odour improvement project mogden sewage treatment works
play

Odour Improvement Project Mogden Sewage Treatment Works Residents - PDF document

Odour Improvement Project Mogden Sewage Treatment Works Residents Liaison Meeting 26 September 2007 2 Odour Improvement Project Scope of work: Cover key parts of the treatment process, including: Inlet works (East and West


  1. Odour Improvement Project

  2. Mogden Sewage Treatment Works Residents’ Liaison Meeting 26 September 2007 2

  3. Odour Improvement Project � Scope of work: – Cover key parts of the treatment process, including: • Inlet works (East and West side of Mogden) • Primary settlement tanks (East side) • Two storm tanks (East Side) – Independent tests have been used to decide what areas of the site to cover – Install equipment to extract and treat the odorous air from the covered areas: • Two new odour control units (East and West side) • Designed to robustly comply with the requirements of the odour abatement notice. 3

  4. Agenda 17:15 Site walk-around 18:15 1. Apologies 2. Odour Improvement Project 3. Odour 4. Mosquitoes 5. Working for a cleaner Thames 6. Further points raised by residents 7. Communications 8. Any other business and date of next meeting 20:15 Meeting Close 4

  5. Progress of Works 5

  6. East Works Progress AREA PROGRESS Inlet Penstocks 100% Screenhouse & Screens 90% Screenings Handling Plant 95% Grit Channels 70% Storm Weir 95% Grit Handling Plant 80% Storm Tanks 4 and 5 95% Circular PSTs (Decommission) 0% Rectangular SSTs 65% Odour Control Unit (Chemical) 100% 6

  7. Screenings Handling Plant 7

  8. CV Grit Channels 1 and 2 8

  9. Storm Weir 9

  10. Grit Handling Plant 10

  11. Storm Tank 5 11

  12. Secondary Settlement Tanks 2 & 3 12

  13. Secondary Settlement Tank 4 13

  14. Secondary Settlement Tank 1 14

  15. East Odour Control Unit 15

  16. West Works Progress AREA PROGRESS Chambers Upstream of Screens 100% Fine Screens 70% Cross Flow Grit Traps 95% Washpactors and Skip Loaders 100% Grit Handling Plant 70% Screw Pumps 100% Pre-Aeration Lanes 100% Odour Control Unit (Biological) 90% 16

  17. Cross Flow Grit Traps 17

  18. Pre-Aeration Lanes 18

  19. Noise Update � Noise attenuator installed on 17 May 2007 (pictured) � Significant noise reduction on site � Final noise survey to be undertaken tonight (26/09/07), commencing at 9:00pm 19

  20. Operation of Mogden- Update � Informative email notifications sent to residents: � 17 Proactive Notifications: � Odour Improvement project works (x12) � Site Maintenance works (x5) � 2 Reactive Notifications: � Interruption to Power Supply � Channel Cleaning 20

  21. 21 Complaints Received at Mogden 100 10 20 30 40 50 60 70 80 90 0 Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 N.B Figures reported to 31 August 07 Feb-07 Mar-07 Odour Odour and mosquitoes Mosquitoes Apr-07 May-07 Jun-07 Jul-07 Aug-07

  22. Mosquitoes 22

  23. Surveying and controlling Mosquitoes at Mogden � Strict year-round programme to survey and control mosquitoes � Summer surveying and treatment programme began in mid-April 07: � Weekly Surveys � Target Summer breeding sites � Mosquito treatment: � Less than two days after the weekly survey � Controls regular breeding sites & ad hoc sites as identified in the surveys � Spraying near standing water 23

  24. Methods of Mosquito control at Mogden � Physical � Site housekeeping- Removing Mosquito breeding sites � Biological � Spraying Mosquito larvae with bacteria � Mechanical � Using ultraviolet insect traps � Chemical � Controlling adult Mosquitoes with pesticides 24

  25. Number of sites inspected for Mosquitoes at Mogden 250 200 150 2003 2004 2005 2006 100 2007 50 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Week 25

  26. Percentage of sites surveyed found to contain Mosquito activity 80 70 60 50 2003 2004 % 40 2005 2006 2007 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Week 26

  27. Number of sites where larvae have been found 35 30 25 2003 20 2004 2005 2006 15 2007 10 5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Week 27

  28. Number of sites where Adult Mosquitoes have been found 14 12 10 2003 8 2004 2005 2006 6 2007 4 2 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Week 28

  29. Mosquito Project 2007 � Project Scope: � Target the main over-wintering sites: � Digester galleries, aeration galleries, main pumping station drywell, power house basement & pumping stations 4 & 5 � Project aim: � To physically alter sites to reduce the number of places where Mosquitoes can breed and to make control work easier � Project commenced in March 2007 29

  30. Working for a Cleaner Thames 30

  31. Working for a cleaner Thames- Update � Proposed site improvement works: � Increase the amount of flow that can be fully treated � Less use of storm tanks � Includes new covered inlet works, covered primary tanks and new aeration lanes � Odour control of the new works � Reduce the likelihood of overflows from the works to the River Thames � To help boost oxygen levels in the tidal Thames � Improving the water quality and the habitants for aquatic life 31

  32. Preferred Solution for Mogden Area of development. Other land in applicants ownership. Buildings. Site roads / hardstanding. Above ground structures. New & re-profiled embankment. Soft landscaped areas. Earth retaining wall. 32

  33. Working for a cleaner Thames- Update � Timescales: � Planning Application: TBC- Delay due to finalisation of details � Proposed construction date: Spring/Summer 2008 � Complete and operational: Spring/Summer 2012 � Public displays were held in Isleworth Public Library on the 21 st , 22 nd and 24 th of May 2007: � Well received by local residents and businesses � Questions answered by Thames Water representatives � Comments Book completed 33

  34. Further points raised by residents 34

  35. Communication 35

  36. Communication � E-mail notifications: � Informing residents of possible increase in odour � Mogden newsletter: � Updating residents with progress on the odour improvement project � To be distributed by end September/Beginning October 2007 � Mosquito Campaign: � ‘Help control mosquitoes in your area’ 36

  37. Communication � Contact us about Mogden: � Via the customer centre: 0845 9200 800 � Through our website: www.thameswater.co.uk/mogden � By post: Thames Water, PO Box 436, Swindon, SN38 1TU � Visit our website: � Categorised ‘Answers to your questions’ webpage � Mogden weekly site log webpage (includes regular updates of the Odour Improvement project) 37

  38. Thank You 38

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend