Odour Improvement Project Mogden Sewage Treatment Works Residents - - PDF document

odour improvement project mogden sewage treatment works
SMART_READER_LITE
LIVE PREVIEW

Odour Improvement Project Mogden Sewage Treatment Works Residents - - PDF document

Odour Improvement Project Mogden Sewage Treatment Works Residents Liaison Meeting 26 September 2007 2 Odour Improvement Project Scope of work: Cover key parts of the treatment process, including: Inlet works (East and West


slide-1
SLIDE 1

Odour Improvement Project

slide-2
SLIDE 2

2

Mogden Sewage Treatment Works

Residents’ Liaison Meeting 26 September 2007

slide-3
SLIDE 3

3

Odour Improvement Project

  • Scope of work:

– Cover key parts of the treatment process, including:

  • Inlet works (East and West side of Mogden)
  • Primary settlement tanks (East side)
  • Two storm tanks (East Side)

– Independent tests have been used to decide what areas of the site to cover – Install equipment to extract and treat the odorous air from the covered areas:

  • Two new odour control units (East and West side)
  • Designed to robustly comply with the requirements
  • f the odour abatement notice.
slide-4
SLIDE 4

4

Agenda

17:15 Site walk-around 18:15

1.

Apologies

2.

Odour Improvement Project

3.

Odour

4.

Mosquitoes

5.

Working for a cleaner Thames

6.

Further points raised by residents

7.

Communications

8.

Any other business and date of next meeting 20:15 Meeting Close

slide-5
SLIDE 5

5

Progress of Works

slide-6
SLIDE 6

6

East Works Progress

AREA PROGRESS Inlet Penstocks 100% Screenhouse & Screens 90% Screenings Handling Plant 95% Grit Channels 70% Storm Weir 95% Grit Handling Plant 80% Storm Tanks 4 and 5 95% Circular PSTs (Decommission) 0% Rectangular SSTs 65% Odour Control Unit (Chemical) 100%

slide-7
SLIDE 7

7

Screenings Handling Plant

slide-8
SLIDE 8

8

CV Grit Channels 1 and 2

slide-9
SLIDE 9

9

Storm Weir

slide-10
SLIDE 10

10

Grit Handling Plant

slide-11
SLIDE 11

11

Storm Tank 5

slide-12
SLIDE 12

12

Secondary Settlement Tanks 2 & 3

slide-13
SLIDE 13

13

Secondary Settlement Tank 4

slide-14
SLIDE 14

14

Secondary Settlement Tank 1

slide-15
SLIDE 15

15

East Odour Control Unit

slide-16
SLIDE 16

16

West Works Progress

AREA PROGRESS Chambers Upstream of Screens 100% Fine Screens 70% Cross Flow Grit Traps 95% Washpactors and Skip Loaders 100% Grit Handling Plant 70% Screw Pumps 100% Pre-Aeration Lanes 100% Odour Control Unit (Biological) 90%

slide-17
SLIDE 17

17

Cross Flow Grit Traps

slide-18
SLIDE 18

18

Pre-Aeration Lanes

slide-19
SLIDE 19

19

Noise Update

Noise attenuator installed

  • n 17 May 2007 (pictured)

Significant noise reduction

  • n site

Final noise survey to be

undertaken tonight (26/09/07), commencing at 9:00pm

slide-20
SLIDE 20

20

Operation of Mogden- Update

Informative email notifications sent to residents: 17 Proactive Notifications: Odour Improvement project works (x12) Site Maintenance works (x5) 2 Reactive Notifications: Interruption to Power Supply Channel Cleaning

slide-21
SLIDE 21

21

Complaints Received at Mogden

10 20 30 40 50 60 70 80 90 100 Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06 Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 Nov-06 Dec-06 Jan-07 Feb-07 Mar-07 Apr-07 May-07 Jun-07 Jul-07 Aug-07

Mosquitoes Odour and mosquitoes Odour

N.B Figures reported to 31 August 07

slide-22
SLIDE 22

22

Mosquitoes

slide-23
SLIDE 23

23

Surveying and controlling Mosquitoes at Mogden

Strict year-round programme to survey and control mosquitoes Summer surveying and treatment programme began in mid-April 07: Weekly Surveys Target Summer breeding sites Mosquito treatment: Less than two days after the weekly survey Controls regular breeding sites & ad hoc sites as identified in the

surveys

Spraying near standing water

slide-24
SLIDE 24

24

Methods of Mosquito control at Mogden

Physical Site housekeeping- Removing Mosquito breeding sites Biological Spraying Mosquito larvae with bacteria Mechanical Using ultraviolet insect traps Chemical Controlling adult Mosquitoes with pesticides

slide-25
SLIDE 25

25

Number of sites inspected for Mosquitoes at Mogden

50 100 150 200 250 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43

Week

2003 2004 2005 2006 2007

slide-26
SLIDE 26

26

Percentage of sites surveyed found to contain Mosquito activity

10 20 30 40 50 60 70 80 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Week % 2003 2004 2005 2006 2007

slide-27
SLIDE 27

27

Number of sites where larvae have been found

5 10 15 20 25 30 35 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Week 2003 2004 2005 2006 2007

slide-28
SLIDE 28

28

2 4 6 8 10 12 14 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 Week 2003 2004 2005 2006 2007

Number of sites where Adult Mosquitoes have been found

slide-29
SLIDE 29

29

Mosquito Project 2007

Project Scope: Target the main over-wintering sites: Digester galleries, aeration galleries, main pumping station drywell, power

house basement & pumping stations 4 & 5

Project aim: To physically alter sites to reduce the number of places where

Mosquitoes can breed and to make control work easier

Project commenced in March 2007

slide-30
SLIDE 30

30

Working for a Cleaner Thames

slide-31
SLIDE 31

31

Working for a cleaner Thames- Update

Proposed site improvement works: Increase the amount of flow that can be fully treated Less use of storm tanks Includes new covered inlet works, covered primary tanks and

new aeration lanes

Odour control of the new works Reduce the likelihood of overflows from the works to the River

Thames

To help boost oxygen levels in the tidal Thames Improving the water quality and the habitants for aquatic life

slide-32
SLIDE 32

32

Preferred Solution for Mogden

Area of development. Other land in applicants ownership. Buildings. Site roads / hardstanding. Above ground structures. New & re-profiled embankment. Soft landscaped areas. Earth retaining wall.

slide-33
SLIDE 33

33

Working for a cleaner Thames- Update

Timescales: Planning Application: TBC- Delay due to finalisation of details Proposed construction date: Spring/Summer 2008 Complete and operational: Spring/Summer 2012 Public displays were held in Isleworth Public Library on the 21st,

22nd and 24th of May 2007:

Well received by local residents and businesses Questions answered by Thames Water representatives Comments Book completed

slide-34
SLIDE 34

34

Further points raised by residents

slide-35
SLIDE 35

35

Communication

slide-36
SLIDE 36

36

Communication

E-mail notifications:

Informing residents of possible increase in odour

Mogden newsletter:

Updating residents with progress on the odour improvement project To be distributed by end September/Beginning October 2007

Mosquito Campaign:

‘Help control mosquitoes in your area’

slide-37
SLIDE 37

37

Communication

Contact us about Mogden: Via the customer centre: 0845 9200 800 Through our website:

www.thameswater.co.uk/mogden

By post: Thames Water, PO Box 436, Swindon,

SN38 1TU

Visit our website: Categorised ‘Answers to your questions’ webpage Mogden weekly site log webpage (includes regular

updates of the Odour Improvement project)

slide-38
SLIDE 38

38

Thank You