Steering Committee Meeting #2 July 26, 2011 Steering Committee - - PDF document

steering committee meeting 2 july 26 2011
SMART_READER_LITE
LIVE PREVIEW

Steering Committee Meeting #2 July 26, 2011 Steering Committee - - PDF document

Steering Committee Meeting #2 July 26, 2011 Steering Committee Attendees City of Missouri City - Valerie Marvin, Jessica Kelley, Sharon Valiante, Dwayne Williams, Jaime Ponce de Leon TxDOT - Manny Francisco Houston-Galveston Area Council -


slide-1
SLIDE 1

Steering Committee Meeting #2 July 26, 2011

1 | P a g e

Steering Committee Attendees

City of Missouri City - Valerie Marvin, Jessica Kelley, Sharon Valiante, Dwayne Williams, Jaime Ponce de Leon TxDOT - Manny Francisco Houston-Galveston Area Council - Christy Willhite, Roland Strobel, Cristin Emshoff, Bill Tobin

Project Team Attendees

Gunda Corporation - Ramesh Gunda, Megh Govindu, Lori Grubbs Kendig Keast Collaborative - Greg Flisram, Liz Probost The Lentz Group - Nicole Gilbert Parsons Brinckerhoff - Kevin Mineo, Russell Smart

Project Description

The Houston-Galveston Area Council (H-GAC) is conducting a study regarding transportation improvements to the section of FM 1092 (Murphy Road) that runs from Dove Country Road to State Highway 6 in Missouri City. The study is seeking solutions to reduce crashes, improve traffic flow and minimize motorist delay.

Meeting Discussion

Christy Willhite, the H-GAC project manager for the study, welcomed the steering committee members to the meeting and provided a brief overview of the project. The meeting was then turned over to the consultant team. Ramesh Gunda, Gunda Corporation, consultant team project manager, gave a recap of the first meeting including a review of the project scope and boundaries, project goals, data collection, project schedule and public involvement. A copy of the presentation is attached to these minutes. A schedule of the upcoming meetings was also presented. Christy Willhite mentioned that she will present project information to TAC/TPC, and Gunda Corporation will support with presentation slides if needed. The presentation then focused on the analysis of the data collected. Analysis included existing conditions (roadway/pedestrian/bicycle/transit/traffic/crashes /land use/zoning), existing access management practices, planned improvements, crash analysis and traffic simulation analysis. During this portion of the discussion, Sharon Valiante, City of Missouri City, notified the consultant team that there is a new temporary Park and Ride facility in Missouri City, which will be available in September at Fort Bend Parkway/SH 6 (in addition to the existing Park and Ride facility at Fondren Road). Three locations have been identified for a new permanent park and ride facility, but a final location is not yet determined. Valerie Marvin, City of Missouri City, also updated the consultant team that two planned improvements discussed during the presentation, City Wide ITS Improvements and Traffic Management Center, are in progress (90% completed) and should be completed by the end of the year. The timeframe for the TxDOT roadway widening improvements along FM 1092 were discussed. Manny Francisco, TxDOT, will check the status of widening FM 1092 from four to six lanes and from six to eight lanes. The presentation focused on the preliminary findings:

  • Safety in school zones
  • Crash rate higher than Statewide average
  • 5th Street skewed intersection
  • Increase in traffic volumes/congestion
slide-2
SLIDE 2

Steering Committee Meeting #2 July 26, 2011

2 | P a g e

  • Disconnected sidewalk segments
  • Prevent access to main activity areas
  • Corridor width, traffic volumes and vehicular speeds
  • Inhibit cross-corridor pedestrian movement
  • Lack of pedestrian bridges and intersecting sidewalks along the Oyster Creek trail
  • Limits its use as an effective off-street pedestrian route
  • Missing pedestrian features at signalized intersections
  • Only one transit facility
  • Strip center at Cartwright is not operating at full potential
  • Needs to be repositioned as a neighborhood shopping/activity center
  • Vacant tracts

During the presentation, the following preliminary recommendations were made:

  • Raised median, with planned median openings
  • Full access - at street intersection or approximately 1,320 feet
  • Directional access - at approximately 660 feet
  • Curb and gutter with closed storm drainage
  • Roadway widening
  • Signal timing optimization
  • New traffic signals
  • Turn lanes at intersections
  • Re-align 5th Street to eliminate skew
  • Driveway consolidation/relocation
  • Right-turn lanes at major driveways
  • Pedestrian/Bicycle path
  • Pedestrian facilities at both Hampton Road and Dove Country Road intersections
  • Countdown pedestrian facilities at all signalized intersections
  • Connect the west side of the corridor to school property via a pedestrian underpass and bridges
  • Position the creek trail as a main pedestrian spine (or loop)
  • Requires new pedestrian bridges and trail spurs along the south/east creek bank
  • Expand the area trail network and sidewalk system using existing easements and linear features
  • Signature entry feature at the culvert crossing on the north end of the corridor
  • Similar to State Highway 6
  • Transit opportunities
  • Walkable neighborhood center on the west side of the Cartwright Road intersection
  • Access controlled planned neighborhood development on vacant tracts in the mid-corridor

vicinity Greg Flisram, Kendig Keast Collaborative, presented recommendations for land use and walkability

  • ptions.

The Steering Committee and consultant team reviewed the aerial images with the proposed improvements including raised medians and made modifications as needed. Jaime Ponce de Leon, City

  • f Missouri City Fire Department, made notations on the aerials of crossings that would need to have

mountable medians to allow emergency vehicles to cross in the event of an emergency. Areas for potential future median openings based on development were indicated on the map. Valerie asked the consultant team to recommend locations for openings and include them in this study. Manny also preferred to have the recommended locations for median openings in the study.

slide-3
SLIDE 3

Steering Committee Meeting #2 July 26, 2011

3 | P a g e

Other important items discussed while reviewing the aerial images are:

  • Relocating Palm Grove Drive
  • New church (near Quail Valley Church) under construction will not have a driveway
  • Area north of Heritage Baptist Church is wetlands
  • Note recommendations for ADA compliant ramps at intersections
  • Add parcel lines on the aerial images
  • There is a proposal for residential/townhomes development in the vacant land between 5th

Street and Lexington. Missouri City prefers this area to be commercial/industrial.

  • Fire Department will check ladder truck turning radius requirements
  • Mountable median design should consider fire truck requirements because air bags will come
  • n as soon as the trucks hit any big obstruction
  • Review plat for storage unit and apartments (north of 5th Street and west of FM 1092) to check

for any existing cross access

  • Add driveway on the aerial for the new Subway

Discussion of proposed improvements included where to end the median recommendations at the north project limits – Missouri City limits, Dove Country Road or Avenue E. The area north of Missouri City limits is Fort Bend County and in Stafford’s ETJ, and Sharon requested that Christy contact Fort Bend County. Christy suggested increasing the cross-streets limits on the aerial images so that alternative access roads are shown. Christy wrapped up the meeting by thanking everyone for coming and providing their input. She notified the committee that revised maps and boards will be sent for review before they are presented at the first public meeting on August 31, 2011.

Next Meetings:

  • Public Meeting #1: August 31, 2011 from 6-8 p.m., Quail Valley Middle School
  • Steering Committee #3: September 13, 2011 from 10–11:30 a.m., City of Missouri City EOC

Training Room

  • Stakeholder Meeting #2: September 13, 2011 from 1–3 p.m., City of Missouri City EOC Training

Room

  • Public Meeting #2: Early November (TBD)
  • Council Meeting – City of Missouri City: November 21, 2011
slide-4
SLIDE 4

1

FM 1092/Murphy Road FM 1092/Murphy Road A M t St d A M t St d Access Management Study Access Management Study Steering Committee Meeting #2 Steering Committee Meeting #2

Tuesday, July 26, 2011 Tuesday, July 26, 2011 10:00 a.m. 10:00 a.m. – – 11:30 a.m. 11:30 a.m.

Introductions Introductions

Agency Partners Agency Partners

  • H-GAC
  • Missouri City
  • TxDOT

FM 1092/Murphy Road Access Management Study

slide-5
SLIDE 5

2

Introductions Introductions

Consulting Team Consulting Team

In Association with :

FM 1092/Murphy Road Access Management Study

CJ Hensch & Associates, Inc. Kendig Keast Collaborative The Lentz Group Parsons Brinckerhoff

Agenda Agenda

Introductions (5 Minutes) ( ) Recap of First Meeting (10 Minutes)

Project Scope and Boundaries Project Goals Data Collection Project Schedule Public Involvement

Analysis (25 Minutes)

Existing Conditions (Roadway/Pedestrian/Bicycle/Transit/Traffic/Land Use/Zoning) Existing Access Management Practices Planned Improvements FM 1092/Murphy Road Access Management Study p Crash Analysis Traffic Simulation Analysis

Preliminary Findings (10 Minutes) Preliminary Recommendations (35 Minutes) Next Steps (5 Minutes)

slide-6
SLIDE 6

3

Project Scope and Boundaries Project Scope and Boundaries

  • Access Management Process

Access Management Process

  • Public/Agency Involvement
  • Assembly and Review of Data
  • Evaluation of Existing Corridor
  • Analysis of Short Term Solutions
  • Long Term Strategies
  • Boundaries

FM 1092/Murphy Road Access Management Study

  • Boundaries
  • FM 1092 from SH 6 to Dove Country Drive
  • Approximately 3 miles

Project Goals Project Goals

  • Safety for all modes of transportation

Safety for all modes of transportation

  • Reduce crashes and conflicts
  • Improve traffic flow
  • Explore bicycle accommodation opportunities
  • Reduce motorist delay
  • Improve quality of life

FM 1092/Murphy Road Access Management Study

slide-7
SLIDE 7

4

Data Collection Data Collection

  • City ordinances

City ordinances

  • Thoroughfare Plans
  • Land Use Plans
  • GIS Layers
  • Planned Improvements
  • Traffic & Crash Data
  • Aerial Photos

FM 1092/Murphy Road Access Management Study

Project Schedule Project Schedule

FM 1092/Murphy Road Access Management Study

slide-8
SLIDE 8

5

Project Schedule (Contd..) Project Schedule (Contd..)

S # f

  • Stakeholder Meeting #1: July 26, 2011 from 1 – 3 p.m.
  • Public Meeting #1: August 31, 2011 from 6 – 8 p.m. (Tentative)
  • Steering Committee #3: September 13, 2011 from 10 – 11:30 a.m.
  • Stakeholder Meeting #2: September 13, 2011 from 1 – 3 p.m.
  • TAC/TPC Presentation: September (TBD)
  • Public Meeting #2: Early November (TBD)
  • Council Meeting – City of Missouri City: November 21, 2011

FM 1092/Murphy Road Access Management Study

Public Involvement Public Involvement

S f G C

  • Submitted draft plan to H-GAC
  • Incorporated H-GAC comments
  • Submitted final plan to H-GAC and City of Missouri City

FM 1092/Murphy Road Access Management Study

slide-9
SLIDE 9

6

Existing Roadway Characteristics Existing Roadway Characteristics

F l i h l

  • Four-lanes with center two-way turn lane
  • Eight feet shoulders and open drainage
  • 125 to 140 feet right-of-way
  • Posted speed limit is 45/50 miles per hour
  • Eight signalized intersections
  • Four span-wire and four mast-arm
  • Video detection
  • Dove Country maintained by TxDOT
  • All others maintained by Missouri City
  • School zone @ Plantation Settlement Lane

FM 1092/Murphy Road Access Management Study

  • School zone @ Plantation Settlement Lane
  • Speed limit is 35 miles per hour when lights are flashing

Existing Roadway Characteristics (Contd..) Existing Roadway Characteristics (Contd..)

From To Distance (Feet) Number of Driveways Driveway Density (Driveways/Mile) West Side East Side West Side East Side S.H. 6 Hampton Dr. 750 2 1 14 7 Hampton Dr. Township Ln. 725 1 1 7 7 Township Ln. Plantation Settlement Ln. 2,000 3 3 8 8 Plantation Settlement Ln. El Dorado Blvd. 1,615 1 3 El Dorado Blvd. Cartwright Rd. 1,115 3 14

FM 1092/Murphy Road Access Management Study

Cartwright Rd. 5 th St. 3,000 8 13 14 23 5th St. Lexington Blvd. 3,660 17 2 25 3 Lexington Blvd. Dove Country Dr. 2,700 12 2 23 4 Total Driveways 46 23

slide-10
SLIDE 10

7

Existing Pedestrian, Bicycle and Transit Existing Pedestrian, Bicycle and Transit Characteristics Characteristics

Si i li d i t ti h d t i f iliti

  • Six signalized intersections have pedestrian facilities
  • No pedestrian facilities at Hampton and Dove Country
  • Eight feet shoulders serve as bike path
  • No continuous sidewalk along FM 1092
  • Sidewalks only at signalized intersections
  • Mosley Park – Oyster Creek trail
  • METRO
  • Missouri City Park and Ride Facility @ 13849 Fondren Road
  • Routes 163 and 170
  • Destination to Houston Downtown and Texas Medical Center

FM 1092/Murphy Road Access Management Study

  • Destination to Houston Downtown and Texas Medical Center

Existing Traffic Characteristics Existing Traffic Characteristics

B d 2009 H t Di t i t RI 2T L

  • Based on 2009 Houston District RI-2T Log
  • 2011 AADT is 29,900
  • 2031 AADT is 51,500
  • Based on Missouri City Traffic Management Plan
  • 2008 AADT is 35,550
  • 2015 AADT is 41,700
  • 2025 AADT is 48,500

FM 1092/Murphy Road Access Management Study

slide-11
SLIDE 11

8

Existing Crash Data Existing Crash Data

Year Number of Crashes Total Injuries Total Fatalities 2008 82 31 2009 85 21 1 2010 116 33 Source: City of Missouri City FM 1092/Murphy Road Access Management Study Source: City of Missouri City

Existing Land Existing Land Use & Use & Zoning Zoning

P i i f h d d ki f iliti

  • Provision for shared access and parking facilities
  • Commercial or industrial (non-residential) tracts
  • Zoning
  • Non-residential (local commercial)
  • Higher-density residential (multi-family)
  • Planned developments
  • Specific use permit

FM 1092/Murphy Road Access Management Study

slide-12
SLIDE 12

9

Existing Access Management Practices Existing Access Management Practices -

  • TxDOT

TxDOT

C ti S i

  • Connection Spacing

Posted Speed Limit (Miles per Hour) Distance (Feet) < 30 200 35 250 40 305 45 360 > 50 425 FM 1092/Murphy Road Access Management Study

  • Median Opening Spacing
  • For street intersections or major developed areas
  • Directional median opening to limit conflicts
  • Left-turn bays at all median openings

Existing Access Management Practices Existing Access Management Practices – – Missouri City Missouri City

C ti S i

  • Connection Spacing
  • Median Opening Spacing

Posted Speed Limit (Miles per Hour) Distance (Feet) 25 150 30 230 35 300 40 350 45 400 50 450 > 50 TIA Required FM 1092/Murphy Road Access Management Study

  • Median Opening Spacing
  • 1,000 feet when adjacent areas not planned for immediate development
  • At all street intersections on divided thoroughfares, with left-turn lanes
  • At non-residential driveways based on min. spacing requirements and a traffic

study

  • Min. spacing between intersection and median opening – 400 to 480 feet
  • Min. spacing between median openings without left-turn lanes – 300 to 350 feet
slide-13
SLIDE 13

10

Planned Improvements Planned Improvements

R tl C l t d

  • Recently Completed
  • Intersection improvements at Cartwright, Lexington, and SH 6
  • Under Construction
  • Traffic signal @ Township Lane
  • Planned Improvements (Schedule TBD)
  • City wide ITS Improvements
  • Upgrade existing signal equipment
  • Build Traffic Management Center

FM 1092/Murphy Road Access Management Study

Planned Improvements (Contd..) Planned Improvements (Contd..)

Pl d R d I t (TIP & RTP)

  • Planned Roadway Improvements (TIP & RTP)
  • From US 90A to SH 6 (Year 2015): Reconstruction to six-lane divided curb

and gutter roadway with closed storm drains, cross-drainage culverts, and bridge widening

  • From Cartwright Road to SH 6 (Year 2016): Widening to eight-lanes
  • From Lexington Boulevard to Cartwright Road (Year 2017): Widening to

eight-lanes

FM 1092/Murphy Road Access Management Study

slide-14
SLIDE 14

11

Crash Analysis Crash Analysis

C h S

  • Crash Summary
  • Additional Data
  • Crashes involving vehicle run off the roadway = 7

Year Number of Crashes Crashes per 100 Million Vehicle Miles Travelled Total Injuries Total Fatalities 2008 82 241.6 31 2009 85 287.5 21 1 2010 116 378.3 33 Source: City of Missouri City FM 1092/Murphy Road Access Management Study

  • Crashes involving vehicle run off the roadway = 7
  • Crashes involving vehicle hit Pedestrian/Bicyclist = 2
  • 2009 Statewide traffic crash rates (Per 100 Million Vehicle Miles Travelled)
  • Urban Farm-to-Market roads = 224.75
  • Urban four or more lanes, divided = 114.65

Traffic Simulation Analysis Traffic Simulation Analysis

SYNCHRO ft l d i li d i t ti

  • SYNCHRO software - analyzed signalized intersections
  • Input
  • Lane configuration, turning movement counts, signal timing

FM 1092 AM Peak Hour LOS & Delay ‐ With Four Lanes Intersection Name 2011 2025 2035 LOS Delay 1 LOS Delay 1 LOS Delay 1 1 SH 6 @ FM 1092 D 43.1 F 113.0 F 189.7 2 Hampton Dr. @ FM 1092 C 22.2 E 70.3 F 131.0 3 Plantation Settlement Ln. @ FM 1092 B 19.7 C 27.2 C 34.5 4 El D d Bl d @ FM 1092 A 8 0 B 13 9 D 51 9

FM 1092/Murphy Road Access Management Study

4 El Dorado Blvd. @ FM 1092 A 8.0 B 13.9 D 51.9 5 Cartwright Rd. @ 1092 D 47.8 E 78.2 F 113.8 6 5th St. @ FM 1092 A 9.5 B 13.5 C 25.8 7 Lexington Blvd. @ FM 1092 D 53.1 F 126.0 F 182.0 8 Dove Country Dr. @ FM 1092 A 9.8 B 18.8 D 46.0 LOS ‐ Level of Service

1 Delay is presented in seconds per vehicle

slide-15
SLIDE 15

12

Traffic Simulation Analysis (Contd..) Traffic Simulation Analysis (Contd..)

FM 1092 PM Peak Hour LOS & Delay ‐ With Four Lanes Intersection Name 2011 2025 2035 LOS Delay 1 LOS Delay 1 LOS Delay 1 1 SH 6 @ FM 1092 F 106.1 F 231.0 F 317.7 2 Hampton Dr. @ FM 1092 C 21.0 D 42.7 E 75.4 3 Plantation Settlement Ln. @ FM 1092 B 11.3 B 16.3 D 43.0 4 El Dorado Blvd. @ FM 1092 B 12.3 C 20.5 E 61.7 5 Cartwright Rd. @ 1092 E 58.2 F 95.1 F 141.4 6 5th St. @ FM 1092 C 20.8 D 35.4 E 75.5 7 Lexington Blvd. @ FM 1092 D 48.1 F 102.0 F 147.8

FM 1092/Murphy Road Access Management Study

8 Dove Country Dr. @ FM 1092 A 10.0 C 26.4 E 69.4 LOS ‐ Level of Service

1 Delay is presented in seconds per vehicle

Traffic Simulation Analysis (Contd..) Traffic Simulation Analysis (Contd..)

FM 1092 AM Peak Hour LOS & Delay ‐ With Six Lanes Intersection Name 2011 2025 2035 LOS Delay 1 LOS Delay 1 LOS Delay 1 1 SH 6 @ FM 1092 D 43.1 E 77.9 F 128.1 2 Hampton Dr. @ FM 1092 C 22.2 C 25.6 D 36.9 3 Plantation Settlement Ln. @ FM 1092 B 19.7 C 26.8 C 33.2 4 El Dorado Blvd. @ FM 1092 A 8.0 A 7.8 B 10.7 5 Cartwright Rd. @ 1092 D 47.8 F 81.0 F 117.5 6 5th St. @ FM 1092 A 9.5 A 9.6 B 12.0 7 Lexington Blvd. @ FM 1092 D 53.1 E 69.2 F 96.4 8 Dove Country Dr. @ FM 1092 A 9.8 B 10.1 B 12.3 LOS ‐ Level of Service

1 Delay is presented in seconds per vehicle

FM 1092 PM Peak Hour LOS & Delay ‐ With Six Lanes Intersection Name 2011 2025 2035 LOS Delay 1 LOS Delay 1 LOS Delay 1 1 SH 6 @ FM 1092 F 106 1 F 207 2 F 286 2

FM 1092/Murphy Road Access Management Study

1 SH 6 @ FM 1092 F 106.1 F 207.2 F 286.2 2 Hampton Dr. @ FM 1092 C 21.0 C 22.3 C 28.9 3 Plantation Settlement Ln. @ FM 1092 B 11.3 B 11.0 B 12.6 4 El Dorado Blvd. @ FM 1092 B 12.3 A 8.1 B 11.1 5 Cartwright Rd. @ 1092 E 58.2 F 99.1 F 145.4 6 5th St. @ FM 1092 C 20.8 C 23.4 C 34.0 7 Lexington Blvd. @ FM 1092 D 48.1 D 51.4 E 71.0 8 Dove Country Dr. @ FM 1092 A 10.0 A 9.2 B 11.6 LOS ‐ Level of Service

1 Delay is presented in seconds per vehicle

slide-16
SLIDE 16

13

Pedestrian/Bicycle/Transit Analysis Pedestrian/Bicycle/Transit Analysis

L k f f iliti

  • Lack of facilities

FM 1092/Murphy Road Access Management Study

Land Use & Zoning Analysis Land Use & Zoning Analysis

St i t t C t i ht

  • Strip center at Cartwright
  • Vacant tracts in the mid corridor vicinity

FM 1092/Murphy Road Access Management Study

slide-17
SLIDE 17

14

Preliminary Findings Preliminary Findings

S f t i h l

  • Safety in school zones
  • Crash rate higher than Statewide average
  • 5th Street skewed intersection
  • Increase in traffic volumes/congestion
  • Disconnected sidewalk segments
  • Prevent access to main activity areas
  • Corridor width, traffic volumes and vehicular speeds
  • Inhibit cross-corridor pedestrian movement
  • Lack of pedestrian bridges and intersecting sidewalks along the Oyster Creek trail
  • Limits its use as an effective off street pedestrian route

FM 1092/Murphy Road Access Management Study

  • Limits its use as an effective off-street pedestrian route
  • Missing pedestrian features at signalized intersections
  • Only one Transit facility
  • Strip center at Cartwright is not operating at full potential
  • Needs to be repositioned as a neighborhood shopping/activity center
  • Vacant tracts

Preliminary Recommendations Preliminary Recommendations

P d R d ti

  • Proposed Recommendations
  • Raised median, with planned median openings
  • Full access - at street intersection or approximately 1,320 feet
  • Directional access - at approximately 660 feet
  • Curb and gutter with closed storm drainage
  • Roadway widening
  • Signal timing optimization
  • New traffic signals
  • Turn lanes at intersections
  • Re align 5th Street to eliminate skew

FM 1092/Murphy Road Access Management Study

  • Re-align 5th Street to eliminate skew
  • Driveway consolidation/relocation
  • Right-turn lanes at major driveways
  • Pedestrian/Bicycle path
  • Pedestrian facilities at Hampton and Dove Country intersections
  • Countdown pedestrian facilities at all signalized intersections
slide-18
SLIDE 18

15

Preliminary Recommendations (Contd..) Preliminary Recommendations (Contd..)

P d R d ti

  • Proposed Recommendations
  • Connect the west side of the corridor to school property via a pedestrian

underpass and bridges

  • Position the creek trail as a main pedestrian spine (or loop)
  • Requires new pedestrian bridges and trail spurs along the south/east

creek bank

  • Expand the area trail network and sidewalk system using existing easements

and linear features

  • Signature entry feature at the culvert crossing on the north end of the corridor
  • Similar to State Highway 6

FM 1092/Murphy Road Access Management Study

  • Similar to State Highway 6
  • Transit opportunities
  • Walkable neighborhood center on the west side of Cartwright intersection
  • Access controlled planned neighborhood development on vacant tracts in the

mid-corridor vicinity

Preliminary Recommendations (Contd..) Preliminary Recommendations (Contd..)

FM 1092/Murphy Road Access Management Study

slide-19
SLIDE 19

16

Preliminary Recommendations (Contd..) Preliminary Recommendations (Contd..)

FM 1092/Murphy Road Access Management Study

Preliminary Recommendations (Contd..) Preliminary Recommendations (Contd..)

Di i l i ith di d ti

  • Discuss aerial image with median recommendations

FM 1092/Murphy Road Access Management Study

slide-20
SLIDE 20

17

Next Steps Next Steps

St k h ld M ti

  • Stakeholder Meeting
  • Steering Committee and Stakeholders meeting minutes
  • Incorporate Steering Committee and Stakeholders feedback
  • Finalize analysis
  • Public Meeting

FM 1092/Murphy Road Access Management Study

Questions?

FM 1092/Murphy Road Access Management Study

slide-21
SLIDE 21

FM 1092/Murphy Road Access Management Plan Steering Committee Meeting #2  July 26, 2011 10:00 a.m. – 11:30 a.m.

Steering Committee Meeting Sign-in, Nov. 18, 2009ring Committee Meeting Sign-in, Nov. 18, 2009

Page | 1

Name Position Company Phone Email Check Beeler, R. Police City of Missouri City P.D. 281.403.8700 rbeeler@missouricitytx.gov Davis, David Transportation Director Fort Bend ISD 281.682.9841 David.davis@fortbendisd.com Francisco, Manny Texas Department of Transportation 713.802.5250 Manny.francisco@txdot.gov

Hunt, Jim Area Engineer Texas Department of Transportation 281.238.7900 Jim.hunt@txdot.gov Isidienu, Brendan Texas Department of Transportation Kelley, Jessica Project Manager City of Missouri City 281.403.8970 jkelley@missouricitytx.gov

Luera, S. Police City of Missouri City P.D. 281.403.8700 sluera@missouricitytx.gov Marvin, Valerie CIP Administrator City of Missouri City 281.403.8578 vmarvin@missouricitytx.gov

McCreight, Catherine TxDOT Catherine.mccreight@txdot.gov Milner, Travis Texas Department of Transportation Travis.Milner@txdot.gov

slide-22
SLIDE 22

FM 1092/Murphy Road Access Management Plan Steering Committee Meeting #2  July 26, 2011 10:00 a.m. – 11:30 a.m.

Steering Committee Meeting Sign-in, Nov. 18, 2009ring Committee Meeting Sign-in, Nov. 18, 2009

Page | 2

Name Position Company Phone Email Check Ponce de Leon, Jaime

  • Asst. Fire Chief

City of Missouri City 281.403.4300 jponcedeleon@missouricitytx.gov

Upadhyay, Sanjay G. Advanced Transportation Planning Texas Department of Transportation 713.802.5302 Sanjay.upadhyay@txdot.gov Valiante, Sharon

  • Asst. Director of Public

Works City of Missouri City 281.261.4338 svaliante@missouricitytx.gov

Williams, Dwayne Police Captain City of Missouri City 281.403.8745 dwilliams@missouricitytx.gov

H-GAC & Consultant Team

Emshoff, Cristin Houston-Galveston Area Council 713.993.2462 Cristin.emshoff@h-gac.com

Flisram, Greg Kendig Keast Collaborative 281.242.2960 flisram@sbcglobal.net

Gilbert, Nicole The Lentz Group 713.864.2623 nicoleg@lentzgroup.com

Govindu, Meghavardhan Gunda Corporation 713.541.3530 mgovindu@gundacorp.com

Grubbs, Lori Gunda Corporation 713.541.3530 lgrubbs@gundacorp.com

slide-23
SLIDE 23

FM 1092/Murphy Road Access Management Plan Steering Committee Meeting #2  July 26, 2011 10:00 a.m. – 11:30 a.m.

Steering Committee Meeting Sign-in, Nov. 18, 2009ring Committee Meeting Sign-in, Nov. 18, 2009

Page | 3

Name Position Company Phone Email Check Gunda, Ramesh Gunda Corporation 713.541.3530 rgunda@gundacorp.com

Henshall, Ruth The Lentz Group 713.864.2623 ruthh@lentzgroup.com Mineo, Kevin PB Mineo@pbworld.com

Mitchell, Gary Kendig Keast Collaborative 281.242.2960 gary@kendigkeast.com Mitteco, Gina Houston-Galveston Area Council Gina.mitteco@h-gac.com Probst, Liz Kendig Keast Collaborative 281.242.2960 liz@kendigkeast.com

Smart, Russell PB 281.589.5942 smart@pbworld.com

Strobel, Roland Houston-Galveston Area Council 713.993.4538 Roland.strobel@h-gac.com

Tobin, Bill Houston-Galveston Area Council Bill.tobin@h-gac.com

Willhite, Christy Houston-Galveston Area Council 713.627.3200 christy.willhite@h-gac.com