  for excavation for culvert installation. Utilities affected include Columbia Gas of Pennsylvania, Pennsylvania American Water, and Connellsville Municipal Authority (sanitary). Construction anticipated to begin the summer of 2022. 

  7. PROPOSED TRAFFIC CONTROL Traffic Control Plan  Project Location During construction of the bridge replacement and  roadway work, vehicular traffic on South Arch Street (SR 1037) will be detoured via West Cedar Avenue, South Pittsburgh Street (SR 1037), and West Woodlawn Connellsville Area Draybella Salon School Stadium Ave. The detour route length is just under one (1) mile (0.9 miles) from closure point to closure point. Pedestrians will be expected to use these same roads, but total detour length is 1.1 miles. Local Traffic Access  Access to Connellsville Area School Stadium, Draybella  Salon, Rocky’s Auto Services and residences along South Arch Street will be provided at all times, from the south via South Arch Street and West Woodlawn Avenue.

  8. SOUTH ARCH STREET (SR 1037) VEHICLE DETOUR PLAN SR 1037 Detour Route Detour Length – 0.9 miles Traffic Flow

  9. SOUTH ARCH STREET (SR 1037) PEDESTRIAN DETOUR PLAN SR 1037 Detour Route Detour Length – 1.1 miles Traffic Flow

  10. NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) Public outreach begins with PennDOT Connects and extends into the NEPA (National Environmental Policy Act) process: NEPA requires agencies to integrate  environmental values into their decision-making processes by considering the environmental impacts of their proposed actions and reasonable alternatives to those actions NEPA also includes public involvement  activities and gathering feedback from the public Image courtesy of MDOT

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend