Northumberland Reconstruction Project SR 147, Sec 110 & SR 11, Sec 113 Northumberland Borough Northumberland County ~ PennDOT District 3-0 February 13, 2019 Agenda Purpose and Need of Project Ted Deptula, P.E., PennDOT
Agenda
- Purpose and Need of Project
– Ted Deptula, P.E., PennDOT Assistant Construction Engineer
- Construction 2018 Review
- 2019 Construction and Detours
– Joe Whitcomb, New Enterprise Project Manager – Mindy Foresman, PennDOT Project Manager
- Conclusion
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
2
Why Now?
3
Why Now?
4
Project Scope of Work
- Roadway Reconstruction
- Drainage
- ADA Ramps, Curb, & Sidewalk
- Intersection Improvements
- Utilities
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
5
Northumberland Reconstruction Project
- Construction Status
– Work started June 5, 2017 – Contractor = New Enterprise Stone and Lime Co., Inc. – Cost = $14 M – Contract completion date is Summer 2020
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
6
11
Project Limits & Schedule
- 2017 Construction
– Phase 1-3
- Duke Street
- 2018 Construction
– Phase 4-9
- Duke Street
– Phase 14 & 15
- Front Street
- 2019 Construction
– Phase 10 – 13
- Water Street
- King Street
- 2020 Construction
– Clean up
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
LOCATION MAP
7
Traffic Phasing
- Maintain access to businesses and residents
- Maintain bicycle/pedestrian traffic
- Pineknotter Days – Week of July 4th each year
- Detour traffic using borough streets
- Restrict non-local truck traffic (>36’)
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
8
No Parking Area During Detour
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
9
No Parking Areas
Existing Condition Proposed Detour Condition
Parking Lane Travel Lane
LEGEND
Travel Lane
Existing Condition Proposed Detour Condition
Local Detour Condition
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
10
King, Queen and Orange Streets
2018 Review
- Duke Street Reconstructed
– 5th Street to Front Street
- Utilities
– Duke, Front and Water Streets
- Temporary Wearing Course
- Car and Truck Detours
- Front Street Reconstructed
11
2Roadway 2012Reconstruction Completed 2017
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
Completed Roadway Work Area
LEGEND
12
2018 Completed Work
TO SUNBURY PA 147 P A 1 4 7 T O M I L T O N
PROJECT LOCATION
COLUMBIA WEST MILTON WINFIELD MILTON NEW LEWISBURG NORTHUMBERLAND MONTANDON
Truck Detour & Alternate Routes SR 147
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
Work Area Detour (SR 147)
LEGEND
13
Truck Detour
2019 Construction Season
Joe Whitcomb, New Enterprise Project Manager Mindy Foresman, PennDOT Project Manager
- Scope
– Duke Street, Front Street to Water Street – Water Street, King Street to Rail Road Underpass – Front Street, Old Danville Hwy to Wallace Avenue – Traffic signals, King & Water, Duke & Water
- Work shifts
- Detours
14
15
2019 Roadway Reconstruction Phasing
TO SUNBURY PA 147
Roadway Reconstruction Traffic Control Plan Pink Phase
ROADWAY WORK
LEGEND
DETOUR SOUTH CLOSED
16
Duke Street Project
X
TEMPORARY TRAFFIC SIGNAL X S R 1 1 N B C L O S E D O P E N S R 1 1 S B X
X
DETOUR NORTH
Roadway Reconstruction Traffic Control Plan Blue Phase
17
Duke Street Project
OPEN SR 11 SB X X SR 11 NB CLOSED X PA 147 TO SUNBURY PA 147 TO MILTON TEMPORARY TRAFFIC SIGNAL
WORK AREA DETOUR SOUTH
LEGEND
CLOSED DETOUR NORTH
X X
Roadway Reconstruction Traffic Control Plan Green Phase
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
18
Duke Street Project
P A 1 4 7 T O S U N B U R Y SR 11 SB CLOSED TO X SR 11 SB TO SR 147 SB X SR 147 SB SR 147 NB OPEN
WORK AREA NB DETOUR SOUTH
LEGEND
CLOSED WORK AREA SB
X
X X X X X X X X S R 1 1 N B O P E N D A M PA 147 TO SUNBURY TEMPORARY TRAFFIC SIGNAL P A 1 1 T O S H A M O K I N TEMPORARY TRAFFIC SIGNAL
Roadway Reconstruction Traffic Control Plan Purple Phase
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
CLOSED
LEGEND
DETOUR NORTH & SOUTH WORK AREA
19
Duke Street Project
X
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
20
Roadway Reconstruction Traffic Control Plan Orange Phase
CLOSED
LEGEND
DETOUR NORTH & SOUTH WORK AREA
X X
Duke Street Project
DAM PA 147 TO SUNBURY TEMPORARY TRAFFIC SIGNAL PA 11 TO SHAMOKIN TEMPORARY TRAFFIC SIGNAL X X X SR 11 NB OPEN
Railroad Underpass Reconstruction
- Contractor: Kriger Construction, Inc.
– Southbound lane completed – Northbound lane under construction
- Bridge repairs
- Remove sidewalk
- Reconstruct concrete pavement
- Mill and overlay between river bridge and concrete
pavement
– Complete before Pineknotter Days
21
Northumberland Reconstruction Project
- Conclusion
– Duke Street, Front Street, Water Street & King Street – 2019
- Water Street and King Street
- Railroad Underpass
- Front Street completion
– 2020
- Final Paving and Project completion
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
22
Northumberland Reconstruction Project
- Communication
– Website: www.penndot.gov/dukestreet – E-mail: DukeStreet@pa.gov – 24-Hour Hotline: 855-336-8698 – Community Roundtables
SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County
23
NORTHUMBERLAND RECONSTRUCTION PROJECT
www.penndot.gov/dukestreet SR 147, Sec 110 & SR 11, Sec 113 ~ District 3-0 ~ Northumberland County