Welcome! Please sign in on your mobile device: http://communitymeeting.ocps.net/ Sunrise Elementary School 100% Community Meeting February 20, 2018 Superintendent Dr. Barbara Jenkins Chief Facilities Officer John Morris
Orange County Public Schools Sunrise Elementary School Meeting Agenda February 20, 2017 6:00 pm • Welcome – School Board Member: Daryl Flynn • Introductions – Lauren Roth / Facilities Communications • Project Update – Architect: HuntonBrady Architects Construction Manager: Core Construction • Questions and Answers • Adjournment 1
Orange County Public Schools Existing Campus Data Site Area: 15.7 acres NORTH Permanent Capacity: 622 students Building Area: 95,900 sf Bloodhound St. Existing Parking: 90 spaces 2 3 1 4 8 6 5 7 BUILDING 1 – ADMIN/MEDIA BUILDING 2 – CLASSROOM BUILDING 3 – CLASSROOM BUILDING 4 – CAFETERIA BUILDING 5 – CLASSROOM BUILDING 6 – CLASSROOM BUILDING 7 - STORAGE BUILDING 8 - CEP Sunrise Elementary School- Existing Aerial Site Plan 2
Orange County Public Schools Proposed Campus Data Existing Campus Data Original Permanent Capacity = 622 Permanent Capacity = 626 Modular Capacity 0 = 0 Future Modular Capacity = 12 Total Capacity = 622 Total Permanent SS Capacity = 626 NORTH Parking Capacity: 90 spaces Bike Racks Bus Loop BUILDING 02 BUILDING 03 EMERGENCY ACCESS ROAD Retention Parent Drop-off PORTABLES BUILDING 01 BUILDING 04 CEP Marquee BUILDING 06 BUILDING 05 Sign PLAYCOURTS TOT YOUTH NORTH LOT LOT Sunrise Elementary School- New Site Plan 3
Example Primary Classroom 10
Example Resource Room 11
Orange County Public Schools Sunrise Elementary School 12
Example Cafeteria and Multi-Purpose Room 13
Example Play Equipment 14
Orange County Public Schools Other School Improvements - Repair roof, gutters and downspouts as needed - Replace playground surface and structures as needed - Digital LED Sign - Upgrade restroom fixtures and accessories as needed - Replace carpet and vinyl flooring as needed - Repair or Replace ceiling tiles as needed - Repair cabinets/countertops as needed - Replace acoustical treatments as needed - Reduce sound transfer between classrooms as needed - Upgrade HVAC system - Upgrade Fire Alarm system as needed - Upgrade school / classroom / media technology Sunrise Elementary School- Improvements 15
Orange County Public Schools Sunrise Elementary School- Schedule 16
Orange County Public Schools SUNRISE PHASING PLAN PHASE I MOBILIZE + SITE June 2018 – August 2018 BLDG. 8 & 3 August 2018 – November 2018 PHASE II BLDG. 5 November 2018 – February 2019 NORTH PHASE III BLDG. 6 February 2019 – May 2019 PHASE IV BLDG. 2 + SITE May 2019 – August 2019 PHASE V BLDG. 1 & 4 May 2019 – August 2019 PHASING PORTABLES BUILDING 02 BUILDING 03 EMERGENCY ACCESS ROAD BUILDING 01 BUILDING 04 CEP BUILDING 06 BUILDING 05 PLAYCOURTS TOT YOUTH LOT LOT Sunrise Elementary School- New Site Plan 17
Orange County Public Schools SUNRISE PHASING PLAN PHASE I MOBILIZE + SITE June 2018 – August 2018 BLDG. 8 & 3 August 2018 – November 2018 PHASE II BLDG. 5 November 2018 – February 2019 NORTH PHASE III BLDG. 6 February 2019 – May 2019 PHASE IV BLDG. 2 + SITE May 2019 – August 2019 PHASE V BLDG. 1 & 4 May 2019 – August 2019 PHASING PORTABLES BUILDING 02 BUILDING 03 EMERGENCY ACCESS ROAD BUILDING 01 BUILDING 04 CEP BUILDING 06 BUILDING 05 PLAYCOURTS NORTH TOT YOUTH LOT LOT Sunrise Elementary School- New Site Plan 18
Orange County Public Schools SUNRISE PHASING PLAN PHASE I MOBILIZE + SITE June 2018 – August 2018 BLDG. 8 & 3 August 2018 – November 2018 PHASE II BLDG. 5 November 2018 – February 2019 NORTH PHASE III BLDG. 6 February 2019 – May 2019 PHASE IV BLDG. 2 + SITE May 2019 – August 2019 PHASE V BLDG. 1 & 4 May 2019 – August 2019 PHASING PORTABLES BUILDING 02 BUILDING 03 EMERGENCY ACCESS ROAD BUILDING 01 BUILDING 04 CEP BUILDING 06 BUILDING 05 PLAYCOURTS TOT YOUTH LOT LOT Sunrise Elementary School- New Site Plan 19
Orange County Public Schools SUNRISE PHASING PLAN PHASE I MOBILIZE + SITE June 2018 – August 2018 BLDG. 8 & 3 August 2018 – November 2018 PHASE II BLDG. 5 November 2018 – February 2019 NORTH PHASE III BLDG. 6 February 2019 – May 2019 PHASE IV BLDG. 2 + SITE May 2019 – August 2019 PHASE V BLDG. 1 & 4 May 2019 – August 2019 PHASING PORTABLES BUILDING 02 BUILDING 03 EMERGENCY ACCESS ROAD BUILDING 01 BUILDING 04 CEP BUILDING 06 BUILDING 05 PLAYCOURTS TOT YOUTH LOT LOT Sunrise Elementary School- New Site Plan 20
Orange County Public Schools SUNRISE PHASING PLAN PHASE I MOBILIZE + SITE June 2018 – August 2018 BLDG. 8 & 3 August 2018 – November 2018 PHASE II BLDG. 5 November 2018 – February 2019 NORTH PHASE III BLDG. 6 February 2019 – May 2019 PHASE IV BLDG. 2 + SITE May 2019 – August 2019 PHASE V BLDG. 1 & 4 May 2019 – August 2019 PHASING PORTABLES BUILDING 02 BUILDING 03 EMERGENCY ACCESS ROAD BUILDING 01 BUILDING 04 CEP BUILDING 06 BUILDING 05 PLAYCOURTS TOT YOUTH LOT LOT Sunrise Elementary School- New Site Plan 21
Orange County Public Schools Thank You! Thank you to the Orange County taxpayers, you make this construction possible. Sunrise Elementary School 22
Orange County Public Schools Questions? Sunrise Elementary School 23
Recommend
More recommend