Northwest Wichita Water Facility (NWWF) Oversight Steering Committee Public Works & Utilities November 19, 2019 GMP R EVIEW 2 WWP submitted $494.2m Guaranteed Maximum Price (GMP) on October 28 for final design and construction


  1. Northwest Wichita Water Facility (NWWF) Oversight Steering Committee Public Works & Utilities November 19, 2019

  2. GMP R EVIEW 2  WWP submitted $494.2m Guaranteed Maximum Price (GMP) on October 28 for final design and construction  City staff & Owner’s Representative have since reviewed the submittal Design Contract Unit Costs • Basis of Design • GMP Scope • Pricing from Report Suppliers • Negotiated Risk • 30% Engineering Assignment • Pricing from Drawings Subcontractors

  3. GMP R EVIEW 3  WWP value engineering proposal from 10/11 has been refined and accepted  Dual-purpose functionality utilizing existing asset  Delivers raw water from in- town wells to the NWF Acts as redundant drinking  water pipeline in an emergency Reduced cost by $14 million 

  4. 4 PHASE 2 STAFF RECOMMENDATIONS

  5. W ICHITA W ATER P ARTNERS 5  Competitive price that’s under budget and meets all requirements  Locks the City into a lower risk position and minimized contingency  Protection against future cost escalation  More certainty of WIFIA/SRF financing by proceeding with Phase 2 and Wichita Water Partners  Highly qualified team with a contractual obligation to meet the City’s needs for redundancy and water quality

  6. W ICHITA W ATER P ARTNERS 6 AVERAGE ANNUAL RESIDENTIAL BILL COST INCREASE POTENTIAL Without WIFIA/SRF With WIFIA/SRF $891.09 2020 $880.99 Other Market $983.48 Impacts 2021 $3,000,000 $926.20 Risk-Based $1,087.08 Contingency 2022 $973.99 $25,000,000 Construction Inflation $1,203.35 $6,000,000 2023 $1,023.00 $1,325.99 2024 $1,074.72

  7. G ARVER E NGINEERING 7  Scope revised to match construction workloads  2020 responsibilities would primarily be focused on design reviews  Future work would be centered on construction management and inspection  Likely to need multiple personnel on site monitoring construction  Would be supported by a diverse set of technical experts

  8. WIFIA E LIGIBLE C OSTS 8  WIFIA application inclusive of all eligible expenses, not just core project costs to design and construct the plant, pipelines, and power  Maximizes WIFIA benefits; all costs included in previous rate projections $600 CORE PROJECT OTHER ELIGIBLE ITEMS FEES $500 $494 $400 Millions $300 $200 $100 $44 $21 $10 $12 $10 $6 $2 $2 $1 $0 Phase 1 Phase 2 Evergy Power Owner's Additional Hess ROW & Site Capitalized Misc Fees Design Design & Substation Distribution Representative Sites Improvements Improvements Interest Construction

  9. C OMBINED R ATE I NCREASES 9 12% 10% 8% 6% 4% 2% 0% 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 Current Projection National Average No WIFIA/SRLF for NWWF Last Year's Projection

  10. O UTCOMES 10    UNDER BUDGET ON SCOPE ON TIME  Fully redundant plant  Final Phase 2 price is  WIFIA application that can operate with $494.2 million submitted on time any single asset out of service  Total cost for plant,  Early works package power substation, to begin in January  High water quality, and pipelines is water source $14.1 million under  Startup and flexibility, and 120 commissioning the budget MGD capacity begins March 2024

  11. P ATH F ORWARD 11 Recommendations Upcoming Actions  November 26 th City Council Workshop  City staff recommends approval of the following package:  December 3 rd City Council Meeting  Phase 2 amendment for Wichita Water  Phase 2 with WWP to construct the NWWF Partners to build the NWWF  Phase 2 with Garver  Phase 2 contract with Garver for Owner’s  SRF application Representation  2020 rates  2020 combined utility rate increase of 5.0%  SRF application submittal  December 17 th SRF Application  Submit to state following approval of Phase 2  Owner’s Representative recommends amendment and public hearing on Dec. 3 rd Phase 2 amendment  Jan – Oct 2020: Early Works Package  Garver Engineering  Design completion & site preparation What path does the Steering Committee   Sept. 17, 2024: Substantial Completion recommend to the City Council?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.