steering committee meeting
play

Steering Committee Meeting July 7, 2011 Terry Egger and Jamie - PowerPoint PPT Presentation

Steering Committee Meeting July 7, 2011 Terry Egger and Jamie Ireland Co-Chairs Welcome and Opening Remarks Terrance Egger and Jamie Ireland III Meeting Objectives Steering Committee Co-Chairs Updates since September 8, 2010 Meeting


  1. Steering Committee Meeting July 7, 2011 Terry Egger and Jamie Ireland Co-Chairs

  2. Welcome and Opening Remarks Terrance Egger and Jamie Ireland III Meeting Objectives Steering Committee Co-Chairs • Updates since September 8, 2010 Meeting • Discussion of a Recommended Preferred Alternative • Preparation for July Public Meetings • Next Steps to Complete Planning Phase

  3. Project Updates Terri Hamilton Brown, GCP • New Steering Committee Members – Myron Pakush, ODOT - District 12, Director Agenda – Ed Fitzgerald, Cuyahoga County Executive • US EPA Brownfield Planning Grant – Kim Scott, City Planning Commission • Grants awarded by George Gund, Cleveland and Mather Foundations • Economic Impact Study – Michael Cantor, Allegro Realty Advisors

  4. Transportation Planning Update Matt Wahl, HNTB Agenda • Step 5 – Summary of Alternatives and CSS Activities • Step 6 (Current Activities) – Reviewed Community Input and Conducted Additional Stakeholder Meetings – Revised Typical Section – Refined and Evaluated Alternatives • Discuss Recommended Preferred Alternative

  5. Next Steps and Project Schedule • Update Travel Demand Modeling Agenda • Further Refine Preferred Alternative • Continue Corridor CSS/Design Planning • Preparation for July Public Meetings • Integrate all Planning Efforts – Community / Brownfield Land Use Studies – Economic Impact and Traffic Studies – HNTB / ODOT Environmental Impact Study (EIS)

  6. Cleveland Opportunity Corridor Brownfields Area-Wide Planning Pilot Program (COC BAWPPP) A Planning Process for Sustainable Development Update for the OC Steering Committee July 7, 2011 Presented by Kim Scott, City Planner Cleveland Planning Commission

  7. Goals COC BAWPPP  Educate residents and business owners about brownfields  Establish a priority list of sites for assessment and remediation  Outline the steps and resources needed to address remediation issues  Develop a Community Supported Brownfield Area-Wide Plan

  8. Map of Pilot Area

  9. Project Partners  Kinsman & Lower Buckeye Neighborhood Residents  City of Cleveland: City Planning & Economic Development  Opportunity Corridor Steering Committee / GCP  City Architecture with Partners Environmental  Burten, Bell, Carr Development, Inc.  Buckeye Area Development Corporation  CUDC, NPI & ParkWorks  Environmental Health Watch  Northeast Ohio Regional Sewer District  Ohio State University Extension Program  U.S. Environmental Protection Agency  And the list is growing

  10. What When Why Wednesday, July 20 th Community Meeting - 1 To introduce BAWPPP grant to the community, receive 6 – 8 pm feedback about areas of concern in the Kinsman & Lower Buckeye neighborhoods Wednesday, August 3 rd BAWPPP Design Facilitate a hands-on workshop soliciting the Charrette #1 2 – 4 pm community’s sustainable redevelopment ideas for brownfields in Development District 2 Wednesday, August 10 th BAWPPP Design Facilitate a hands-on workshop soliciting the Charrette #2 8 – 10 am community’s sustainable redevelopment ideas for brownfields in Development District 5 Wednesday, August 10 th BAWPPP Design Facilitate a hands-on workshop soliciting the Charrette #3 6 – 8 pm community’s sustainable redevelopment ideas for brownfields in Development District 3 Community Meeting - 2 Wednesday, September 21 st To present initial area-wide plan and receive 6 – 8 pm community input and feedback Wednesday, October 19 th Advisory Committee To discuss outcome of Community Meeting #2 and Meeting - 2 2 – 3:30 pm refine ideas for Community Meeting #3 Community Meeting - 3 Wednesday, November 16 th To present final area-wide plan, outline next steps for 6 – 8 pm plan implementation and receive plan feedback Wednesday, January 11 th Advisory Committee To discuss outcome of final area-wide plan and Meeting - 3 2 – 3:30 implementation

  11. Allegro Realty Advisors Highest and “Most Appropriate” Use Model: Scope of Services:  Phase I — High-level Land Use Analysis  Phase II — Economic Impact Analysis

  12. • Need Elements OC Project – Improve system linkage Overview – Improve mobility – Support planned economic development • Goals and Objectives – Public transportation – Pedestrian and bike facilities

  13. Steps 1-4 Steps 1-4 of ODOT PDP No-Build Alternative Alternative 1 Alternative 2 Alternative 3 Alternative 4 14

  14. Step 5 87 8 87 87 Study Area NORTH

  15. Alternate C Alternate B Alternate A West Central East

  16. Summary of CSS activities and feedback on priorities Step 5 Context – Roadway elements Sensitive Solutions – Roadside elements – Community elements – Vegetative elements – Landform elements – Corridor theme

  17. Roadway Elements: Step 5 • Enhanced bridges Context Sensitive • Ornamental roadway lighting Solutions • Ornamental railings and fencing Some elements Roadside Elements: will require additional • Pedestrian amenities funding • Ornamental pedestrian and sources access lighting • Bike facilities

  18. Community Elements: Step 5 • Plaza/Community areas Context Sensitive • Stormwater runoff sustainable Solutions management Some elements Vegetation Elements: will require additional • Street trees funding sources • Green/sustainable street program • Planted roadway median

  19. Landform Elements: Step 5 • Naturalistic approach to grading Context Sensitive Solutions Some elements Corridor design character and Theme: will require • Community Inspired Theme additional funding sources

  20. Step 6 Alternatives and Recommendations

  21. • Revised Typical Section Step 6 – Community input Activities – Traffic Analysis • Further developed alignments • Evaluated alternates • Established a Recommended Preferred Alternative

  22. Step 5 Typical Section – Local street – Multipurpose path – 35 mph speed limit – Landscaping – Sidewalk – Lighting

  23. Step 6 Typical Sections The number of lanes required may change once new traffic volumes are developed and analyzed

  24. Typical Sections The number of lanes required may change once new traffic volumes are developed and analyzed

  25. Alternate A WEST SECTION ALTERNATES At Grade Intersection Alternate B Grade Separated Alternate C Quadrant Roadway

  26. West Section – E.55 th Street to E.75 th Street – At Grade Alternate A Alternate is not feasible due to geometric constraints at I-490/I-77 ramps

  27. West Section – E.55 th Street to E.75 th Street – Quadrant Alternate C

  28. Quadrant Roadway Example

  29. Alternate C Quadrant Roadway West Alternate Potential Hazardous Material Sites Impacted 3 Evaluation Historic/Parkland Impacts (Acres) 0 Residential Displacements (Units) 45 (71) to 48 (76) Church Displacements (Number) 0 Commercial Business (Relocations) 4 (3) Public /Community/City Support Preferred Yes Recommended as preferred alternative Impacts listed are based on a 4-lane roadway. The number of lanes required may change once the travel demand study is completed and new traffic volumes are developed and analyzed

  30. Alternate A CENTRAL SECTION ALTERNATES Discontinuous Woodland Alternate B Continuous Woodland Alternate C Eastern Alignment

  31. Central Section – E.75 th Street to Quincy Avenue (Step 5) A X X X X X X X X X X X Ken Johnson Rec Center X X X X X X X X X

  32. Central Section – E.75 th Street to Quincy Avenue (Step 6) A X X X X X X X X X X Ken Johnson Rec Center X X X X X X X X X

  33. Central Section – E.75 th Street to Quincy Avenue (Step 5) B X X X X X X X X Ken Johnson Rec Center

  34. Central Section – E.75 th Street to Quincy Avenue (Step 6) B X X X X X X X X X X X X X X X X Ken Johnson Rec Center

  35. Alternate A Alternate B Discontinuous Woodland Continuous Woodland Central Alternates 7 12 Potential Hazardous Material Sites Impacted Evaluation 0 0 Historic/Parkland Impacts (Acres) Residential Displacements (Units) 6 (10) 11 (11) Church Displacements (Number) 1 1 Commercial Business (Relocations) 12 (5) 16 (7) Public /Community/City Support Less Preferred Preferred Yes Recommended as preferred alternative No Impacts listed are based on a 4-lane roadway. The number of lanes required may change once the travel demand study is completed and new traffic volumes are developed and analyzed

  36. Alternate A EAST SECTION ALTERNATES Western Widening RTA Street/Station Modifications Alternate B Symmetric Widening Alternate C Eastern Widening

  37. Alternate C Eastern Widening East Alternate Potential Hazardous Material Sites Impacted 3 Evaluation Historic/Parkland Impacts (Acres) 1 (possible) Residential Displacements (Units) 4 (8) Church Displacements (Number) 0 Commercial Business (Relocations) 3 (3) Public /Community/City Support Preferred Recommended as preferred alternative Yes Impacts listed are based on a 4-lane roadway. The number of lanes required may change once the travel demand study is completed and new traffic volumes are developed and analyzed

  38. Alternate C Alternate B Alternate A West Central East

  39. Step 6 Recommended Preferred Alternative 87 8

  40. Step 6 Recommended Preferred Alternative 87 8

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend