Northumberland Reconstruction Project SR 147, Sec 110 & SR 11, Sec 113 Northumberland Borough Northumberland County ~ PennDOT District 3-0 February 13, 2019 Agenda Purpose and Need of Project Ted Deptula, P.E., PennDOT


slide-1
SLIDE 1

February 13, 2019

Northumberland Reconstruction Project

SR 147, Sec 110 & SR 11, Sec 113

Northumberland Borough Northumberland County ~ PennDOT District 3-0

slide-2
SLIDE 2

Agenda

  • Purpose and Need of Project

– Ted Deptula, P.E., PennDOT Assistant Construction Engineer

  • Construction 2018 Review
  • 2019 Construction and Detours

– Joe Whitcomb, New Enterprise Project Manager – Mindy Foresman, PennDOT Project Manager

  • Conclusion

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

2

slide-3
SLIDE 3

Why Now?

3

slide-4
SLIDE 4

Why Now?

4

slide-5
SLIDE 5

Project Scope of Work

  • Roadway Reconstruction
  • Drainage
  • ADA Ramps, Curb, & Sidewalk
  • Intersection Improvements
  • Utilities

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

5

slide-6
SLIDE 6

Northumberland Reconstruction Project

  • Construction Status

– Work started June 5, 2017 – Contractor = New Enterprise Stone and Lime Co., Inc. – Cost = $14 M – Contract completion date is Summer 2020

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

6

slide-7
SLIDE 7

11

Project Limits & Schedule

  • 2017 Construction

– Phase 1-3

  • Duke Street
  • 2018 Construction

– Phase 4-9

  • Duke Street

– Phase 14 & 15

  • Front Street
  • 2019 Construction

– Phase 10 – 13

  • Water Street
  • King Street
  • 2020 Construction

– Clean up

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

LOCATION MAP

7

slide-8
SLIDE 8

Traffic Phasing

  • Maintain access to businesses and residents
  • Maintain bicycle/pedestrian traffic
  • Pineknotter Days – Week of July 4th each year
  • Detour traffic using borough streets
  • Restrict non-local truck traffic (>36’)

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

8

slide-9
SLIDE 9

No Parking Area During Detour

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

9

No Parking Areas

Existing Condition Proposed Detour Condition

Parking Lane Travel Lane

LEGEND

Travel Lane

slide-10
SLIDE 10

Existing Condition Proposed Detour Condition

Local Detour Condition

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

10

King, Queen and Orange Streets

slide-11
SLIDE 11

2018 Review

  • Duke Street Reconstructed

– 5th Street to Front Street

  • Utilities

– Duke, Front and Water Streets

  • Temporary Wearing Course
  • Car and Truck Detours
  • Front Street Reconstructed

11

slide-12
SLIDE 12

2Roadway 2012Reconstruction Completed 2017

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

Completed Roadway Work Area

LEGEND

12

2018 Completed Work

TO SUNBURY PA 147 P A 1 4 7 T O M I L T O N

slide-13
SLIDE 13

PROJECT LOCATION

COLUMBIA WEST MILTON WINFIELD MILTON NEW LEWISBURG NORTHUMBERLAND MONTANDON

Truck Detour & Alternate Routes SR 147

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

Work Area Detour (SR 147)

LEGEND

13

Truck Detour

slide-14
SLIDE 14

2019 Construction Season

Joe Whitcomb, New Enterprise Project Manager Mindy Foresman, PennDOT Project Manager

  • Scope

– Duke Street, Front Street to Water Street – Water Street, King Street to Rail Road Underpass – Front Street, Old Danville Hwy to Wallace Avenue – Traffic signals, King & Water, Duke & Water

  • Work shifts
  • Detours

14

slide-15
SLIDE 15

15

2019 Roadway Reconstruction Phasing

TO SUNBURY PA 147

slide-16
SLIDE 16

Roadway Reconstruction Traffic Control Plan Pink Phase

ROADWAY WORK

LEGEND

DETOUR SOUTH CLOSED

16

Duke Street Project

X

TEMPORARY TRAFFIC SIGNAL X S R 1 1 N B C L O S E D O P E N S R 1 1 S B X

X

DETOUR NORTH

slide-17
SLIDE 17

Roadway Reconstruction Traffic Control Plan Blue Phase

17

Duke Street Project

OPEN SR 11 SB X X SR 11 NB CLOSED X PA 147 TO SUNBURY PA 147 TO MILTON TEMPORARY TRAFFIC SIGNAL

WORK AREA DETOUR SOUTH

LEGEND

CLOSED DETOUR NORTH

X X

slide-18
SLIDE 18

Roadway Reconstruction Traffic Control Plan Green Phase

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

18

Duke Street Project

P A 1 4 7 T O S U N B U R Y SR 11 SB CLOSED TO X SR 11 SB TO SR 147 SB X SR 147 SB SR 147 NB OPEN

WORK AREA NB DETOUR SOUTH

LEGEND

CLOSED WORK AREA SB

X

slide-19
SLIDE 19

X X X X X X X X S R 1 1 N B O P E N D A M PA 147 TO SUNBURY TEMPORARY TRAFFIC SIGNAL P A 1 1 T O S H A M O K I N TEMPORARY TRAFFIC SIGNAL

Roadway Reconstruction Traffic Control Plan Purple Phase

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

CLOSED

LEGEND

DETOUR NORTH & SOUTH WORK AREA

19

Duke Street Project

X

slide-20
SLIDE 20

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

20

Roadway Reconstruction Traffic Control Plan Orange Phase

CLOSED

LEGEND

DETOUR NORTH & SOUTH WORK AREA

X X

Duke Street Project

DAM PA 147 TO SUNBURY TEMPORARY TRAFFIC SIGNAL PA 11 TO SHAMOKIN TEMPORARY TRAFFIC SIGNAL X X X SR 11 NB OPEN

slide-21
SLIDE 21

Railroad Underpass Reconstruction

  • Contractor: Kriger Construction, Inc.

– Southbound lane completed – Northbound lane under construction

  • Bridge repairs
  • Remove sidewalk
  • Reconstruct concrete pavement
  • Mill and overlay between river bridge and concrete

pavement

– Complete before Pineknotter Days

21

slide-22
SLIDE 22

Northumberland Reconstruction Project

  • Conclusion

– Duke Street, Front Street, Water Street & King Street – 2019

  • Water Street and King Street
  • Railroad Underpass
  • Front Street completion

– 2020

  • Final Paving and Project completion

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

22

slide-23
SLIDE 23

Northumberland Reconstruction Project

  • Communication

– Website: www.penndot.gov/dukestreet – E-mail: DukeStreet@pa.gov – 24-Hour Hotline: 855-336-8698 – Community Roundtables

SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County

23

slide-24
SLIDE 24

NORTHUMBERLAND RECONSTRUCTION PROJECT

www.penndot.gov/dukestreet SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County