peggy ryan williams center
play

Peggy Ryan Williams Center AE Senior Thesis April 14, 2014 Angela - PowerPoint PPT Presentation

Peggy Ryan Williams Center AE Senior Thesis April 14, 2014 Angela Mincemoyer Structural Option Advisor | Dr. Boothby Ithaca, New York Peggy Ryan Williams Center Introduction AE Senior Thesis Proposal April 14, 2014 Structural


  1. Peggy Ryan Williams Center AE Senior Thesis April 14, 2014 Angela Mincemoyer Structural Option Advisor | Dr. Boothby Ithaca, New York

  2. Peggy Ryan Williams Center  Introduction AE Senior Thesis  Proposal April 14, 2014  Structural Depth  Gravity System Angela Mincemoyer  Lateral System Structural Option  Bridge Truss  Architectural Breadth Advisor | Dr. Boothby  Lighting Breadth  Conclusion Ithaca, New York

  3. Peggy Ryan Williams Center  Introduction  Proposal Owner | Ithaca College Architect | Holt Architects  Structural Depth Structural Engineer | Ryan-Biggs Associates  Gravity System  Lateral System 58,200 GSF  Bridge Truss 4 Stories Substantial Completion | March 2010  Architectural Breadth Photo provided courtesy of Holt Architects  Lighting Breadth  Conclusion Introduction

  4. Peggy Ryan Williams Center  Introduction Composite steel floor  Proposal 3” x 20 gauge composite metal deck 6” concrete slab  Structural Depth 48’  Gravity System Wide Flange Beams, girder, columns  Lateral System Irregular Layout  Bridge Truss Geometry, cantilevers  Architectural Breadth  Lighting Breadth  Conclusion Existing Gravity System

  5. Peggy Ryan Williams Center  Introduction  Proposal Concentrically braced structural steel frames North-South  Structural Depth East-West  Gravity System Seismic Design Category A  Lateral System Wind Controlled Design  Bridge Truss  Architectural Breadth  Lighting Breadth  Conclusion Existing Lateral System

  6. Peggy Ryan Williams Center  Introduction  Proposal Pratt Trusses  Structural Depth HSS  Gravity System 3.5” pipe  Lateral System Double Cantilever  Bridge Truss  Architectural Breadth  Lighting Breadth  Conclusion Existing Bridge System

  7. Peggy Ryan Williams Center Scenario | Project Schedule is no longer critical Scenario | Learning opportunity  Introduction  Proposal Proposal | One way concrete slab system with Proposal | Two different redesign options will pan joists and girders be considered  Structural Depth  Beneficial for cantilevers  Reflection of New York’s  Gravity System historic covered bridges  Accommodates varying spans  Lateral System  Reflect on original name of & geometries  Bridge Truss the building  Thinner slab  Architectural Breadth (“The Gateway Building”)  Minimize architectural impact  Lighting Breadth  Conclusion Building Bridge

  8. Peggy Ryan Williams Center Scenario | Project Schedule is no longer critical Scenario | Learning opportunity  Introduction  Proposal Proposal | One way concrete slab system with Proposal | Two different redesign options will pan joists and girders be considered  Structural Depth  Beneficial for cantilevers  Reflection of New York’s  Gravity System historic covered bridges  Accommodates varying spans  Lateral System  Reflect on original name of & geometries  Bridge Truss the building  Thinner slab  Architectural Breadth (“The Gateway Building”)  Minimize architectural impact  Lighting Breadth  Conclusion Building Bridge

  9. Peggy Ryan Williams Center Proposal| One way concrete slab system with Proposal| Two different redesign options will  Introduction pan joists and girders be considered  Proposal Goals| Design a one way concrete slab system Goals| After considering two redesign options:  Structural Depth  Determine which option to while:  Gravity System move forward with  Minimizing floor system depth  Lateral System  Design one side truss of the  Minimizing architectural impact  Bridge Truss bridge  Architectural Breadth  Lighting Breadth  Conclusion Building Bridge

  10. Peggy Ryan Williams Center Proposal| One way concrete slab system with Proposal| Two different redesign options will  Introduction pan joists and girders be considered  Proposal Goals| Design a one way concrete slab system Goals| After considering two redesign options:  Structural Depth  Determine which option to while:  Gravity System move forward with  Minimizing floor system depth  Lateral System  Design one side truss of the  Minimizing architectural impact  Bridge Truss bridge  Architectural Breadth  Lighting Breadth  Conclusion Building Bridge

  11. Peggy Ryan Williams Center  Introduction  CRSI Manual  Proposal  Same joist size and spacing used throughout  Structural Depth  2 worst case spans considered  Gravity System  30” forms with 6” rib @ 36” o.c.  Lateral System  20” rib depth + 4.5” slab = 24.5” system depth  Bridge Truss  f ’c = 4,000 psi  Architectural Breadth  fy = 60 ksi  Lighting Breadth  Conclusion Pan Joist System

  12.  8 Designed members indicated Peggy Ryan Williams Center D  Chosen due to: Long spans,  Introduction large tributary widths, high loadings  Proposal  Designed using spBeam  Strength requirements 2  Structural Depth  Deflections checked per ACI 318-11  Gravity System Table 9.5b 13  Lateral System  Bridge Truss  Architectural Breadth  Lighting Breadth Column Line D Column Line 2 Column Line 13 Column Line 8  Conclusion Framing Plan Girders/Beams

  13. Peggy Ryan Williams Center  Designed using spColumn  Introduction  Both axial loads from above & moments were  Proposal applied  Structural Depth  Square section chosen  Gravity System  Ease of construction  Lateral System  Aid in future lateral system design  Bridge Truss  All column sizes were increased to  Architectural Breadth 18”x 18” for constructability  Lighting Breadth  Conclusion Columns

  14. Peggy Ryan Williams Center  Introduction  Proposal  Columns & girders were removed from  Structural Depth original design  Gravity System  Floor system depth decreased by 5- 5/8”  Lateral System  Larger floor-to-ceiling height  Bridge Truss  Architectural Breadth  Lighting Breadth  Conclusion Summary Existing Redesign

  15. Peggy Ryan Williams Center  Current lateral system  Introduction  Concentrically braced structural steel frames  Proposal  No longer the best option  Structural Depth  Gravity system may double as the lateral system  Gravity System  Concrete moment frames in North-South and  Lateral System East-West directions  Bridge Truss  4 concrete moment frames were considered in  Architectural Breadth each direction  Lighting Breadth  Conclusion Lateral System Introduction

  16. Peggy Ryan Williams Center  Both wind and seismic forces were calculated per ASCE7-10  Introduction  Wind controlled  Proposal  Using spColumn , 18”x18” columns were  Structural Depth designed  Gravity System  Biaxial bending was considered  Lateral System  Worst case girder and joist were checked for  Bridge Truss beam-column interaction  Architectural Breadth  Found to be adequate  Lighting Breadth  Conclusion Lateral System Analysis

  17. Peggy Ryan Williams Center  Introduction  Analysis was done using 4 frames in both  Proposal directions  Structural Depth  By adding frames the system will surely be  Gravity System adequate   Lateral System The gravity system of the building doubles as the lateral system  Bridge Truss  Architectural Breadth  Lighting Breadth  Conclusion Summary

  18. Peggy Ryan Williams Center  Introduction  Sketches were produced to determine which  Proposal inspiration would be used in the redesign  Structural Depth  The covered bridge option was chosen  Gravity System  Box truss design  Lateral System  Move supports out to open up the space  Bridge Truss  Warren Truss  Architectural Breadth  Lighting Breadth  Conclusion Bridge Introduction

  19. Peggy Ryan Williams Center  Introduction  Only gravity loads were considered for the side  Proposal trusses  Structural Depth  Panel point loads were determined based on layout  Gravity System   Lateral System Controlling Load Combinations:   Bridge Truss 1.2 D + 1.6 L + 0.5 S   Architectural Breadth 1.2 D + 1.6 S + L  Lighting Breadth  Conclusion Loads

  20. Peggy Ryan Williams Center 1.2 D + 1.6 L + 0.5 S  Indexing Method  Introduction  Loading all panel points  Proposal  Produced worst case force in top chord,  Structural Depth bottom chord, and far left diagonal  Gravity System  Use of geometry to determine member forces  Lateral System  Method of Joints to verify Indexing Method  Bridge Truss forces   Architectural Breadth Indexing Method is an accurate method of analysis  Lighting Breadth  Conclusion Member Force Determination

  21. Peggy Ryan Williams Center  Introduction  Proposal  Steel Manual Tables  Structural Depth  Table 4-4 for top chord and diagonal  Gravity System compression members  Lateral System  Table 5-5 for bottom chord tension member Top Chord: HSS7x7x¼  Bridge Truss Bottom Chord: HSS7x7x¼  Architectural Breadth Diagonals: HSS4x4x½  Lighting Breadth  Conclusion Member Design

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend