Northwest Wichita Water Facility (NWWF)
Public Works & Utilities November 19, 2019
Oversight Steering Committee Public Works & Utilities November - - PowerPoint PPT Presentation
Northwest Wichita Water Facility (NWWF) Oversight Steering Committee Public Works & Utilities November 19, 2019 GMP R EVIEW 2 WWP submitted $494.2m Guaranteed Maximum Price (GMP) on October 28 for final design and construction
Public Works & Utilities November 19, 2019
2
Design
Report
Drawings Contract
Assignment Unit Costs
Suppliers
Subcontractors
construction
3
proposal from 10/11 has been refined and accepted
utilizing existing asset
town wells to the NWF
water pipeline in an emergency
4
5
and Wichita Water Partners
needs for redundancy and water quality
6
$1,074.72 $1,023.00 $973.99 $926.20 $880.99 $1,325.99 $1,203.35 $1,087.08 $983.48 $891.09 2024 2023 2022 2021 2020
AVERAGE ANNUAL RESIDENTIAL BILL
Without WIFIA/SRF With WIFIA/SRF Construction Inflation $6,000,000 Risk-Based Contingency $25,000,000 Other Market Impacts $3,000,000
COST INCREASE POTENTIAL
7
inspection
8
$6 $494 $10 $2 $21 $10 $12 $2 $44 $1 $0 $100 $200 $300 $400 $500 $600
Phase 1 Design Phase 2 Design & Construction Evergy Substation Power Distribution Owner's Representative Additional Sites Hess Improvements ROW & Site Improvements Capitalized Interest Misc Fees
Millions
construct the plant, pipelines, and power
CORE PROJECT OTHER ELIGIBLE ITEMS FEES
9
0% 2% 4% 6% 8% 10% 12% 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 Current Projection National Average No WIFIA/SRLF for NWWF Last Year's Projection
10
$494.2 million
power substation, and pipelines is $14.1 million under the budget
that can operate with any single asset out
water source flexibility, and 120 MGD capacity
submitted on time
to begin in January
commissioning begins March 2024
UNDER BUDGET ON SCOPE ON TIME
11
Recommendations
following package: Phase 2 amendment for Wichita Water Partners to build the NWWF Phase 2 contract with Garver for Owner’s Representation 2020 combined utility rate increase of 5.0% SRF application submittal
Phase 2 amendment Garver Engineering
recommend to the City Council? Upcoming Actions
amendment and public hearing on Dec. 3rd